Atico Mining Enters into an Agreement with the Colombian Government Over El Roble Property Royalty Dispute and Provides Update on the Title Renewal

Atico Mining Enters into an Agreement with the Colombian Government Over El Roble Property Royalty Dispute and Provides Update on the Title Renewal

Atico Mining Corporation (the "Company" or "Atico") (TSX.V: ATY | OTCQX: ATCMF) announces it has entered into an agreement (the "Agreement") with the National Mining Agency ("NMA") in Colombia related to the ongoing royalty dispute covering the El Roble property. While the Company has maintained that it has been in good standing with the requirements for a new title, with this agreement the company has formally been brought into good standing by the NMA.

As a part of the Agreement, the NMA and the Company have also agreed to settle the dispute via binding arbitration at the Center for Arbitration and Conciliation of the Bogota Chamber of Commerce for the purposes of seeking an expedited resolution to the ongoing claim, which is currently being resolved in Colombian courts where the proceedings can last several years. In contrast, the arbitration rules state the final decision by the tribunal takes approximately six to twelve months from the commencement of the arbitration process. To the extent that a final ruling is made in favor of the Company, the Payment Plan will cease, and any amounts already paid will be offset against future royalty obligations. As advised by its Colombian legal counsel, the Company continues to believe that it has a strong case for a positive outcome in an upcoming arbitration.

The Agreement calls for the Company to enter into a five-year Payment Plan, payable in biannual instalments for a total amount of approximately US$21.9 million plus interest at a 6% annual rate. The Company will make an initial upfront payment of US$1 million, followed by US$3.2 million in year 1, US$3.3 million in year 2, US$3.4 million in year 3, US$5.8 million in year 4 and US$9.7 million in year 5. The total amount payable represents all outstanding royalty payments which the NMA has claimed through to the end of December 2021. The parties have agreed to this interim arrangement until a final arbitration decision is made.

For this arrangement to comply with Colombian law, a secured guarantee equal to the value of the agreed payment plan is required. The Company intends to provide the required guarantee by granting security over 9,700 wet metric tonnes of concentrate. The security and the guarantee will be released proportionally as payments are made in accordance with the payment schedule. The security may be substituted for another type at a later date.

The Company continues to work towards renewing the title to the El Roble property claims which are set to expire on January 23, 2022. If the Company is unable to obtain the new title on time, it will continue operating after the expiration date while the process for the new title continues, as pronounced by the NMA in response to a formal query made by the company. Although the process for the new title is progressing favorably, there is no assurance at this stage that the Company will obtain a new title.

About Atico Mining Corporation

Atico is a growth-oriented Company, focused on exploring, developing and mining copper and gold projects in Latin America. The Company generates significant cash flow through the operation of the El Roble mine and is developing its high-grade La Plata VMS project in Ecuador. The Company is also pursuing additional acquisition of advanced stage opportunities. For more information, please visit www.aticomining.com .

ON BEHALF OF THE BOARD

Fernando E. Ganoza
CEO
Atico Mining Corporation

Trading symbols: TSX.V: ATY | OTCQX: ATCMF

Investor Relations
Igor Dutina
Tel: +1.604.633.9022

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

No securities regulatory authority has either approved or disapproved of the contents of this news release. The securities being offered have not been, and will not be, registered under the United States Securities Act of 1933, as amended (the ‘‘U.S. Securities Act''), or any state securities laws, and may not be offered or sold in the United States, or to, or for the account or benefit of, a "U.S. person" (as defined in Regulation S of the U.S. Securities Act) unless pursuant to an exemption therefrom. This press release is for information purposes only and does not constitute an offer to sell or a solicitation of an offer to buy any securities of the Company in any jurisdiction.

