Galena Mining

Drilling Hits Northern Extension Of Abra Mineralisation

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) announces assay results from the first exploration holes drilled from underground at the Abra Mine (“Abra” or the “Project”) have been received. The holes were drilled in Q4 2022 as dual-purpose holes for both exploration (previously identified target) and geotechnical evaluation (underground development planning). Assays associated with these holes have been received after the release of the December quarter activities report.


HIGHLIGHTS:

  • Two underground diamond drill holes drilled to the north of the Abra Fault have confirmed the presence of the Abra style Apron and Core mineralisation, with multiple lead, silver, and copper intercepts, including,
    • 4.8m at 3.1% lead and 6.7g/t silver from 276.88m in 22AUD0159
    • 3.7m at 4.0% lead and 7.2g/t silver from 286.48m in 22AUD0159
    • 2.4m at 5.1% lead and 9.6g/t silver from 314.42m in 22AUD0159
    • 6.9m at 4.9% lead and 7.5g/t silver from 352.73m in 22AUD0160, including,
      • 2.1m at 10.6% lead and 22g/t silver from 352.73m and
      • 1.0m at 1.9% copper from 338.66m in 22AUD0160.
  • Existing Abra Mineral Resource estimate is constrained to the north by Abra Fault and does not include the newly identified mineralisation.
  • Newly identified mineralisation is quite expansive, covering an area approximately 100 metres by 300 metres (in plan) and is open to the north, east and west directions.
  • Drilling also confirms the approximate displacement on the north side of the Abra fault is approximately 70-100 metres lower so newly encountered mineralised zone remains within the mining reach of the existing mine plan.
Prior to these holes, underground drilling has been focused on grade control and resource conversion to support Abra mine production planning for 2023. A total of 122 underground drill holes have been completed in 2022 and the company is currently updating the geology and mining models in the areas where this drilling has occurred. Results and geological confidence associated with the drilling completed to date is considered positive in relation to the previous work.

The Abra mine successfully achieved its first concentrate production on 12 January 2023 (See ASX announcement 13 January 2023). Over 1,000t of saleable concentrate has been produced during plant commissioning to date and the project remains on target to achieve first concentrate shipment in Q1, 2023.

Two new drillholes (22AUD0159 and 0160) were drilled in October 2022, adjacent to a historical intercept drilled by Abra Mining Limited in 2007 (AB41). The new holes confirm the presence of Abra style mineralisation north of the Abra fault. Including the historical hole, the three holes are spread over an area of 300m (east-west) and 100m (north-south). They are approximately 200m from the current Abra Deposit and 100m from the proposed Abra decline infrastructure.

Managing Director, Tony James commented, “This drilling confirmed our belief that Apron style mineralisation is north of the Abra fault and offset some 70 - 100m below the top of the Abra mineralisation. Its very pleasing to see these results in the very first underground exploration holes we have drilled, and its great reward for the team’s hard work to get the mine to this stage. It’s also nice that our progress to date and confidence in the ore body has allowed us to start to do some exploration work on one of the many targets we have at Abra.”

Figure 1. Isometric view looking West of the drill holes (AB41, 22AUD0159 and 0160) drilled north of the Abra Fault and the 2021 Abra Mineral Resources mineralisation domains (Apron/Core). The image also shows the significant intercepts along the drill hole traces, existing underground development.

ABRA UNDERGROUND DIAMOND DRILLING

The underground drilling program at Abra Deposit commenced on 9 June 2022 with the establishment of the first underground drilling platform. A second underground drill rig was introduced into the mine on 13 September 2022. The initial drilling has been focussed on the 2023 production areas with 122 holes completed in 2022, complementing our 2023 production mine plan. The drilling associated with this announcement was done for dual purposes to understand the geotechnical conditions lower on the northern side of the Abra fault where long- term Abra mine infrastructure will be established, whilst also testing a previously identified mineralisation target seen in that location from previous exploration drilling and electromagnetic work.


Click here for the full ASX Release

This article includes content from Galena Mining, licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.


