Altiplano Metals Inc. (TSXV: APN) (WKN: A2JNFG) ("Altiplano" or the "Company") is pleased to report on quarterly results for Q3 2022 from the Farellon Copper-Gold-Iron (Cu-Au-Fe) mine located near La Serena, Chile.

During Q3, 2022, the Company extracted a total 13,440 tonnes of mineralized Cu-Au material at Farellon. This represents an increase of 25% from Q2 results of 10,742 tonnes with Q3 representing the highest quarterly production since operations began in 2018. Tonnes processed in Q3 represented 7,570 tonnes, up 1% from the previous quarter of 7,488 tonnes. The copper grade recovered was 1.87%, down 4.8% from the previous Q2 result of 1.96%. Waste removal in Q3 decreased by 56% to 1,199 tonnes in Q2 as focus returned to advancing production headings.

Sales of 297,400 pounds of copper generated approximately US$691,000 in revenue (after processing costs). While Q3 copper sales were generally in line with the previous quarter (down 4% from 310,0000), revenues were reduced by 35% based on the effect of copper prices falling to $3.51/pound compared to the previous Q2 average of $4.21/pound.

At the end of September 2022, the Company had 750 tonnes in stockpiles at the Farellon site and a total of 3,160 tonnes of stockpiles at the El Peñón mill site. In addition, the company currently has 1,738 tonnes of material in process with ENAMI. This material will be processed for sale and the revenue will be realized in the next coming months.

President and CEO Alastair McIntyre comments: "We are pleased to see operational improvements continue at Farellon, with Q3 production being its highest on record. This puts us on track to achieve full operational capacity at Farellon as El Peñón completes the commissioning process with full-scale processing transitioning to the plant. We are also pleased to reach another significant milestone: achieving US$10.5 mm in revenues from our total sales since operations began at Farellon."

Figure 1. Quarterly Review of US$ Revenue and Copper Pounds Sold

PeriodMinedUSD RevenueCu Pounds Sold
Q1 20182,520$148,20094,909
Q2 201810,269$210,492118,287
Q3 20186,298$274,499109,283
Q4 210811,365$695,386272,381
Q120198,075$589,098233,425
Q220196,935$578,282229,986
Q3 20195,643$460,273318,832
Q4 20195,968$381,427238,371
Q1 20205,557$320,960188,671
Q2 20209,075$431,906310,256
Q3 20209,660$831,241460,384
Q4 202011,685$576,386322,130
Q1 20219,770$540,713257,522
Q2 202110,090$599,711220,660
Q3 202111,624$561,345221,518
Q4 202111,189$779,054267,927
Q1 20229,843$908,419295,199
Q2 202210,742$967,685310,062
Q3 202213,440$691,323297,403
TOTAL169,748$10,546,400 4,767,208

 

Cannot view this image? Visit: https://images.newsfilecorp.com/files/4303/142424_altiplanofigure2_550.jpg

Figure 2. Mined, Processed, Waste Removed and Cu Grade by Quarter

To view an enhanced version of Figure 2, please visit:
https://images.newsfilecorp.com/files/4303/142424_altiplanofigure2.jpg

Cannot view this image? Visit: https://images.newsfilecorp.com/files/4303/142424_altiplanofigure3_550.jpg

Figure 3. Processed Material, Income vs. Mining Costs by Quarter

To view an enhanced version of Figure 3, please visit:
https://images.newsfilecorp.com/files/4303/142424_altiplanofigure3.jpg

Cannot view this image? Visit: https://images.newsfilecorp.com/files/4303/142424_1dfee8ca241da985_003.jpg

Figure 4. Farellon Mine Section

To view an enhanced version of Figure 4, please visit:
https://images.newsfilecorp.com/files/4303/142424_1dfee8ca241da985_003full.jpg

The decision to commence production on the Farellon deposit is not based on a feasibility study of mineral reserves demonstrating economic and technical viability and there is increased uncertainty and economic and technical risks of failure associated with the production decision

Mining activity during Q3, 2022, focused on the 360 m and 352 m levels where grade of this material has averaged approximately 1.95% copper to date in 2022. Widening of the first 150 m of the Hugo Decline has begun to improve the operational efficiency of the Farellon mine. This work will provide transit trucks to operate with greater efficiency thus reducing mining costs. The Hugo Decline continues the advance to the next production area at the 344 m level. To date 50 m of this work has been completed with the end of November targeted for completion.