Cautionary Note Regarding Forward Looking Statements

This announcement includes certain "forward-looking statements" within the meaning of Canadian securities legislation. All statements, other than statements of historical fact, included herein, without limitation the terms of the payment plan, the timing of the arbitration proceedings, the belief that the Company has a strong case for a positive outcome in the royalty dispute, the intention to provide the required guarantee by granting security over 9,700 tonnes of concentrate, the potential for the guarantee of concentrate to be substituted for other security at a later date, the potential renewal of title to the claims comprising the El Roble property and the continuation of operations while a new contract is perfected and a new title is obtained , are forward-looking statements. Forward- looking statements involve various risks and uncertainties and are based on certain factors and assumptions.   There can be no assurance that such statements will prove to be accurate, and actual results and future events could differ materially from those anticipated in such statements. Important factors that could cause actual results to differ materially from the Company's expectations include uncertainties as to the timing and process for renewal of title to the El Roble claims; uncertainties relating to interpretation of drill results and the geology, continuity and grade of mineral deposits; uncertainty of estimates of capital and operating costs; the need to obtain additional financing to maintain its interest in and/or explore and develop the Company's mineral projects; uncertainty of meeting anticipated program milestones for the Company's mineral projects; the world-wide economic and social impact of COVID-19 is managed and the duration and extent of the coronavirus pandemic is minimized or not long-term; disruptions related to the COVID-19 pandemic or other health and safety issues, or the responses of governments, communities, the Company and others to such pandemic or other issues; and other risks and uncertainties disclosed under the heading "Risk Factors" in the prospectus of the Company dated March 2, 2012 filed with the Canadian securities regulatory authorities on the SEDAR website at www.sedar.com .   Readers should not place undue reliance on forward-looking statements, which speak only as of the date made. The forward-looking statements contained in this release represent our expectations as of the date of this release. We disclaim any intention or obligation or undertaking to update or revise any forward-looking statements whether as a result of new information, future events or otherwise, except as required under applicable securities laws.


Primary Logo

News Provided by GlobeNewswire via QuoteMedia

ATY:CA
The Conversation (0)
Atico Mining Announces Completion NI 43-101 Feasibility Study for the La Plata Project in Ecuador

Atico Mining Announces Completion NI 43-101 Feasibility Study for the La Plata Project in Ecuador

Atico Mining Corporation (the "Company" or "Atico") (TSX.V: ATY | OTC: ATCMF) is pleased to announce the results of the Definitive Feasibility Study (the "DFS" or the "Study") for its 100% owned La Plata Project ("La Plata") located in Ecuador. The DFS was prepared in accordance with the National Instrument 43-101 Standards of Disclosure for Mineral Projects ("NI 43-101"). Please note that all financial figures in this press release are in United States dollars, unless otherwise noted.

Key Highlights:

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
Atico Reports Consolidated Financial Results for First Quarter of 2024

Atico Reports Consolidated Financial Results for First Quarter of 2024

Atico Mining Corporation (the "Company" or "Atico") (TSX.V: ATY | OTC: ATCMF) today announced its financial results for the three months ended March 31, 2024, posting income from mining operations of $2.8 million and a net loss of $0.4 million. Production for the period at Atico's El Roble mine totaled 3.3 million pounds ("lbs") of copper and 2,185 ounces ("oz") of gold in concentrate at a cash cost (1) of $2.57 per payable pound of copper (2) .

Fernando E. Ganoza, CEO and Director, commented, "the operational and financial results for this quarter were in line with Company expectations. We are already into development of the newly discovered reserves and have been making additional investments in preparation for ore extraction from these areas." Mr. Ganoza continued, "for the remainder of the year, we should start to see an improvement in our operating costs as we progressively gain access to mining the upper areas of the mine, while at the same time the recent increase in metals prices, particularly in copper should be positively reflected in our revenue and margin."

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
Atico Produces 3.34 Million Pounds of Cu and 2,156 Ounces of Au in First Quarter 2024

Atico Produces 3.34 Million Pounds of Cu and 2,156 Ounces of Au in First Quarter 2024

Atico Mining Corporation (the "Company" or "Atico") (TSX.V: ATY | OTCQX: ATCMF) announces its operating results for the three months ended March 31, 2024 from its El Roble mine. Production for the quarter totaled 3.34 million pounds of copper and 2,156 ounces of gold in concentrates, an increase of 44% for copper and a decrease of 16% for gold, respectively, over the same period in 2023.

"The El Roble mine operated in line with set expectations for this quarter as we improved on almost all metrics over the same period last year," said Fernando E. Ganoza, CEO. "For the remainder of the year, the team will be focused on optimizing production to take advantage of the higher metal price environment and to deliver on this year's set guidance. In parallel, we continue to drill new high-grade resources in the mine vicinity target areas. These new areas will be incorporated into our mine plan as well as the new resource update which is planned to be published imminently."

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
Atico Reports Consolidated Financial Results for 2023

Atico Reports Consolidated Financial Results for 2023

(All amounts expressed in US dollars, unless otherwise stated)

Atico Mining Corporation (the "Company" or "Atico") (TSX.V: ATY | OTC: ATCMF) today announced its financial results for the year ended December 31, 2023, posting income from mining operations of $7.4 million and a net loss of $5.8 million. Production for the year at Atico's El Roble mine totaled 13.2 million pounds ("lbs") of copper and 10,149 ounces ("oz") of gold in concentrate at a cash cost ( 1) of $2.04 per payable pound of copper (2) .

