March 14, 2024
Elixir Energy Limited (“Elixir” or the “Company”) is pleased to provide an operations update on its 100% owned Grandis and Nomgon projects located in Queensland and Mongolia respectively.
HIGHLIGHTS
- Coiled tubing unit cleaning out Daydream-2 wellbore in preparation for DFITs
- Significant stimulation and testing program at Grandis on track for April through to June
- Nomgon Pilot Project continues reservoir de-pressurisation process
Grandis Project
A coiled tubing unit has recently been mobilised and is currently cleaning out the Daydream-2 cased wellbore.

This cleanout is a pre-cursor to the Diagnostic Formation Integrity Test (DFIT) program which will follow shortly thereafter. The results of this DFIT program will then be used to optimize the subsequent stimulation and flow testing phases of Daydream-2, which will run from April through to around June.
The detailed design of the stimulation and testing program has now been finalized, with a total of 6 zones to be stimulated. These zones cover ~47 metres of pay out a total of 245 metres (being the final sandstone net pay of 180 metres and coals of 65 metres) recorded in the Daydream 2 wellbore (19% of the total net interval). The sandstone net pay advised to the market on 14 December 2023 of 154 metres has been revised upwards following an external independent expert review.
The zones selected represent a cross-section of permeable sands, tight sands and coals. The total zones being tested in Daydream-2 are guided by the key principle of maximizing useful data acquisition from an appraisal well – that would then inform how future development wells would be designed.
In such future development wells, much greater pay would likely be stimulated and flowed. The results from the stimulation program in Daydream-2 will guide the targeting of further zones in future wells and can be extrapolated over the entire gas prone intervals.
The stimulation program, to be conducted by global leading contractor Halliburton, will be followed by a series of flow tests in May and June.
Nomgon Project
In conjunction with this intense program in Queensland, operations also continue at the Nomgon Pilot Project in Mongolia. In Mongolia, the current key objective is to continue to de-pressurise the gas- bearing coal reservoir through the ongoing pumping of water therefrom.
Recently one of the pilot wells, Nomgon-10, was worked over, with a larger downhole pump installed. Increased water rates have already been observed. Elixir’s engineers are actively managing the Pilot Plant to maximise water production and therefore accelerate the time to reach desorption pressure. Data analysis from the Nomgon field indicates that steady progress is being made in reducing the reservoir pressure required to reach the gas desorption pressure.
Click here for the full ASX Release
This article includes content from Elixir Energy, licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.
EXR:AU
INN Article Notification
The Conversation (0)
02 May 2024
Elixir Energy
Early-mover in natural gas exploration and appraisal in Australia and Mongolia.
Early-mover in natural gas exploration and appraisal in Australia and Mongolia. Keep Reading...
20 April
Oil Surges, Gold Slips as US Navy Seizes Iranian Ship Amid Ceasefire Collapse
Oil prices spiked more than 5 percent to start the week after the US Navy seized an Iranian cargo ship, casting severe doubt on peace deal prospects before the current ceasefire expires this week.West Texas Intermediate (WTI) crude futures jumped 5.4 percent to US$88.39 per barrel, while... Keep Reading...
20 April
QIMC to Begin Drilling DDH-26-03 April 21, 2026; Expands Depth to 900 Metres; DDH-26-02 Extension to 700 Metres Planned
Deeper drilling targets vertically stacked hydrogen-bearing intervals defined across Domains 4-6 of DDH-26-02 in Nova ScotiaQuebec Innovative Materials Corp. (CSE: QIMC,OTC:QIMCF) (OTCQB: QIMCF) (FSE: 7FJ) ("QIMC" or the "Company") is pleased to announce that DDH-26-03 at its Nova Scotia... Keep Reading...
20 April
Kinetiko Launches Rolling Cluster Development Strategy
Kinetiko Energy (KKO:AU) has announced Kinetiko Launches Rolling Cluster Development StrategyDownload the PDF here. Keep Reading...
17 April
Global Energy Markets Rethink Strategy as Strait of Hormuz Reopens
In a sudden diplomatic turn, Iran announced on Friday (April 17) that it would reopen the Strait of Hormuz, ending a nearly two month blockade that had crippled energy shipments from the Persian Gulf. The decision followed weeks of heightened military tensions and a brief but disruptive conflict... Keep Reading...
16 April
Trillion Energy Announces Independent Resource Evaluation
Highlights include 27.6 MMbbl 2C (unrisked) Contingent Oil Resource to Trillion on North Lead Discovery;
Trillion Energy International Inc. (CSE: TCF) (OTCQB: TRLEF) (FSE: Z620) ("Trillion" or the "Company") announces the results of an independent evaluation of contingent and prospective oil resources for Block M47C3,C4 in Southeast Türkiye, prepared by Chapman Hydrogen and Petroleum Engineering... Keep Reading...
15 April
Angkor Resources Invited to Present at Seapex Convention in Manila on Oil & Gas Results in Cambodia
(TheNewswire) GRANDE PRAIRIE, ALBERTA TheNewswire - April 15, 2026 - Angkor Resources Corp. (TSXV: ANK,OTC:ANKOF) ("ANGKOR" OR "THE COMPANY") is pleased to announce that it has been invited to present at the South East Asia Petroleum Exploration Society ("SEAPEX") Regional Convention in Manila,... Keep Reading...
Latest News
Interactive Chart
Latest Press Releases
Related News
TOP STOCKS
American Battery4.030.24
Aion Therapeutic0.10-0.01
Cybin Corp2.140.00