CENTURY LITHIUM CHANGES PROJECT NAME TO ANGEL ISLAND MINE

CENTURY LITHIUM CHANGES PROJECT NAME TO ANGEL ISLAND MINE

Century Lithium Corp. (TSXV: LCE) (OTCQX: CYDVF) (Frankfurt: C1Z) (Century Lithium or the Company) announces it has changed the name of its 100%-owned Clayton Valley Lithium Project in Nevada, USA to the Angel Island Mine (the Project). In April 2024 the Company announced a positive Feasibility Study for the Project, making it one of the few advanced lithium projects being developed in the United States . As the Company now continues to work towards permitting the Project, regulators encouraged a name change for clarity in the permitting process. The Angel Island name distinguishes it from other mining and energy projects in the area by using the name of a topographical feature from the Project.

ABOUT ANGEL ISLAND
Angel Island is named for the ridge of older metavolcanic and clastic rocks bordering the west side of Century's lithium clay deposit. The name itself dates to the 1800's, one of three landforms in Clayton Valley named for islands in San Francisco Bay (Alcatraz and Goat islands being the other two). Of the three landforms, Angel Island is the largest, rising to a height 400 meters above the valley floor. Its presence on the east side of the valley, separating Century's lithium clay deposit from the lithium brine operation of Albemarle Corp., is owed to uplift along a major northeast trending normal fault located along the western base of the ridge. Although not directly related to the formation of Century's deposit, uplift of Angel Island along this fault was responsible for elevating the clay deposits east of the fault and bringing them to the surface where they are now accessible for mining. The harder rocks in the ridge also likely acted as a physical barrier protecting Century's lithium clay deposit from erosion.

ABOUT Century Lithium CORP.
Century Lithium Corp. is an advanced stage lithium company, focused on developing its 100%-owned Angel Island Mine in west-central Nevada, USA . Century Lithium recently completed a Feasibility Study on the Project and is currently in the permitting stage, with the goal of becoming a domestic producer of lithium for the growing electric vehicle and battery storage market.

ON BEHALF OF Century Lithium CORP.
WILLIAM WILLOUGHBY , PhD., PE
President & Chief Executive Officer

NEITHER THE TSX VENTURE EXCHANGE NOR ITS REGULATION SERVICES PROVIDER ACCEPTS RESPONSIBILITY FOR THE ADEQUACY OR ACCURACY OF THE CONTENT OF THIS NEWS RELEASE.

Cautionary Note Regarding Forward-Looking Statements

This release contains certain forward-looking statements within the meaning of applicable Canadian securities legislation. In certain cases, forward-looking statements can be identified by the use of words such as "plans", "expects" or "does not anticipate", or "believes", or variations of such words and phrases or statements that certain actions, events or results "may", "could", "would", "might" or "will be taken", "occur" or "be achieved" and similar expressions suggesting future outcomes or statements regarding an outlook.

Forward-looking statements relate to any matters that are not historical facts and statements of our beliefs, intentions and expectations about developments, results and events which will or may occur in the future, without limitation, statements with respect to the potential development and value of the Project and benefits associated therewith, statements with respect to the expected project economics for the Project, such as estimates of life of mine, lithium prices, production and recoveries, capital and operating costs, IRR, NPV and cash flows, any projections outlined in the Feasibility Study in respect of the Project, the permitting status of the Project and the Company's future development plans.

These and other forward-looking statements and information are subject to various known and unknown risks and uncertainties, many of which are beyond the ability of the Company to control or predict, that may cause their actual results, performance or achievements to be materially different from those expressed or implied thereby, and are developed based on assumptions about such risks, uncertainties and other factors set out herein. These risks include those described under the heading "Risk Factors" in the Company's most recent annual information form and its other public filings, copies of which can be under the Company's profile at www.sedarplus.com . The Company expressly disclaims any obligation to update-forward-looking information except as required by applicable law. No forward-looking statement can be guaranteed, and actual future results may vary materially. Accordingly, readers are advised not to place reliance on forward-looking statements or information. Furthermore, Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.

Cision View original content to download multimedia: https://www.prnewswire.com/news-releases/century-lithium-changes-project-name-to-angel-island-mine-302203730.html

SOURCE Century Lithium Corp.

