Denison Completes Commissioning of Lixiviant Injection Modules for Phoenix ISR Feasibility Field Test

Denison Mines logo (CNW Group/Denison Mines Corp.)

Denison Mines Corp. ("Denison" or the "Company") (TSX: DML) (NYSE American: DNN) is pleased to announce the completion of commissioning of the lixiviant injection system for the Phoenix in-situ recovery ("ISR") Feasibility Field Test ("FFT") at the Company's 95% owned Wheeler River project ("Wheeler River" or the "Project"). The lixiviant injection system is the critical operating component necessary to support the leaching phase of the FFT. View PDF version .

Kevin Himbeault , Denison's Vice President of Plant Operations & Regulatory Affairs, commented, "   With the completion of construction and w   et commissioning of the injection modules   ,   we   have   now   successfully   commenced   our initial injection of lixiviant into the test area   , which represents the beginning of the   leaching phase of the FFT.   "

David Cates , Denison's President and CEO, added, "We   are   proud of this notable milestone, particularly given the extensive   coordination   and   efforts   of   Denison   's Saskatoon -based technical   team and our   various   construction   partners   that   have delivered on the safe and timely construction and   commissioning   of this first-of-its-kind test facility.   "

Limited construction activities continue on-site to support future phases of the FFT (discussed below). Construction efforts for the FFT are being completed in collaboration with Tron Construction & Mining, a well-established operator in northern Saskatchewan that is part of the Des Nedhe Group and owned 100% by English River First Nation. Civil earthworks for the FFT are substantially completed, and continue to be supported by Snake Lake Contracting, another northern Saskatchewan -based and Indigenous-owned business.

Th   is press release constitutes a "designated news release" for the purposes of the Company's prospectus supplement dated September 28, 2021 to its short form base shelf prospectus dated September 16, 2021 .

Background on the FFT

The FFT is designed to use the existing commercial-scale ISR test pattern ("Test Pattern"), installed at Phoenix in 2021 (see news releases dated July 29, 2021 , and October 28, 2021 ), to facilitate a combined assessment of the Phoenix deposit's hydraulic flow properties with the leaching characteristics that have been assessed through the metallurgical core-leach testing program.

The FFT is fully permitted, having been authorized by both the Saskatchewan Minister of Environment (see news release dated July 12 , 2022) and the Canadian Nuclear Safety Commission (see news release dated August 8, 2022 ).

Overall, the FFT is intended to provide further verification of the permeability, leachability, and containment parameters needed for the successful application of the ISR mining method at Phoenix and is expected to validate and inform various feasibility study design elements – including the expected production and remediation profiles.

The operation of the FFT is planned to occur in three phases: (1) the leaching phase, (2) the neutralization phase, and (3) the recovered solution management phase.

The leaching phase is designed to assess the effectiveness and efficiency of the leaching process in the mineralized zone, which is approximately 400m below the surface. The leaching phase includes the controlled injection of an acidic solution into a portion of the existing Test Pattern within the mineralized zone (the "Leaching Zone") and the recovery of the solution back to the surface using existing test wells. The recovered solution from the leaching phase is expected to contain dissolved minerals, including uranium, copper, iron, molybdenum, and zinc.

The neutralization phase involves the recovery of the remainder of the leached mineralized solution from the Leaching Zone and is intended to verify the efficiency and effectiveness of the process for returning the Leaching Zone to environmentally acceptable conditions. During this phase, a mild alkaline (basic) solution will be injected into the Leaching Zone to neutralize the area and reverse the residual effects of the acidic solution injected during the leaching phase.

The recovered solution management phase involves separating the solution recovered from both the leaching phase and the neutralization phase into (i) mineralized precipitates and (ii) a neutralized treated solution.