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
Atico Reports Multiple High Grade Intercepts up to 20.70m of 5.76% Cu, 4.46 g/t Au and 11.50m of 8.16% Cu, 8.09 g/t Au and Continues to Extend the Ore Body at El Roble Mine in Colombia

Atico Reports Multiple High Grade Intercepts up to 20.70m of 5.76% Cu, 4.46 g/t Au and 11.50m of 8.16% Cu, 8.09 g/t Au and Continues to Extend the Ore Body at El Roble Mine in Colombia

Atico Mining Corporation (TSX.V: ATY | OTCQX: ATCMF) ("Atico" or the "Company") is pleased to announce positive results for the latest 49 drill holes being carried out in an area of historical mining to expand tonnage at the El Roble mine. In addition, the Company reports the results for sixteen diamond drill core holes (see first table below), which included 20.70m of 5.76% Cu, 4.46 gt Au and 11.50m of 8.16% Cu, 8.09 gt Au. Ore grade intercepts in another fourteen drill holes are also reported over narrower widths of approximately 1 to 2 meters in areas with limited drilling which highlights the possibility of further extending the ore body with additional drill programs.

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
Gianni Kovacevic, lithium-ion battery.

Gianni Kovacevic: 3 Copper Stocks for Speculators, Watch These Metals Under Trump

Investor and author Gianni Kovacevic shared his thoughts on copper market dynamics, saying that while the long-term trend is up, speculators can create significant shorter-term prices moves.

He also mentioned three copper companies he's interested in right now: CopperNico Metals (TSX:COPR,OTCQB:CPPMF), Entree Resources (TSX:ETG,OTCQB:ERLFF) and Horizon Copper (TSXV:HCU,OTCQX:HNCUF).

In addition to copper, Kovacevic spoke about the growing opportunity he sees in lithium, highlighting how major miners like Rio Tinto (ASX:RIO,NYSE:RIO,LSE:RIO) are increasing their exposure to this important battery metal.

Keep reading...Show less
Copper pipes laid on top of each other in bundles.

5 Best-performing Copper Stocks on the TSX in 2024

Copper prices surged in 2024, breaking the US$5.00 per pound barrier for the first time and setting an all-time high on the COMEX of US$5.20 per pound on May 20.

Prices have since retreated but have largely traded above the US$4.00 per pound mark and above the average price of US$3.83 per pound in 2023.

Copper demand remained high in energy transition sectors. However, it was also affected by bottlenecks at Chinese smelters, which cut production during the first half of the year due to low treatment charges.

Keep reading...Show less
VVC Resources (TSXV:VVC)

VVC Resources

Keep reading...Show less
S&P/TSX on ticker board.

FireFly Metals Gets Approval to Dual List on Toronto Stock Exchange

FireFly Metals (ASX:FFM,OTC Pink:MNXMF) announced plans to dual list on Wednesday (December 11) after receiving conditional approval to trade on the main board of the Toronto Stock Exchange (TSX).

It will use the symbol FFM, the same symbol it uses on the Australian Securities Exchange (ASX).

The copper- and gold-focused company is set to debut on the TSX on December 16.

Keep reading...Show less
Lobo Tiggre, copper bars.

Lobo Tiggre: Copper is My Highest-Confidence Trade for 2025 — Here's Why

Lobo Tiggre, CEO of IndependentSpeculator.com, gave the Investing News Network his updated thoughts on the US economy, as well as his outlook for gold, silver and uranium in 2025.

However, he said his highest-confidence trade for next year is copper.

"I think that it's easier to see — and highly likely to see — copper moving higher next year," Tiggre explained.

Keep reading...Show less
Large chunk of copper.

29Metals Shares Feasibility Study and Final Investment Decision for Gossan Valley Project

29Metals (ASX:29M) has announced a feasibility study and final investment decision for the Gossan Valley project at its Golden Grove volcanic-hosted massive sulphide mine in Western Australia.

The feasibility study is an update to the 2022 version of the document. It outlines production of 4,000 tonnes of copper and 20,000 tonnes of zinc annually at Gossan Valley over an initial mine life of seven years.

CEO James Palmer said the development of Gossan Valley is the "next logical development option" when it comes to moving forward at Golden Grove, which was first discovered in 1971.

Keep reading...Show less