News Provided by PR Newswire via QuoteMedia

LCE:CA
Century Lithium

Century Lithium Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

The Conversation (0)
Century Lithium (TSXV:LCE)

Century Lithium


Keep reading...Show less
CENTURY LITHIUM FILES TECHNICAL REPORT ON THE FEASIBILITY STUDY OF THE CLAYTON VALLEY LITHIUM PROJECT, NEVADA

CENTURY LITHIUM FILES TECHNICAL REPORT ON THE FEASIBILITY STUDY OF THE CLAYTON VALLEY LITHIUM PROJECT, NEVADA

Century Lithium Corp. (TSXV: LCE) (OTCQX: CYDVF) (Frankfurt: C1Z) (Century Lithium or the Company) is pleased to announce the filing of the report " NI 43-101 Technical Report on the Feasibility Study of the Clayton Valley Lithium Project, Esmeralda County, Nevada USA", with effective date April 29 2024 (Feasibility Study or Report), to support the disclosure in the Company's news release dated April 29, 2024 (see news release ). The Report was prepared in accordance with National Instrument 43-101 (NI 43-101) by Wood Canada Limited (Wood), Global Resource Engineering, Ltd. (GRE) and WSP USA Environment and Infrastructure, Inc. (WSP). All currency amounts in this news release are presented in US dollars.

News Provided by PR Newswire via QuoteMedia

Keep reading...Show less
CENTURY LITHIUM ANNOUNCES POSITIVE FEASIBILITY STUDY FOR THE CLAYTON VALLEY LITHIUM PROJECT, NEVADA

CENTURY LITHIUM ANNOUNCES POSITIVE FEASIBILITY STUDY FOR THE CLAYTON VALLEY LITHIUM PROJECT, NEVADA

FEASIBILITY STUDY HIGHLIGHTS

  • Large-Scale Nevada-based Lithium Project: three-phase production plan will generate a life-of-mine average of 34,000 tonnes per annum (tpa) of battery-quality lithium carbonate (Li 2 CO 3 )

  • Innovative Approach in Processing: patent-pending chloride leaching process combined with Direct Lithium Extraction (DLE), the Feasibility Study is supported by 2+ years of testing at the Company's Pilot Plant

  • Mineral Resource Estimate: Measured and Indicated resources totaling 1,207.33 million tonnes (Mt) at an average grade of 957 parts per million (ppm) lithium (Li) containing 1. 155 Mt of Li or 6. 148 Mt of lithium carbonate equivalent (LCE)

  • Long 40-Year Mine Life : Proven and Probable Mineral Reserve Estimate totaling 287.65 Mt at an average grade of 1,149 ppm Li containing 0. 330 Mt of lithium or 1. 759 Mt of LCE

  • Initial Project: Phase 1 Capital Cost $1.537 billion for production capacity of 13,000 tpa LCE

  • Designed for Expansion: Phase 2 $0.651 billion for 28,000 tpa LCE, and Phase 3 $1.336 billion for 41,000 tpa LCE; Project expansions are capitalized with Project cash flow

  • Low Operating Cost: average operating cost $8,223 /t of Li 2 CO 3 produced, or $2,766 /t after sales of surplus sodium hydroxide (NaOH)

  • After-tax IRR of 17.1% at $24,000 /t Li 2 CO 3 : $3.01 billion after-tax net present value (NPV) at 8% discount rate and a 17.1% after-tax internal rate of return (IRR), using price assumptions of $24,000 /t for Li 2 CO 3 and $600 /dry metric tonne (dmt) for NaOH

Century Lithium Corp. (TSXV : LCE ) (OTCQX: CYDVF ) (Frankfurt: C1Z ) (Century Lithium or the Company) is pleased to announce the results of a National Instrument 43-101 (NI 43-101) feasibility study (Feasibility Study, FS or Study) completed on its 100% owned Clayton Valley Lithium Project (Project) in Nevada, USA . The Feasibility Study was prepared by Wood Group USA Inc. (Wood) and Global Resource Engineering, Ltd. (GRE). All currency amounts in this news release are presented in U.S. dollars.

News Provided by Canada Newswire via QuoteMedia

Keep reading...Show less
CENTURY LITHIUM PROVIDES UPDATE ON THE FEASIBILITY STUDY

CENTURY LITHIUM PROVIDES UPDATE ON THE FEASIBILITY STUDY

Century Lithium Corp. (TSXV: LCE) (OTCQX: CYDVF) (Frankfurt: C1Z) (Century Lithium or Company) reports that the Feasibility Study on the Company's Clayton Valley Lithium Project (Project), in Nevada, USA under the direction of Wood PLC and Global Resource Engineering Ltd., is currently under review by the Qualified Persons, and the Company anticipates its announcement imminently.

Century Lithium Provides Update on the Feasibility Study (CNW Group/Century Lithium Corp.)

To date, the Company's Feasibility Study team has revised and updated estimates for a phased production approach at the Project. These revisions also included assessment and evaluation of the economic benefit of sales of the surplus sodium hydroxide produced by the chlor-alkali plant.