G1A:AU
Galena Mining

Galena Mining Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

The Conversation (0)
Galena Mining (ASX:G1A)

Galena Mining


Keep reading...Show less
Galena Mining

Abra Construction At 97% Complete – First Ore Stockpiled For January Processing

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 97% complete as of 30 November 2022. Processing plant commissioning is progressing quickly with practical completion now expected in December 2022. Ore currently being mined from underground is being stockpiled in readiness for processing to begin in January 2023. Concentrate production will commence January 2023.

Keep reading...Show less
Galena Mining

Abra Construction At 92% Complete – Reaches First Ore Underground

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 92% complete as of 31 October 2022. Underground mine has reached the first ore (see ASX announcement 14 November 2022) and plant commissioning continues in several key areas with the project focussed on achieving first concentrate production in Q1 2023.
Keep reading...Show less
Galena Mining

Abra Mine Reaches Ore

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the underground development at its Abra Base Metals Mine (“Abra” or the “Project”) has reached the Abra orebody. Commissioning has commenced in several key areas of the processing facility and the Power Station (Pacific Energy) completed full integration of the hybrid gas/solar/battery energy storage system (BESS) power station on 10 November. The project remains on track for first concentrate production in Q1 2023.
Keep reading...Show less
Galena Mining

Galena Mining Activities Report For Quarter Ended 30 September 2022

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) reports on its activities for the quarter ended 30 September 2022 (the “Quarter”), primarily focused on construction of its 60%- owned Abra Base Metals Mine (“Abra” or the “Project”) located in the Gascoyne region of Western Australia.

Keep reading...Show less

SilverCrest Reports Third Quarter 2024 Financial Results

Strong Free Cash Flow Continues, Supporting 29% Growth in Treasury Assets

TSX: SIL | NYSE American: SILV

News Provided by Canada Newswire via QuoteMedia

Keep reading...Show less

MAG Silver Reports Third Quarter Financial Results

MAG Silver Corp. (TSX NYSE American: MAG) ("MAG", or the "Company") announces the Company's unaudited consolidated financial results for the three months ended September 30, 2024 ("Q3 2024"). For details of the unaudited condensed interim consolidated financial statements of the Company for the three and nine months ended September 30, 2024 ("Q3 2024 Financial Statements") and management's discussion and analysis for the three and nine months ended September 30, 2024 ("Q3 2024 MD&A"), please see the Company's filings on the System for Electronic Document Analysis and Retrieval Plus ("SEDAR+") at ( www.sedarplus.ca ) or on the Electronic Data Gathering, Analysis, and Retrieval ("EDGAR") at ( www.sec.gov ).

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
Wooden blocks with check mark on them.

Pan American Silver Releases Quarterly Results, Gets Canada's Approval for La Arena Sale

Pan American Silver (TSX:PAAS,NASDAQ:PAAS) said on Tuesday (November 5) that it has received final regulatory approval from the Canadian government for the sale of its La Arena assets in Peru.

The company is selling the La Arena gold mine and development-stage La Arena II copper-gold project to Jinteng (Singapore) Mining, a subsidiary of Zijin Mining Group (OTC Pink:ZIJMF,HKEX:2899).

Under the terms of the deal, Zijin will pay US$245 million in cash for the properties. Pan American will also receive a 1.5 percent life-of-mine net smelter return royalty on gold production from La Arena II.

Keep reading...Show less

First Majestic Announces Financial Results for Q3 2024 and Quarterly Dividend Payment

First Majestic Silver Corp. (NYSE: AG) (TSX: AG) (FSE: FMV) (the "Company" or "First Majestic") is pleased to announce the Company's unaudited condensed interim consolidated financial results for the third quarter ended September 30, 2024. The full version of the financial statements and the accompanying management's discussion and analysis can be viewed on the Company's website at www.firstmajestic.com or on SEDAR+ at www.sedarplus.ca and on EDGAR at www.sec.govedgar. All amounts are in U.S. dollars unless stated otherwise.

THIRD QUARTER HIGHLIGHTS

News Provided by Newsfile via QuoteMedia

Keep reading...Show less
Galena Mining

Galena Mining Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

Latest Press Releases

Related News

×