Cannot view this image? Visit: https://images.newsfilecorp.com/files/4303/142424_1dfee8ca241da985_004.jpg

Figure 5. Trucks Loading for Shipment to Processing Facilities

To view an enhanced version of Figure 5, please visit:
https://images.newsfilecorp.com/files/4303/142424_1dfee8ca241da985_004full.jpg

Cannot view this image? Visit: https://images.newsfilecorp.com/files/4303/142424_1dfee8ca241da985_005.jpg

Figure 6. Jumbo at the Face of the 344 m Hugo Decline Advance

To view an enhanced version of Figure 6, please visit:
https://images.newsfilecorp.com/files/4303/142424_1dfee8ca241da985_005full.jpg

Altiplano has generated over US$10.5 million from the recovery and sale (after processing costs) of 4.77 million pounds of copper with an average grade of 1.78% Cu (2018 Q1-2022 Q3). Cash flow has been re-invested into equipment, underground drilling, expanding underground development at Farellon, enhancing ventilation to increase productivity and capacity, new underground development and exploration at Maria Luisa, and the commissioning of the El Peñón fit-for-purpose mill and flotation plant located 15 km from the Farellon site.

About Altiplano
Altiplano Metals is a growing gold, silver, and copper company focused on the Americas. The Company has a diversified portfolio of assets that include an operating copper/gold/iron mine, development near term producing gold/copper projects, and exploration land packages with district-scale potential. Altiplano is focused on creating long-term stakeholder value through developing safe and sustainable production, reinvesting into exploration, and pursuing acquisition opportunities to complement its existing portfolio. Management has a substantial record of success in capitalizing on opportunity, overcoming challenges and building shareholder value. Altiplano trades on the Toronto Venture Exchange trading under the symbol APN and the Frankfurt Exchange under the symbol A2JNFG.

John Williamson, B.Sc., P.Geol., a Qualified Person as defined by NI 43-101, has reviewed, and approved the technical contents of this document.

Altiplano is part of the Metals Group of companies. Metals Group is an award-winning team of professionals who stand for technical excellence, painstaking project selection and uncompromising corporate governance, with a proven ability to capitalize on investment opportunities and deliver shareholder returns.

www.metalsgroup.com

ON BEHALF OF THE BOARD

/s/ "John Williamson"
Chairman

For further information, please contact:
Alastair McIntyre, CEO
alastairm@apnmetals.com
Tel: (416) 434-3799

Jeremy Yaseniuk, Director
jeremyy@apnmetals.com
Tel: (604) 773-1467

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the (TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

This release includes certain statements that may be deemed "forward-looking statements". All statements in this release, other than statements of historical facts, that address exploration drilling, exploitation activities and events or developments that the Company expects are forward-looking statements. A qualified person has not done sufficient work to classify any historical estimates as current mineral resources or mineral reserves and the issuer is not treating the historical estimates as current mineral resources or mineral reserves. The Farellon mine was previously in production dating back to the 1970's with a reported historical production (to a depth of 70 m) yielding approximately 300,000 tonnes at an average grade of 2.5% copper and 0.5g/t gold. This material was processed locally and sold to ENAMI. Altiplano is relying upon past production records, underground sampling and related activities and current diamond drilling to estimate grade and widths of the mineralization to reactivate production. The decision to commence production on the Farellon deposit is not based on a feasibility study of mineral reserves demonstrating economic and technical viability and there is increased uncertainty and economic and technical risks of failure associated with any production decision. Although the Company believes the expectations expressed in such forward-looking statements are based on reasonable assumptions, such statements are not guarantees of future performance and actual results or developments may differ materially from those in the forward-looking statements. Factors that could cause actual results to differ materially from those in forward-looking statements include market prices, exploitation and exploration successes, continuity of mineralization, uncertainties related to the ability to obtain necessary permits, licenses and title and delays due to third party opposition, changes in government policies regarding mining and natural resource exploration and exploitation, and continued availability of capital and financing, and general economic, market or business conditions. Investors are cautioned that any such statements are not guarantees of future performance and actual results or developments may differ materially from those projected in the forward-looking statements. For more information on the Company, investors should review the Company's continuous disclosure filings that are available at www.sedar.com.