The Company's Lithium Extraction Facility (Pilot Plant) in Amargosa Valley, Nevada is now in its third year of testing the processing of lithium-bearing claystone from the Project. All data collected has been essential to the Feasibility Study. Century Lithium continues to work toward permitting the Project including the collection of baseline data collection for biology, surface and groundwater hydrology, and social impacts. Earlier this year, baseline reports were submitted by the Company's consultants and were accepted by the appropriate government agencies. Multiple reports have been completed which will aide in the preparation of a Plan of Operations to initiate the National Environmental Policy Act (NEPA) process.

About Century Lithium Corp.

Century Lithium Corp. (formerly Cypress Development Corp.) is an advanced stage lithium company, focused on developing its 100%-owned Clayton Valley Lithium Project in west-central Nevada, USA . Century Lithium is currently in the pilot stage of testing on material from its lithium-bearing claystone deposit at its Lithium Extraction Facility in Amargosa Valley, Nevada and progressing towards completing a Feasibility Study and permitting, with the goal of becoming a domestic producer of lithium for the growing electric vehicle and battery storage market.

ON BEHALF OF Century Lithium CORP.
WILLIAM WILLOUGHBY , PhD., PE
President & Chief Executive Officer

NEITHER THE TSX VENTURE EXCHANGE NOR ITS REGULATION SERVICES PROVIDER ACCEPTS RESPONSIBILITY FOR THE ADEQUACY OR ACCURACY OF THE CONTENT OF THIS NEWS RELEASE.

Cautionary Note Regarding Forward-Looking Statements

This release includes certain statements that may be deemed to be "forward-looking statements". Forward-looking statements are subject to risks, uncertainties and assumptions and are identified by words such as " expects," "estimates," "projects," "anticipates," "believes," "could," "scheduled," and other similar words. All statements in this release, other than statements of historical facts, that address events or developments that management of the Company expects, are forward-looking statements. Although management believes the expectations expressed in such forward-looking statements are based on reasonable assumptions, such statements are not guarantees of future performance, and actual results or developments may differ materially from those in the forward-looking statements. The Company undertakes no obligation to update these forward-looking statements if management's beliefs, estimates or opinions, or other factors, should change. Factors that could cause actual results to differ materially from those in forward-looking statements, include market prices, exploration, and development successes, continued availability of capital and financing, and general economic, market or business conditions. Please see the public filings of the Company at www.sedar.com for further information.

Cision View original content to download multimedia: https://www.prnewswire.com/news-releases/century-lithium-provides-update-on-the-feasibility-study-302121633.html

SOURCE Century Lithium Corp.

Cision View original content to download multimedia: http://www.newswire.ca/en/releases/archive/April2024/19/c7578.html

News Provided by Canada Newswire via QuoteMedia

Keep reading...Show less
Century Lithium Corp. to Present at the Metals and Mining Virtual Investor Conference October 3rd

Century Lithium Corp. to Present at the Metals and Mining Virtual Investor Conference October 3rd

Century Lithium Corp (TSX:V: LCE; OTCQX: CYDVF), based in Vancouver, focused on developing its 100%-owned Clayton Valley Lithium Project in Nevada, USA., today announced that William Willoughby, President & CEO, will present live at the Metals and Mining Virtual Investor Conference, hosted by VirtualInvestorConferences.com, on October 3 rd 2023.

DATE : October 3 rd , 2023
TIME: 2:00 PM ET
LINK: https://bit.ly/44FOnTd
Available for 1x1 meetings: October 3

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
CENTURY LITHIUM OBTAINS PROVISIONAL PATENT

CENTURY LITHIUM OBTAINS PROVISIONAL PATENT

Century Lithium Corp. (TSXV: LCE) (OTCQX: CYDVF) (Frankfurt: C1Z) (Century Lithium or the Company) is pleased to report it has obtained a provisional patent with the U.S. Patent and Trademark Office, U.S. Department of Commerce. The provisional patent is titled System and Method for Extracting Lithium from Clay and Other Materials in a Chloride Solution Using Individualized Pretreatments . The patent pending process encompasses the Company's flowsheet, as developed at its Lithium Extraction Facility ("Pilot Plant") in Amargosa Valley, Nevada USA and protects the Company's intellectual property (IP) pertaining to the handling of solutions derived from the treatment of solid materials including clays from the Company's Clayton Valley Lithium Project (Project) in Nevada .