About   Wheeler River

Wheeler River is the largest undeveloped uranium project in the infrastructure rich eastern portion of the Athabasca Basin region, in northern Saskatchewan – including combined Indicated Mineral Resources of 132.1 million pounds U   3   O   8   (1,809,000 tonnes at an average grade of 3.3% U   3   O   8   ), plus combined Inferred Mineral Resources of 3.0 million pounds U   3   O   8   (82,000 tonnes at an average grade of 1.7% U   3   O   8   ). The   P   roject is host to the high-grade Phoenix and Gryphon uranium deposits, discovered by Denison in 2008 and 2014, respectively, and is a joint venture between Denison (operator) and JCU ( Canada ) Exploration Company Limited ("JCU").  Denison has an effective 95% ownership interest in Wheeler River (90% directly, and 5% indirectly through a 50% ownership in JCU).

A PFS was completed for Wheeler River in 2018, considering the potential economic merit of developing the Phoenix deposit as an ISR operation and the Gryphon deposit as a conventional underground mining operation. Taken together, the   P   roject   is estimated to have mine production of 109.4 million pounds U   3   O   8   over a 14-year mine life, with a base case pre-tax NPV of $1.31 billion (8% discount rate), Internal Rate of Return ("IRR") of 38.7%, and initial pre-production capital expenditures of $322.5 million . The Phoenix ISR operation is estimated to have a stand-alone base case pre-tax NPV of $930.4 million (8% discount rate), IRR of 43.3%, initial pre-production capital expenditures of $322.5 million , and industry-leading average operating costs of US$3.33 /lb U   3   O   8   .  The PFS is prepared on a project (100% ownership) and pre-tax basis, as each of the partners to the Wheeler River Joint Venture are subject to different tax and other obligations.

Further details regarding the PFS, including additional scientific and technical information, as well as after-tax results attributable to Denison's ownership interest, are described in greater detail in the NI 43-101 Technical Report titled "Pre-feasibility Study for the Wheeler River Uranium Project, Saskatchewan, Canada " dated October 30, 2018 , with an effective date of September 24 , 2018.  A copy of this report is available on Denison's website and under its profile on SEDAR at www.sedar.com and on EDGAR at www.sec.gov/edgar.shtml .

Denison suspended certain activities at Wheeler River during 2020, including the EA process, which is on the critical path to achieving the project development schedule outlined in the PFS.  While the EA process has resumed, the Company is not currently able to estimate the impact to the project development schedule outlined in the PFS, and users are cautioned against relying on the estimates provided therein regarding the start of pre-production activities in 2021 and first production in 2024.

About Denison

Denison is a uranium exploration and development company with interests focused in the Athabasca Basin region of northern Saskatchewan, Canada . In addition to its effective 95% interest in the Wheeler River project, Denison's interests in the Athabasca Basin include a 22.5% ownership interest in the McClean Lake joint venture, which includes several uranium deposits and the McClean Lake uranium mill that is contracted to process the ore from the Cigar Lake mine under a toll milling agreement, plus a 25.17% interest in the Midwest Main and Midwest A deposits, and a 67.01% interest in the Tthe Heldeth Túé ("THT," formerly J Zone) and Huskie deposits on the Waterbury Lake property. The Midwest Main, Midwest A, THT and Huskie deposits are each located within 20 kilometres of the McClean Lake mill.

Through its 50% ownership of JCU, Denison holds additional interests in various uranium project joint ventures in Canada , including the Millennium project (JCU 30.099%), the Kiggavik project (JCU 33.8118%) and Christie Lake (JCU 34.4508%). Denison's exploration portfolio includes further interests in properties covering approximately 300,000 hectares in the Athabasca Basin region.

Denison is also engaged in post-closure mine care and maintenance services through its Closed Mines group, which manages Denison's reclaimed mine sites in the Elliot Lake region and provides related services to certain third-party projects.

Follow Denison on Twitter @DenisonMinesCo

Qualified Persons

The disclosure of scientific or technical information related to the FFT or Wheeler River project contained in this release has been reviewed and approved, as applicable, by Mr. David Bronkhorst , P.Eng, Denison's Vice President, Operations or Mr. Andrew Yackulic , P. Geo., Denison's Director, Exploration, who are Qualified Persons in accordance with the requirements of NI 43-101.

