Galena Mining

Abra Construction At 92% Complete – Reaches First Ore Underground

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 92% complete as of 31 October 2022. Underground mine has reached the first ore (see ASX announcement 14 November 2022) and plant commissioning continues in several key areas with the project focussed on achieving first concentrate production in Q1 2023.

Managing Director, Tony James commented, “Reaching first ore underground is extremely rewarding for everyone involved in the project. To see for the first time what we have predicted and interpreted as the Abra orebody delivers a significant step forward for the project. Record development metres in October has taken the mine to the ore and we continue to establish key underground infrastructure with the completion of the 6m diameter surface rise that will be the primary return airway.”

Update on Abra Project progress

Overall progress continues to remain in line for Project completion, with first commercial production expected in Q1 CY2023. The processing plant engineering, procurement and construction has reached 97% complete. Structural steel has been completed in October and mechanical installations are at 96% complete. Piping at 80% and electrical at 71% complete continue to progress quickly.

Pacific Energy’s Hybrid 10MW LNG/solar power station completed full integration with the solar power supply, dry commissioning of the crushing and screening areas was completed in early November and first rock crushing is scheduled for late November. Grinding section dry and wet commissioning will commence in the second half of November and is planned for completion by mid-December. The remaining commissioning schedule is unchanged from the last update and is shown below in Table 1.

Mine decline development continued during October. A total of 311m was developed with the decline reaching 1,284mRL. October represents the highest individual development month since the first cut was fired in the portal in October 2021. The decline location is 266m vertically below the surface and is 29m vertically below the original top of the orebody (1313mRL). Underground drilling has now identified mineralisation as high as 1330mRL which is currently being reviewed for potential extraction. The 1300mRL ore access drive reached first ore in early November (See ASX announcement 14 November 2022).

The 1290mRL horizon is a significant work area for development as underground infrastructure for pumping, ventilation, second means of egress and power are all distributed from this level outwards into the development network. All this infrastructure is currently being established and will result in an increased focus on lateral development and lower decline development in the short term.


Click here for the full ASX Release

This article includes content from Galena Mining, licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.

G1A:AU
The Conversation (0)
Galena Mining

Abra Construction At 97% Complete – First Ore Stockpiled For January Processing

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 97% complete as of 30 November 2022. Processing plant commissioning is progressing quickly with practical completion now expected in December 2022. Ore currently being mined from underground is being stockpiled in readiness for processing to begin in January 2023. Concentrate production will commence January 2023.

Keep reading...Show less
Galena Mining

Abra Mine Reaches Ore

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the underground development at its Abra Base Metals Mine (“Abra” or the “Project”) has reached the Abra orebody. Commissioning has commenced in several key areas of the processing facility and the Power Station (Pacific Energy) completed full integration of the hybrid gas/solar/battery energy storage system (BESS) power station on 10 November. The project remains on track for first concentrate production in Q1 2023.
Keep reading...Show less
Galena Mining

Galena Mining Activities Report For Quarter Ended 30 September 2022

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) reports on its activities for the quarter ended 30 September 2022 (the “Quarter”), primarily focused on construction of its 60%- owned Abra Base Metals Mine (“Abra” or the “Project”) located in the Gascoyne region of Western Australia.

Keep reading...Show less
Silver bars with silver graph going up.

When Will Silver Go Up?

It’s no secret that the silver market can be incredibly volatile. From February 2024 to February 2025 alone, silver has seen price levels ranging from lows of US$22.42 per ounce to highs of US$34.72 per ounce.

Many investors are highly focused on the precious metal’s movement. After all, silver is a safe-haven asset that generally fares well during turmoil, and recent times have been packed with tense geopolitical events, environmental disasters and economic uncertainty. While it's trended up over the last 12 months, silver has struggled to maintain the US$30 level.

Why is silver going up? With the support of looming lower interest rates, lower holding costs for bullion, increased central bank interest in precious metals, and the threat of trade wars under US President Donald Trump, the price of silver is trading at highs not seen in nearly decade. But, can silver go even higher? And when?

Answering the question, “When will silver go up?” is tricky. Even seasoned analysts can’t tell the future, and it’s difficult to find a consensus on the topic of when the metal could take off.

Keep reading...Show less
Rows of silver bars with two bars lying on top.

ASX Silver Stocks: 5 Biggest Companies

Silver is often compared to gold due to its importance in jewellery and as a safe-haven investment.

However, silver has many industrial applications too, including in electronics, automobiles and silverware, as well as medicine and photography. Energy transition applications are a growing demand sector for silver too — the metal is valued for its conductive capacity, which makes it particularly useful in the production of photovoltaic panels.

Silver supply has tightened in recent years as industrial demand rises. This was one of several factors that helped the silver price break through the US$34 per ounce mark in October of this year for the first time since 2012.

Keep reading...Show less

SilverCrest Closes Arrangement with Coeur Mining

TSX: SIL | NYSE American: SILV

 SilverCrest Metals Inc. ("SilverCrest" or the "Company") is pleased to announce the completion of the previously announced plan of arrangement (the "Arrangement") involving the Company and Coeur Mining, Inc. ("Coeur"), pursuant to which Coeur indirectly, among other things, acquired all of the issued and outstanding SilverCrest shares (the "SilverCrest Shares").

News Provided by Canada Newswire via QuoteMedia

Keep reading...Show less
Silver bar and metal.

5 Top Canadian Silver Stocks of 2025

Silver-mining companies and juniors have seen support from a strong silver price in 2025. The white metal has gained steadily since the start of the year, rising 11.47 percent to breach the US$32 per ounce mark.

Silver’s dual function as a monetary and industrial metal offers great upside. Demand from energy transition sectors, especially for use in the production of solar panels, has created tight supply and demand forces.

Demand is already outpacing mine supply, making for a positive situation for silver-producing companies.

Keep reading...Show less

First Majestic Announces 2025 Production and Cost Guidance and Announces Conference Call Details

First Majestic Silver Corp. (NYSE: AG) (TSX: AG) (FSE: FMV) (the "Company" or "First Majestic") is pleased to announce the Company's consolidated 2025 production and cost guidance for the Company's four producing underground mines in Mexico, namely the Cerro Los Gatos Silver Mine (the Company holds a 70% interest in the Los Gatos Joint Venture that owns the mine), the Santa Elena SilverGold Mine, the San Dimas SilverGold Mine, and the La Encantada Silver Mine. The Company will be holding a conference call with management at 8:30 a.m. (PT) on Thursday, February 20, 2025, to discuss First Majestic's 2024 financial results and 2025 production and cost guidance.

News Provided by Newsfile via QuoteMedia

Keep reading...Show less

First Majestic Announces 2025 Production and Cost Guidance and Announces Conference Call Details

First Majestic Silver Corp. (NYSE: AG) (TSX: AG) (FSE: FMV) (the "Company" or "First Majestic") is pleased to announce the Company's consolidated 2025 production and cost guidance for the Company's four producing underground mines in Mexico, namely the Cerro Los Gatos Silver Mine (the Company holds a 70% interest in the Los Gatos Joint Venture that owns the mine), the Santa Elena SilverGold Mine, the San Dimas SilverGold Mine, and the La Encantada Silver Mine. The Company will be holding a conference call with management at 8:30 a.m. (PT) on Thursday, February 20, 2025, to discuss First Majestic's 2024 financial results and 2025 production and cost guidance.

News Provided by Newsfile via QuoteMedia

Keep reading...Show less

Latest Press Releases

Related News

×