News Provided by PR Newswire via QuoteMedia

Keep reading...Show less
Brunswick Exploration Outlines New Spodumene Rich Boulder Trains at Mirage and Launches Summer Drill Campaign

Brunswick Exploration Outlines New Spodumene Rich Boulder Trains at Mirage and Launches Summer Drill Campaign

Brunswick Exploration Inc. (" BRW " or the " Company ") is pleased to announce the completion of the 2024 prospecting program and start of a 5,000-metre summer drill program at the Mirage Project, located in the Eeyou Istchee-James Bay region of Quebec. To date, 71 drill holes and more than12,000 meters have been drilled on the Mirage project which have delineated nine near-surface spodumene-bearing pegmatite dykes, all of which remain open at depth and along strike. Approximately two dozen additional dykes, with widths ranging from 8 metres to approximately 20 metres, have also been intercepted in the two previous campaigns with minimal to no follow-up work. The proposed program will focus on MR-6, MR-3 and MR-4 as well as new targets that were delineated using drilling, geophysics, till mineralogy and prospecting.

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
Lithium Universe Ltd  Becancour Lithium Refinery Project Update

Lithium Universe Ltd Becancour Lithium Refinery Project Update

Melbourne, Australia (ABN Newswire) - Lithium Universe Limited (ASX:LU7) (OTCMKTS:ESMAF) is pleased to announce a project update of the Becancour Lithium Refinery Project. The project is advancing well and remains on track. Key milestones include finalizing the plant layout, issuing technical specifications for capex estimation, and progressing with supplier quotation activities. Environmental site visits and studies are ongoing, with no significant issues identified. Hatch's transition from Brisbane to Montreal offices is smoothly underway, ensuring continuity in project management. Early contractor engagement and strategic risk assignment are mitigating potential delays. Overall, the project is adhering to its timeline, with significant progress in engineering and procurement, ensuring readiness for a capital cost estimate and commitment to ensure environmental compliance with the regulatory framework.

Highlights

- Project is advancing well and remains on track

- Engineering milestones include plant layout, equipment packages, datasheets, scopes of work, and specifications

- Procurement priority one packages for quotes about 60% complete

- Early contractor engagement and strategic risk assignment

- Environmental work is progressing with no show-stoppers identified to date

- Strong engagement from Federal, Provincial and Local Government

- Becancour Lithium Refinery well aligned with Provincial strategy

- Mature local government support and project understanding

Procurement

Procurement activities include sending technical specifications to suppliers for detailed quotations to build the capex estimation. For priority one mechanical equipment, nine packages have been issued, with seven offers received and evaluations currently underway. Five priority one electrical equipment supply packages will be issued for inquiry within the next week. The goal is to evaluate all priority one packages by the end of September.

Due to potential lead times for electrical transformers, the tenderer list will be expanded to reduce these lead times.

Engineering

The major engineering activities include finalizing the plant layout and preparing documentation for equipment packages, such as datasheets, scopes of work, and specifications. Key tasks also involve creating the main power distribution single line diagram and providing clarifications during the tender period. Additionally, proposals received are being thoroughly reviewed to ensure they meet project requirements. Effective handling of process effluent and site runoff is another critical focus area. The development of the package register, material take-offs (MTOs), and comprehensive equipment lists are ongoing, ensuring all necessary components and details are accurately documented and organized for the project's successful execution.

Plant Layout

The first release of the plant layout has been published, with several features still under development. These include new plant areas such as the boiler plant and process effluent treatment. Structural framing of buildings and HVAC systems are in progress, along with civil works encompassing drainage, road pavements, vehicle paths, sedimentation ponds, and car parking. The location and number of plant switch rooms is being optimised.

Efforts are being made to enhance spodumene and residue storage, focusing on materials handling and capacity. Additionally, the routing of major pipe and cable racks is being planned. The layout on-site is being designed with consideration of likely environmental constraints to ensure compliance and sustainability. These developments aim to enhance the overall efficiency and effectiveness of the project.

Environmental Work

The team is actively involved in field inventories to develop knowledge of the biodiversity present on site. Four field campaigns have been carried-out to survey the presence of short-eared owls, breeding birds, fish and fish habitat, and wetlands. Based on preliminary results, no species at risk nor species of concern as listed under the Canadian Species at Risk Act (SARA) have been identified so far. The project team is also engaged in activities to optimize the site layout and reduce encroachment on wetlands identified on the property. Surveys are expected to be completed during the Canadian Summer. Field inventory results will be used to support environmental permitting activities and discussions with the Regulators to ensure site layout and the design of the industrial facility are developed in full compliance with the environmental regulatory framework.