Cautionary Statement Regarding Forward-Looking Statements

Certain information contained in this news release constitutes 'forward-looking information', within the meaning of the applicable United States and Canadian legislation, concerning the business, operations and financial performance and condition of Denison.  Generally, these forward-looking statements can be identified by the use of forward-looking terminology such as 'potential', 'plans', 'expects', 'budget', 'scheduled', 'estimates', 'forecasts', 'intends', 'anticipates', or 'believes', or the negatives and/or variations of such words and phrases, or state that certain actions, events or results 'may', 'could', 'would', 'might' or 'will   '   '   be taken', 'occur' or 'be achieved'.

In particular, this news release contains forward-looking information pertaining to the following:   status of commissioning and readiness of the FFT;   scope   , objectives and interpretations of the FS process for the proposed ISR operation for the Phoenix deposit, including   the FFT and other   testing programs and the interpretation of the results therefrom; the scope and design, and related test work, with respect to plans and process designs for the FS; and expectations regarding its joint venture ownership interests and the continuity of its agreements with its partners and third parties.

Forward looking statements are based on the opinions and estimates of management as of the date such statements are made, and they are subject to known and unknown risks, uncertainties and other factors that may cause the actual results, level of activity, performance or achievements of Denison to be materially different from those expressed or implied by such forward-looking statements. For example, the modelling and assumptions upon which the work plans for the Wheeler River Project are based may not be maintained after further work is completed.  In addition, Denison may decide or otherwise be required to discontinue testing, evaluation and development work if it is unable to maintain or otherwise secure the necessary resources (such as testing facilities, capital funding, regulatory approvals, etc.). Denison believes that the expectations reflected in this forward-looking information are   reasonable,   but no assurance can be given that these expectations will prove to be accurate and results may differ materially from those anticipated in this forward-looking information. For a discussion in respect of risks and other factors that could influence forward-looking events, please refer to the factors discussed in Denison's Annual Information Form dated March 25, 2022 or subsequent quarterly financial reports under the heading 'Risk Factors'. These factors are not and should not be construed as being exhaustive.

Accordingly, readers should not place undue reliance on forward-looking statements. The forward-looking information contained in this news release is expressly qualified by this cautionary statement. Any forward-looking information and the assumptions made with respect thereto speaks only as of the date of this news release. Denison does not undertake any obligation to publicly update or revise any forward-looking information after the date of this news release to conform such information to actual results or to changes in Denison's expectations except as otherwise required by applicable legislation.

Cautionary Note to United States Investors Concerning Estimates of Mineral Resources and Mineral Reserves : This news release may use the terms 'measured', 'indicated' and 'inferred' mineral resources. United States investors are advised that such terms have been prepared in accordance with the definition standards on mineral reserves of the Canadian Institute of Mining, Metallurgy and Petroleum referred to in Canadian National Instrument 43-101 Mineral Disclosure Standards ('NI 43-101') and are recognized and required by Canadian regulations. 'Inferred mineral resources' have a great amount of uncertainty as to their existence, and as to their economic and legal feasibility   .   It cannot be assumed that all or any part of an inferred mineral resource will ever be upgraded to a higher category. Under Canadian rules, estimates of inferred mineral resources may not form the basis of feasibility or other economic studies. United States investors are cautioned not to assume that all or any part of an inferred mineral resource exists, or is economically or legally mineable. United States investors are also cautioned not to assume that all or any part of measured or indicated mineral resources will ever be converted into mineral reserves.

Effective February 2019 , the   United States Securities and Exchange Commission ('SEC')   adopted amendments to its disclosure rules to modernize the mineral property disclosure requirements for issuers whose securities are registered with the SEC under the Exchange Act and as a result, the SEC now recognizes estimates of "measured mineral resources", "indicated mineral resources" and "inferred mineral resources". In addition, the SEC has amended its definitions of "proven mineral reserves" and "probable mineral reserves" to be "substantially similar" to the corresponding definitions under the CIM Standards, as required under NI 43-101. However, information regarding mineral resources or mineral reserves in Denison's disclosure may not be comparable to similar information made public by United States companies.

