March 14, 2024
Elixir Energy Limited (“Elixir” or the “Company”) is pleased to provide an operations update on its 100% owned Grandis and Nomgon projects located in Queensland and Mongolia respectively.
HIGHLIGHTS
- Coiled tubing unit cleaning out Daydream-2 wellbore in preparation for DFITs
- Significant stimulation and testing program at Grandis on track for April through to June
- Nomgon Pilot Project continues reservoir de-pressurisation process
Grandis Project
A coiled tubing unit has recently been mobilised and is currently cleaning out the Daydream-2 cased wellbore.

This cleanout is a pre-cursor to the Diagnostic Formation Integrity Test (DFIT) program which will follow shortly thereafter. The results of this DFIT program will then be used to optimize the subsequent stimulation and flow testing phases of Daydream-2, which will run from April through to around June.
The detailed design of the stimulation and testing program has now been finalized, with a total of 6 zones to be stimulated. These zones cover ~47 metres of pay out a total of 245 metres (being the final sandstone net pay of 180 metres and coals of 65 metres) recorded in the Daydream 2 wellbore (19% of the total net interval). The sandstone net pay advised to the market on 14 December 2023 of 154 metres has been revised upwards following an external independent expert review.
The zones selected represent a cross-section of permeable sands, tight sands and coals. The total zones being tested in Daydream-2 are guided by the key principle of maximizing useful data acquisition from an appraisal well – that would then inform how future development wells would be designed.
In such future development wells, much greater pay would likely be stimulated and flowed. The results from the stimulation program in Daydream-2 will guide the targeting of further zones in future wells and can be extrapolated over the entire gas prone intervals.
The stimulation program, to be conducted by global leading contractor Halliburton, will be followed by a series of flow tests in May and June.
Nomgon Project
In conjunction with this intense program in Queensland, operations also continue at the Nomgon Pilot Project in Mongolia. In Mongolia, the current key objective is to continue to de-pressurise the gas- bearing coal reservoir through the ongoing pumping of water therefrom.
Recently one of the pilot wells, Nomgon-10, was worked over, with a larger downhole pump installed. Increased water rates have already been observed. Elixir’s engineers are actively managing the Pilot Plant to maximise water production and therefore accelerate the time to reach desorption pressure. Data analysis from the Nomgon field indicates that steady progress is being made in reducing the reservoir pressure required to reach the gas desorption pressure.
Click here for the full ASX Release
This article includes content from Elixir Energy, licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.
EXR:AU
The Conversation (0)
02 May 2024
Elixir Energy
Early-mover in natural gas exploration and appraisal in Australia and Mongolia.
Early-mover in natural gas exploration and appraisal in Australia and Mongolia. Keep Reading...
28 November
Canada-Alberta Pact: Boosting Oil Exports and Clean Energy
Canada and Alberta have sealed a wide-ranging deal that links deep emissions cuts with a long-term push to grow oil and gas output through new export pipelines and fast-track clean energy infrastructure.Prime Minister Mark Carney and Alberta Premier Danielle Smith signed the memorandum of... Keep Reading...
20 November
Angkor Resources Advances Analysis of Andong Bor Drill Core
(TheNewswire) GRANDE PRAIRIE, ALBERTA TheNewswire - (Nov. 20, 2025): Angkor Resources Corp. (TSXV: ANK,OTC:ANKOF) ("ANGKOR" OR "THE COMPANY") announces further analysis, assays, and conclusions on the drill core from Andong Bor license in Oddar Meanchey Cambodia. Dennis Ouellette, VP Exploration... Keep Reading...
20 November
Coelacanth Announces Q3 2025 Financial and Operating Results
Coelacanth Energy Inc. (TSXV: CEI,OTC:CEIEF) ("Coelacanth" or the "Company") is pleased to announce its financial and operating results for the three and nine months ended September 30, 2025. All dollar figures are Canadian dollars unless otherwise noted. HIGHLIGHTS Increased oil and natural gas... Keep Reading...
18 November
Record Gas Production Milestone Achieved
TMK Energy Limited (ASX: TMK) (“TMK” or the “Company”) is pleased to announce it has achieved another record gas production milestone from its 100% owned Gurvantes XXXV Coal Seam Gas (CSG) Project in Mongolia.HIGHLIGHTS: Record gas production of over 500m3 per day for successive days, another... Keep Reading...
12 November
Angkor Resources Engages Departure Capital Inc. for Marketing and Investor Relations Services
(TheNewswire) GRANDE PRAIRIE, ALBERTA TheNewswire - Nov. 12, 2025 - Angkor Resources Corp. (TSXV: ANK,OTC:ANKOF) ("ANGKOR" OR "THE COMPANY") announces that it has entered into a service agreement with Departures Capital Inc. (" Departures Capital ") was signed November 3 2025 and is effective... Keep Reading...
12 November
CHARBONE Confirms Construction Schedule on Track at Sorel-Tracy and Announces the Imminent Start of Equipment Installation Phase
(TheNewswire) Brossard, Quebec TheNewswire - November 12, 2025 CHARBONE CORPORATION (TSXV: CH,OTC:CHHYF; OTCQB: CHHYF; FSE: K47) (" CHARBONE " or the " Company "), a North American producer and distributor specializing in clean Ultra High Purity (" UHP ") hydrogen and strategic industrial gases,... Keep Reading...
Latest News
Latest Press Releases
Related News
TOP STOCKS
American Battery4.030.24
Aion Therapeutic0.10-0.01
Cybin Corp2.140.00