A Phase I study to understand previous uses of the site is progressing and no potential environmental liability has been identified based on preliminary results. The Phase I Study is expected to be completed by the end of July. Over the coming months, the team is expected to initiate the preparation of permitting documents to ensure the Project follows formal approval lines.

Priorities

The highest priorities for the next few months include finalising the environmental permitting and approvals program, which entails completing the initial field survey, briefing with the Ministry, finalising the Phase 1 Report, and preparing the first application. Engineering work necessary for the environmental permit application is also a top priority, focusing on civil design, updated plant layout, and water management strategy. In parallel, equipment procurement will involve preliminary engineering, securing vendor proposals, and establishing schedules. Confirming the treatment of process effluent and site runoff is crucial for environmental compliance.

Additionally, commencing civil and structural engineering work is essential to maintain project momentum.

Finalising the plant layout will ensure all components are correctly positioned and integrated. Lastly, execution phase planning will be progressed, contingent on the monthly budget, to ensure that all activities are appropriately funded and scheduled for efficient project advancement.

Government and Community Engagement

A trip by key leadership members to Eastern Canada. The delegation, led by CEO Alex Hanly and including Chairman Iggy Tan, Board Directors Patrick Scallan and Dr. Jingyuan Liu, and Canadian Director, Victoria Vargas, engaged with government stakeholders, community partners, and industry peers. The meetings in Montreal, Becancour, Quebec City, and Ottawa reinforced the Company's strategy to address the Lithium Conversion Gap in North America and provided updates on our engineering progress and commercial discussions.

Ministry of Economics, Innovation, and Energy

A meeting was held in Quebec City with the Honourable Minister Pierre Fitzgibbon, Minister of Economics, Innovation, and Energy. This follows the Company's initial presentation of the Company's unique strategy in November 2023 in Dubai. Once again, Minister Fitzgibbon expressed enthusiasm for our engineering progress, the acquisition of the Option agreement within the Becancour Industrial Park, and the Hydro-Quebec application for an estimated 22.5MW energy allocation for our Becancour Lithium Refinery.

Lithium Universe emphasized Quebec's strategic benefits, including hydroelectric power, proximity to the James Bay region, and logistic advantages with port access to the transatlantic region. The Minister reiterated his support for our vision of transforming Quebec into the Centre of Lithium Conversion for the transatlantic region.

The Company is impressed with the forward-thinking provincial government of Quebec and the progress of the Strategic Innovation Zone under the pragmatic guidance of Minister Fitzgibbon.

Becancour Lithium Refinery Site

In February 2024, the Company successfully executed an option agreement to acquire a refinery site strategically located within the Becancour Waterfront Industrial Park (BWIP). The site in Becancour, close to Trois-Rivieres, lies between Montreal and Quebec City and is near major highways and railways. The Port of Becancour supports year-round operations with deep-water access. The site offers low-cost hydroelectric power, robust infrastructure, and comprehensive water and waste facilities, ideal for the proposed Lithium Refinery.

The Company once again met with key executives from the BWIP in Becancour. The meeting focused on the Company's progress in site evaluation activities and included a presentation on the process design, featuring pictures from a reference lithium carbonate refinery. The port was confirmed to have the capacity to manage 50,000-ton bulk shipments, exceeding the Company's initial requirements. The Company had the opportunity to inspect Lot 22, encompassing an area of 27-hectare, and view the proximity to infrastructure and immediate tiein to existing BWIP utilities. The SPIPB team provided an overview of planned expansions and facility upgrades to the onsite infrastructure, positioning Becancour as a leader in offering prime industrial real estate in Quebec.

The Company will be looking to commence various community initiatives to integrate the industrial site into the wider community.

Municipality of Becancour

The Company met with the Mayoress of Becancour to discuss the Company's objectives to contribute to the local economy by providing hundreds of employment opportunities and helping to realize its economic potential.

LU7 reaffirmed its commitment to the Becancour and wider Trois-Rivieres region, pledging to support various social, community, and environmental initiatives in the coming years. The Mayoress expressed enthusiasm for the Company's plans within the SPIPB, recognizing the development of a proven and reliable design with internationally aligned process outputs.

Provincial Government - Quebec

The Company also met with key delegates in Montreal from Investissement Quebec (IQ), the Ministry of Natural Resources and Forests (MRNF), Energy Transition Valley Innovation Zone, and the Ministry of the Environment, the Fight Against Climate Change, Wildlife and Parks. The provincial government has identified a lithium conversion gap within the supply chain, crucial for servicing the expected increase in spodumene supply from the James Bay region in the coming years. Quebec is a North American leader in attracting foreign direct investment, sustainable development, and supporting battery metals projects. The province has a strong history of supporting lithium battery supply chain development, with significant provincial and federal government incentives.