To view the source version of this press release, please visit https://www.newsfilecorp.com/release/142424

News Provided by Newsfile via QuoteMedia

APN:CA
The Conversation (0)
Altiplano Reports Q4 Operational Results with 2.05% Copper Grade at Farellon

Altiplano Reports Q4 Operational Results with 2.05% Copper Grade at Farellon

Altiplano Metals Inc. (TSXV: APN) (WKN: A2JNFG) ("Altiplano" or the "Company") is pleased to report on quarterly results for Q4 2022 from the Farellon Copper-Gold-Iron (Cu-Au-Fe) mine located near La Serena, Chile.

During Q4, 2022, the Company extracted a total 11,340 tonnes of mineralized Cu-Au material at Farellon. This represents a decrease of 15% from the record Q3 results of 13,440 tonnes. Tonnes processed in Q4 represented 6,804 tonnes, down 10% from the previous quarter of 7,570 tonnes. The copper grade recovered was 2.05%, up 10% from the previous Q3 result of 1.87%. Waste removal increased by 18.5% to 1,422 tonnes in Q4 as the decline advanced to the lower 344 levels. Sales of 295,397 pounds of copper generated approximately US$691,000 in revenue (after processing costs). Q4 copper sales and revenue were in line with the previous quarter supported by higher copper grades.

News Provided by Newsfile via QuoteMedia

Keep reading...Show less
2023 New Year Greetings and Update from Alastair McIntyre CEO - Altiplano Metals Inc

2023 New Year Greetings and Update from Alastair McIntyre CEO - Altiplano Metals Inc

Altiplano Metals Inc. (TSXV: APN) (WKN: A2JNFG) ("Altiplano" or the "Company") is pleased to provide a summary of the Company's activity in 2022 and forward-looking activities for 2023 from the Company CEO Alastair McIntyre.

Happy New Year to our shareholders, stake holders, service providers and followers of Altiplano Metals Inc. I wish you the best for 2023 and thank you for your continued support. 2023 is shaping up to be an exciting year of new milestones and company growth.

News Provided by Newsfile via QuoteMedia

Keep reading...Show less
Altiplano Reports November 2022 Results at Farellon with Copper Grade at 2.10%

Altiplano Reports November 2022 Results at Farellon with Copper Grade at 2.10%

Altiplano Metals Inc. (TSXV: APN) (WKN: A2JNFG) ("Altiplano" or the "Company") is pleased to report on the November 2022 operating results from the Farellon Copper-Gold (Cu-Au) mine located near La Serena, Chile.

During the month of November, approximately 4,110 tonnes of mineralized copper-gold material was produced at Farellon with approximately 2,950 tonnes shipped and processed. The November production represents an increase of 2.5% over the October output of 4,010 tonnes. Processing in November increased by 23.5% over the October figure of 2,390 tonnes processed. The copper grade at Farellon observed in November at 2.10%, represents an improvement from the 1.87% observed in October and represents the second highest monthly grade in 2022 and 3rd highest overall. Increased production and good copper grades generated the second highest amount of copper sales from Farellon on record in November at 131,153 pounds.

News Provided by Newsfile via QuoteMedia

Keep reading...Show less
Altiplano Reports on Establishing New 344 m Mining Level at Farellon

Altiplano Reports on Establishing New 344 m Mining Level at Farellon

Altiplano Metals Inc. (TSXV: APN) (WKN: A2JNFG) ("Altiplano" or the "Company") is pleased to report the intersection of the 344 m mining level as part of the ongoing underground development of the Hugo Decline at the Farellon copper gold mine located near La Serena, Chile.