Denison Completes Commissioning of Lixiviant Injection Modules for Phoenix ISR Feasibility Field Test (CNW Group/Denison Mines Corp.)

Cision View original content to download multimedia: https://www.prnewswire.com/news-releases/denison-completes-commissioning-of-lixiviant-injection-modules--for-phoenix-isr-feasibility-field-test-301632765.html

SOURCE Denison Mines Corp.

Cision View original content to download multimedia: https://www.newswire.ca/en/releases/archive/September2022/26/c9836.html

News Provided by Canada Newswire via QuoteMedia

DML:CA,DNN
The Conversation (0)
Denison Announces Completion of Conceptual Mining Study Evaluating ISR for Midwest and Plans to Advance Efforts in 2023

Denison Announces Completion of Conceptual Mining Study Evaluating ISR for Midwest and Plans to Advance Efforts in 2023

Denison Mines logo (CNW Group/Denison Mines Corp.)

Denison Mines Corp. ("Denison" or the "Company") (TSX: DML) (NYSE American: DNN) is pleased to announce the successful completion of an internal conceptual mining study (the "Concept Study") examining the potential application of the In-Situ Recovery ("ISR") mining method at the Company's 25.17% owned Midwest project ("Midwest"). The Concept Study was prepared by Denison during 2022 and was formally issued to the Midwest Joint Venture ("MWJV") in early 2023. Based on the positive results of the Concept Study, the MWJV has now provided Denison with approval to complete additional ISR-related evaluation work for Midwest in 2023. View PDF version .

News Provided by Canada Newswire via QuoteMedia

Keep reading...Show less
Denison Reports Financial and Operational Results for 2022, Including Significant De-Risking and Regulatory Milestones

Denison Reports Financial and Operational Results for 2022, Including Significant De-Risking and Regulatory Milestones

Denison Mines logo (CNW Group/Denison Mines Corp.)

Denison Mines Corp. ('Denison' or the 'Company') (TSX: DML) (NYSE American: DNN) today filed its Condensed Consolidated Financial Statements and Management's Discussion & Analysis ('MD&A') for the year ended December 31, 2022 . Both documents will be available on the Company's website at www.denisonmines.com , SEDAR (at www.sedar.com ) and EDGAR (at www.sec.govedgar.shtml ). The highlights provided below are derived from these documents and should be read in conjunction with them. All amounts in this release are in Canadian dollars unless otherwise stated. View PDF version .

News Provided by Canada Newswire via QuoteMedia

Keep reading...Show less
GTI Energy

Major 50% Upgrade Boosts Lo Herma Uranium Resource to 8.57Mlbs, Scoping Study Initiated

GTI Energy Ltd (GTI or Company) is pleased to update the uranium Mineral Resource Estimate (MRE) at its Lo Herma Project (Lo Herma or the Project) located in Wyoming’s Powder River Basin (Figure 1). The MRE for the Project is focused on mining by In-Situ Recovery (ISR) methods and is reported at an appropriate cut-off grade of 200 ppm U3O8 and a minimum grade thickness (GT) of 0.2 per mineralised horizon as:

6.21 million tonnes of total mineralisation at average grade of 630 ppm eU3O8 for 8.57 million pounds (Mlbs) of eU3O8 contained metal classified as 2.78Mlbs of Indicated (32%) and 5.79Mlbs of Inferred.

Keep reading...Show less
Nick Hodge, gold bars.

Nick Hodge: Uranium and Gold Outlook for 2025, Plus Battery Passport Profits

In an interview at the New Orleans Investment Conference, Nick Hodge, publisher at Digest Publishing, discussed the growing prevalence of "battery passports" and the investment angle he sees there.

He also shared his thoughts on how to invest in uranium at this point in the cycle, saying that power-intensive artificial intelligence (AI) data centers are boosting demand for the commodity, which was already strong.