Recent government support includes the General Motors (GM) and Korea-based POSCO Chemicals' US$1 billion cathode active material (CAM) factory, the Ford/EcoPro BM US$800 million cathode factory, and Northvolt's US$7 billion EV Battery Facility at Saint-Basile-le-Grand. This creates a favourable regulatory environment for the Company's project, ensuring robust support throughout the cycle.

Canadian Federal Government - Ottawa

The Company met with various federal government stakeholders from Invest in Canada (IIC), Natural Resources Canada (NRCAN), Innovation, Science and Economic Development (ISED), and Export Development Canada (EDC). Given the lack of refining capacity in Canada, LU7's lithium carbonate plant is an innovative project, as there are no current operating or planned facilities of this kind within the country. Building lithium conversion capacity alongside spodumene mines will enable Canada to become wholly self-sufficient in the lithium chemical supply chain.

Hatch - Montreal

The Company and its engineering partner, Hatch, held a productive meeting at the Montreal office to align their shared culture and fast-track development vision. They reinforced the philosophy of "same process, same equipment, same supplier," which minimizes technical risks, ensures quality, and reduces costs. The operational environments in Australia and Canada share many similarities, facilitating the integration of skills into Quebec.

Hatch's leadership in building lithium conversion facilities and tackling challenging projects validates the decision to partner with them. Through this collaboration, the Company acknowledges Hatch's expertise as the premier lithium refinery engineering expert.

Lithium Universe Chairman, Iggy Tan said, "The project is on track, finalizing plant layout, issuing capex specs, progressing supplier quotes, with smooth office transition, and no environmental issues, ensuring readiness for capex cost estimate. The reception from federal, provincial and local government delegates has left a very positive impression on the LU7 Board of Directors. The region has made strong commitments since releasing the Critical Minerals Strategies four years ago and we have seen that in the significant investments made within the battery supply chain and pragmatic discussions held with key government executives. We look forward to advancing the Company's Becancour Lithium Refinery to contribute in making Quebec the lithium conversion centre within the Transatlantic region."

*To view tables and figures, please visit:
https://abnnewswire.net/lnk/82C8D877



About Lithium Universe Ltd:

Lithium Universe Ltd (ASX:LU7) (OTCMKTS:ESMAF), headed by industry trail blazer, Iggy Tan, and the Lithium Universe team has a proven track record of fast-tracking lithium projects, demonstrated by the successful development of the Mt Cattlin spodumene project for Galaxy Resources Limited.

Instead of exploring for the sake of exploration, Lithium Universe's mission is to quickly obtain a resource and construct a spodumene-producing mine in Quebec, Canada. Unlike many other Lithium exploration companies, Lithium Universe possesses the essential expertise and skills to develop and construct profitable projects.



Source:
Lithium Universe Ltd

News Provided by ABN Newswire via QuoteMedia

Keep reading...Show less
Victory is Pleased to Announce the Appointment of Gary Musil to the Company's Board of Directors and a Private Placement

Victory is Pleased to Announce the Appointment of Gary Musil to the Company's Board of Directors and a Private Placement

Victory Battery Metals Corp. (CSE:VR)(OTC PINK:VRCFF)(FWB:VR6) welcomes Gary Musil as a director of the Company, effective July 1, 2024. Gary Musil has more than 35 years of management and financial consulting experience and has served as an officer and director on numerous public companies since 1988. This experience has resulted in his overseeing the financial aspects and expenditures on exploration projects in Peru, Chile, Eastern Europe (Slovak Republic), and British Columbia, Ontario, Quebec, Saskatchewan and New Brunswick (Canada). Prior to his public company work, he was employed for 15 years with Dickenson Mines Ltd. and Kam-Kotia Mines Ltd., as the Controller for their producing silverleadzinc mine in the interior of British Columbia

News Provided by ACCESSWIRE via QuoteMedia

Keep reading...Show less
Albemarle Announces Quarterly Common Stock Dividend

Albemarle Announces Quarterly Common Stock Dividend

The Board of Directors of Albemarle Corporation (NYSE: ALB) announces that it has declared a quarterly common stock dividend of $0.405 per share. The dividend, which has an annualized rate of $1.62 is payable Oct. 1, 2024 to shareholders of record at the close of business as of Sept. 13, 2024 . For 30 consecutive years, Albemarle has raised its dividend.