Cross cuts on the 344 m mining level have intersected the Farellon Iron Oxide Copper Gold vein structure with production headings now established on the northeast and southwest directions. Mining in this area has begun along with benching operations continuing between the roofs and floors of the 352 m and 360 m levels. Further development of the Hugo Decline to the 336 m level is expected to begin in the next four weeks with a time frame of approximately eight weeks to reach the new targeted intersection. In addition, the Company is planning an underground drill program in the new year to intersect drill targets below the current workings. This program will be designed to increase the geological confidence by extending the drilling intercepts in the Farellon vein system at depth and along strike.

News Provided by Newsfile via QuoteMedia

Keep reading...Show less
Altiplano Closes Second Tranche of Private Placement and Extends Warrants

Altiplano Closes Second Tranche of Private Placement and Extends Warrants

Altiplano Metals Inc. (TSXV: APN) (WKN: A2JNFG) ("Altiplano" or the "Company") is pleased to announce that it has closed the second tranche of its non-brokered private placement (the "Offering") of 1,625,000 units (the "Units") at $0.20 per Unit for $325,000 in gross proceeds. Each Unit consists of one (1) common share of the Company, and one-half (12) non-transferable share purchase warrant (the "Warrants") to acquire one (1) additional common share at a price of C$0.30 per share for a period of two years.

Certain arm's length finders received cash fees of $3,290 and 16,450 finders warrants, issued on the same terms as the Warrants in the Offering. All the securities issued in this second tranche will be subject to resale restrictions until February 17, 2023.

News Provided by Newsfile via QuoteMedia

Keep reading...Show less
Arch Biopartners Receives Funding for Development of LSALT Peptide Drug Program

Arch Biopartners Receives Funding for Development of LSALT Peptide Drug Program

Today, ARCH Biopartners Inc., ("ARCH" or the "Company") (TSX Venture: ARCH and OTCQB: ACHFF), a clinical stage company focused on the development of novel therapeutics targeting organ inflammation, announced that ARCH is receiving advisory services and up to $4,000,000 in funding from the National ReseARCH Council of Canada Industrial ReseARCH Assistance Program ("NRC IRAP") to support the reseARCH and development of the LSALT peptide (Metablok) program. LSALT peptide is the Company's lead drug candidate for treating acute inflammation injury in the lungs, kidneys and liver.

The research and development funding from NRC IRAP will help support several sub-tasks needed to advance the LSALT peptide drug program. These include: dose escalation studies; costs incurred by Arch during the Canadian Treatments for COVID-19 Phase III human trial; manufacturing new drug product supply to support future non-COVID human trials; the non-COVID Phase II trials (such as a cardiac surgery associated acute kidney injury trial) to gather more human data to support future drug approval; and, additional non-clinical studies to discover potential biomarkers and to further understand the mechanism of action related to LSALT peptide.

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
Auric Mining

Brisbane Mining Conference Presentation

Auric Mining Limited (ASX: AWJ) (Auric or the Company) is pleased to advise Managing Director, Mark English, will be presenting at the Brisbane Mining Conference today at 10.15am (AEST) / 8:15am (AWST).

Keep reading...Show less
Firebird Metals

Firebird Grows Oakover Indicated Resource By 80% To 105.8 Million Tonnes

Firebird Metals Limited (ASX: FRB) (“Firebird” or “the Company”) is pleased to announce a significant Resource upgrade at its flagship Oakover Manganese Project, which is located 85km East of Newman in the Eastern Pilbara region of Western Australia.

Keep reading...Show less
Belararox Limited

BelaraRox Limited (ASX: BRX) – Trading Halt

Description

The securities of BelaraRox Limited (‘BRX’) will be placed in trading halt at the request of BRX, pending it releasing an announcement. Unless ASX decides otherwise, the securities will remain in trading halt until the earlier of the commencement of normal trading on Friday, 24 March 2023 or when the announcement is released to the market.

Keep reading...Show less

Latest Press Releases

Related News

×