"I've been a uranium bull for a long time — our moment is here. You can't have AI without uranium," said Hodge.

Keep reading...Show less
Nuclear Fuels CEO and President Greg Huffman.

Nuclear Fuels Aims to Boost US Domestic Uranium Supply Chain, CEO Greg Huffman says

Issues facing the global uranium supply chain have created a significant opportunity for emerging explorers and producers to leverage the growing demand for nuclear energy and build more secure and stable domestic supply chains.

In an interview with the Investing News Network, Nuclear Fuels (CSE:NF) CEO and President Greg Huffman said his company is strategically positioned to supply growing US uranium demand by advancing its uranium projects in Wyoming.

“We have massive, massive increases in terms of expected demand for uranium,” he said. “What we at Nuclear Fuels are focused on is being able to come up with new sources of domestic US uranium to help supply that increase in demand for nuclear power.”

Keep reading...Show less

Laramide's 2024 Drill Program Continues to Return Strong Results at the Westmoreland Project in Queensland, Australia, including Notable Gold Mineralisation

Highlights:

  • Results continue to demonstrate the potential to link the Huarabagoo and Junnagunna uranium deposits
    • HJ24DD017 – 25.00m @ 393.64 ppm (0.04%) U 3 O 8 from 15.00m ,
      • including 1.00m @ 1,015.29 ppm (0.10%) U 3 O 8 from 28.00m
      • and 1.00m @ 2,128.46 ppm (0.21%) U 3 O 8 from 34.00m
    • HJ24DD019 – 6.00m @ 1,177.43 ppm (0.12%) U 3 O 8 from 87.00m ,
      • including 4.00m @ 1,520.58 ppm (0.15%) U 3 O 8 from 89.00m
  • Uranium mineralisation at Huarabagoo continues to deliver impressive results including:
    • HB24DD010 – 15.60m @ 2,237.03 ppm (0.22%) U 3 O 8 and 0.53 g/t Au from 68.40m ,
      • including 1.00m @ 2,264.06 ppm (0.23%) U 3 O 8 and 0.23 g/t Au from 70.00m
      • and 7.00m @ 4311.16 ppm (0.43%) U 3 O 8 and 0.10 g/t Au from 76.00m
      • with highest intercept result of 1.00m @ 1.42% U 3 O 8 and 0.01 g/t Au from 80.00m
  • Broad zones of gold mineralisation were also intercepted with grades up to 24.2g/t Au
    • HB24DD008 – 19.00m @ 620.58 ppm (0.06%) U 3 O 8 and 1.95 g/t Au from 48.00m ,
      • including 2.00m @ 1,720.45 ppm (0.17%) U 3 O 8 and 1.64 g/t Au from 57.00m
      • and 2.00m @ 2,202.16 ppm (0.22%) U 3 O 8 and 12.39 g/t Au from 64.00m
      • with highest intercept result of 1.00m @ 2,299.44 ppm (0.22%) U 3 O 8 and 24.20g/t Au from 65.00m
    • HB24DD006 – 8.00m @ 1,449.86 ppm (0.14%) U 3 O 8 & 0.22 g/t Au from 36.00m ,
      • including 1.70m @ 6,208.83 ppm (0.62%) U 3 O 8 & 0.78 g/t Au from 37.60m .
  • New Exploration Permit (EPM 28807) granted adjacent to Westmoreland Project adding 327km   2 of highly prospective tenure in NW Queensland

Laramide Resources Ltd. ( "Laramide" or the "Company" ) (TSX: LAM) (ASX: LAM) (OTCQX: LMRXF), a uranium mine development and exploration company with globally significant assets in the United States and Australia is pleased to announce another batch of assay results from the 2024 drilling campaign completed at the Westmoreland Uranium Project in Queensland, Australia ( "Westmoreland" ) and the receipt of a permit for exploration for a large land package immediately east of and adjacent to the current Westmoreland land tenure.

News Provided by Canada Newswire via QuoteMedia

Keep reading...Show less

Latest Press Releases

Related News

×