Albemarle Corp. Logo. (PRNewsFoto/Albemarle Corporation)

About Albemarle
Albemarle Corporation (NYSE: ALB) leads the world in transforming essential resources into critical ingredients for mobility, energy, connectivity and health. We partner to pioneer new ways to move, power, connect and protect with people and planet in mind. A reliable and high-quality global supply of lithium and bromine allows us to deliver advanced solutions for our customers. Learn more about how the people of Albemarle are enabling a more resilient world at Albemarle.com , LinkedIn and on X (formerly known as Twitter) @AlbemarleCorp .

Albemarle regularly posts information to www.albemarle.com , including notification of events, news, financial performance, investor presentations and webcasts, non-GAAP reconciliations, U.S. Securities and Exchange Commission filings and other information regarding the company, its businesses and the markets it serves.

Forward-Looking Statements

Some of the information presented in this press release, including, without limitation, information related to future dividends and results, and all other information relating to matters that are not historical facts may constitute forward- looking statements within the meaning of the Private Securities Litigation Reform Act of 1995. Actual results could differ materially from the views expressed. Factors that could cause actual results to differ materially from the outlook expressed or implied in any forward-looking statement include, without limitation: changes in economic and business conditions; adverse changes in liquidity or financial or operating performance; changes in the demand for our products or the end-user markets in which our products are sold and the other factors detailed from time to time in the reports we file with the U.S. Securities and Exchange Commission, including those described under "Risk Factors" in our Annual Report on Form 10-K and our Quarterly Reports on Form 10-Q. These forward-looking statements speak only as of the date of this press release. We assume no obligation to provide any revisions to any forward-looking statements should circumstances change, except as otherwise required by securities and other applicable laws.

Investor Relations Contact: Meredith Bandy , +1 (980) 999-5768, meredith.bandy@albemarle.com
Media Contact: Peter Smolowitz
, +1 (980) 308-6310, media@albemarle.com

Cision View original content to download multimedia: https://www.prnewswire.com/news-releases/albemarle-announces-quarterly-common-stock-dividend-302198618.html

SOURCE Albemarle Corporation

News Provided by PR Newswire via QuoteMedia

Keep reading...Show less
Altech Batteries Ltd  Update on CERENERGY ABS60 Battery-pack Prototypes

Altech Batteries Ltd Update on CERENERGY ABS60 Battery-pack Prototypes

Perth, Australia (ABN Newswire) - Altech Batteries Limited (ASX:ATC) (FRA:A3Y) (OTCMKTS:ALTHF) is pleased to provide an update on the production of its CERENERGY(R) ABS60 BatteryPack prototypes. All 240 cells for the first ABS60 BatteryPack Prototype have now been fabricated, assembled and initialized at Fraunhofer IKTS Hermsdorf's pilot plant.

Highlights

- Prototype production is progressing well

- All CERENERGY(R) cells for the first 60 KWh Prototype completed

- Cell contacting system manufacturing finished and delivered

- Improved cell electrode design showing excellent results

- Cell quality tests by Fraunhofer delivering better than expected capacity

- Welding of cells to cell contacting system underway

- Completed modules will be mounted into ABS60 BatteryPack next week

To validate a homogeneous cathode material distribution, all cells were cycled through several testing stations at Fraunhofer IKTS Hermsdorf and Arnstadt.

IMPROVED CELL ELECTRODE DESIGN

During the fabrication of the two 60kWh CERENERGY(R) ABS60 BatteryPack prototypes, the Altech and Fraunhofer team made several design improvements to the cell's positive probe. These enhancements aimed to boost the cell's energy capacity and reduce the nickel content. The "V2" design of the positive probe allows for slightly faster charging and discharging while lowering the unit costs of the battery. Testing revealed that most cells had higher-than-expected energy capacities, an outstanding result that strongly supports the chosen electrode design. With all cells manufactured according to the series design and optimized processes, the best cells to date have been completed. The table below demonstrates that all the cells are meeting the expected specifications.

CELL CONTACTING SYSTEM COMPLETED

The Cell Contacting System (CCS) has undergone stringent testing and has now been completed and delivered by key supplier Hofer AG. The CCS was delivered to Fraunhofer IKTS in Dresden, where all parts of the modules will be collected to assemble each of the five modules. Each module contains 48 cells, that are currently being welded to the CCS by an external service provider.

After welding is completed, the ABS60 BatteryPack with its 60 kWh capacity can be completely assembled.

MODULE WELDING TRIALS

To guarantee the most time-efficient welding, a unique tool was designed and built at Xenon, which is responsible for welding and quality control across the 120 MWh battery plant. After completing the welding tool, it was shipped to an external laboratory, accompanied by a test module and several trial cells. The aim was to determine the best working parameters and to proof the handling of certain parts of the module.

The trials were successfully finished.

CELL MANUFACTURING PROGRESSING WELL

All 240 cells for the first ABS60 BatteryPack Prototype have been assembled and initialised at Fraunhofer IKTS, Hermsdorf. To validate a homogeneous cathode material distribution, all cells were cycled through several testing stations at Fraunhofer IKTS Hermsdorf and Arnstadt.

INTERIM CELL TESTING

At Fraunhofer IKTS in Hermsdorf, all cells were scanned using a unique X-ray microtomography device that enables the ability to look inside cells after they are hermetically closed. This is required to ensure the most homogeneous material distribution inside the cells as well as the best possible alignment of cell components e.g. electrode. The results have been excellent to date. Another quality assurance procedure involved cycling cells to ensure the electrical requirements and parameters are operating as designed.

MODULE WELDING AND BATTERYPACK ASSEMBLY

After every cell passed all quality checks, the modules containing the cells were shipped to the laboratory for welding onto the CCS. By using the predetermined parameters for welding, all modules have been successfully welded. After completion, the modules will be shipped to Fraunhofer IKTS, Dresden, where all five modules will then be mounted into the ABS60 BatteryPack and the first Prototype will be completed.

This will enable testing and demonstration to potential customers, to prove individual use cases for each customer.

ABOUT THE ABS60 - BATTERYPACK

The 60kWh Altech Battery Pack consists of five 12kWh modules with 48 cells each, mounted on top of each other and sealed in a thermal isolated stainless steel hood housing. The Battery management system is mounted at the base. To maintain thermal self-sufficiency, an insulation hood was designed, where the required heat of the system can be maintained inside the BatteryPack as long as possible, although the outer surface only has ambient temperature. This was achieved by using vacuum insulation. The base of each module is designed to accommodate folklift transport for easy mounting into the GridPack.

Commenting on the progress, MD and CEO Iggy Tan stated "Altech's team in Germany, together with its joint venture partner Fraunhofer, and with the assistance of key suppliers, have made excellent progress on the fabrication of two 60kWh CERENERGY(R) ABS60 BatteryPack prototypes. All components for the first BatteryPack have now been fabricated. Altech is now completing the welding of the cells to the Cell Contacting System, after which the five completed battery modules will be delivered to Fraunhofer IKTS in Dresden, where all five modules will be mounted into the ABS60 BatteryPack and the first ABS60 Prototype will be completed. The BatteryPack will then be available for testing and demonstration to potential customers, thereby assisting Altech in securing offtake and finance for the 120MWh CERENERGY(R) battery plant to be constructed on Altech's land in Germany".

*To view tables and figures, please visit:
https://abnnewswire.net/lnk/O449B2I4



About Altech Batteries Ltd:

Altech Batteries Limited (ASX:ATC) (FRA:A3Y) is a specialty battery technology company that has a joint venture agreement with world leading German battery institute Fraunhofer IKTS ("Fraunhofer") to commercialise the revolutionary CERENERGY(R) Sodium Alumina Solid State (SAS) Battery. CERENERGY(R) batteries are the game-changing alternative to lithium-ion batteries. CERENERGY(R) batteries are fire and explosion-proof; have a life span of more than 15 years and operate in extreme cold and desert climates. The battery technology uses table salt and is lithium-free; cobalt-free; graphite-free; and copper-free, eliminating exposure to critical metal price rises and supply chain concerns.

The joint venture is commercialising its CERENERGY(R) battery, with plans to construct a 100MWh production facility on Altech's land in Saxony, Germany. The facility intends to produce CERENERGY(R) battery modules to provide grid storage solutions to the market.

News Provided by ABN Newswire via QuoteMedia

Keep reading...Show less
Nevada Sunrise Initiates Data Review to Develop New Drill Targets at the Coronado Copper Project, Nevada

Nevada Sunrise Initiates Data Review to Develop New Drill Targets at the Coronado Copper Project, Nevada

Nevada Sunrise Metals Corporation (TSXV: NEV) (OTCBB: NVSGF) ("Nevada Sunrise" or the "Company") is pleased to announce that the Company has initiated a geological and geophysical data review on its Coronado Copper Project (" Coronado ", or the " Project ") located in Pershing County, Nevada approximately 48 kilometers (30 miles) southeast of Winnemucca . The purpose of the Coronado data review is to identify new, shallow drill targets in an area of the Project where historical drilling in 1976 identified high-grade copper mineralization.

Highlights of the Coronado Copper Project

News Provided by Canada Newswire via QuoteMedia

Keep reading...Show less
Century Lithium

Century Lithium Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

Latest Press Releases

Related News

×