Galena Mining

Abra Construction At 92% Complete – Reaches First Ore Underground

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 92% complete as of 31 October 2022. Underground mine has reached the first ore (see ASX announcement 14 November 2022) and plant commissioning continues in several key areas with the project focussed on achieving first concentrate production in Q1 2023.

Managing Director, Tony James commented, “Reaching first ore underground is extremely rewarding for everyone involved in the project. To see for the first time what we have predicted and interpreted as the Abra orebody delivers a significant step forward for the project. Record development metres in October has taken the mine to the ore and we continue to establish key underground infrastructure with the completion of the 6m diameter surface rise that will be the primary return airway.”

Update on Abra Project progress

Overall progress continues to remain in line for Project completion, with first commercial production expected in Q1 CY2023. The processing plant engineering, procurement and construction has reached 97% complete. Structural steel has been completed in October and mechanical installations are at 96% complete. Piping at 80% and electrical at 71% complete continue to progress quickly.

Pacific Energy’s Hybrid 10MW LNG/solar power station completed full integration with the solar power supply, dry commissioning of the crushing and screening areas was completed in early November and first rock crushing is scheduled for late November. Grinding section dry and wet commissioning will commence in the second half of November and is planned for completion by mid-December. The remaining commissioning schedule is unchanged from the last update and is shown below in Table 1.

Mine decline development continued during October. A total of 311m was developed with the decline reaching 1,284mRL. October represents the highest individual development month since the first cut was fired in the portal in October 2021. The decline location is 266m vertically below the surface and is 29m vertically below the original top of the orebody (1313mRL). Underground drilling has now identified mineralisation as high as 1330mRL which is currently being reviewed for potential extraction. The 1300mRL ore access drive reached first ore in early November (See ASX announcement 14 November 2022).

The 1290mRL horizon is a significant work area for development as underground infrastructure for pumping, ventilation, second means of egress and power are all distributed from this level outwards into the development network. All this infrastructure is currently being established and will result in an increased focus on lateral development and lower decline development in the short term.


Click here for the full ASX Release

This article includes content from Galena Mining, licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.

G1A:AU
The Conversation (0)

Galena Mining

Galena Mining CEO Tony James said, “People have been just sitting and watching how we would perform this year, a perceived difficult construction period. But we've done a great job."

Galena Mining CEO Tony James said, “People have been just sitting and watching how we would perform this year, a perceived difficult construction period. But we've done a great job." Keep Reading...
Galena Mining

Abra Construction At 97% Complete – First Ore Stockpiled For January Processing

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 97% complete as of 30 November 2022. Processing plant commissioning is progressing quickly with practical completion... Keep Reading...
Galena Mining

Abra Mine Reaches Ore

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the underground development at its Abra Base Metals Mine (“Abra” or the “Project”) has reached the Abra orebody. Commissioning has commenced in several key areas of the processing facility and the Power Station... Keep Reading...
Galena Mining

Galena Mining Activities Report For Quarter Ended 30 September 2022

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) reports on its activities for the quarter ended 30 September 2022 (the “Quarter”), primarily focused on construction of its 60%- owned Abra Base Metals Mine (“Abra” or the “Project”) located in the Gascoyne region of Western... Keep Reading...
  Unico Silver Limited

La Negra SE delivers exceptional drill results

JDD113-25 returns 107m at 165gpt AgEq from 18m, the best hole for 2025.

Unico Silver Limited (“USL” or the “Company”) is pleased to report assay results for 31 holes (4,782m) as part of an ongoing drill program at the Company’s 100%-owned Joaquin Project in Santa Cruz, Argentina. HIGHLIGHTSInfill and extensional drilling at La Negra SE confirms broad, shallow zone... Keep Reading...
David Morgan, silver bars.

David Morgan: Silver's Price Breakout — What's Next, Key Drivers

David Morgan, publisher of the Morgan Report, weighs in on silver's record-setting price rise and what could be next for the white metal heading into 2026. "We're still in price discovery. I truly believe that," he said. "What the true price of silver is in US dollars, Canadian dollars, I do not... Keep Reading...
Stacked coins with 2026 blocks and upward arrow representing growth and goals.

9 Experts Share Highest-Conviction Sectors for 2026

2026 has begun, and the Investing News Network (INN) is looking forward to the new year. To kick it off, our team asked nine experts to share their highest-conviction sectors. Here's what they had to say.Want more YouTube content? Check out our expert market commentary playlist, which features... Keep Reading...
Futuristic 3D holographic visualization of resource and geophysical data analysis.

From Data to Discovery: How AI is Changing the Face of Modern Mining

Mineral exploration is one of the riskiest and most capital-intensive phases of the mining lifecycle. The process has traditionally relied heavily on historical geological records, field surveys and extensive drilling, often with low success rates and long time horizons. But a new wave of... Keep Reading...
Silver bar stamped surrounded by silver nuggets.

Top 5 Silver News Stories of 2025

Silver’s 2025 breakout marked one of the metal’s most decisive shifts in more than a decade.As the price pushed through longstanding resistance, investors, miners and policymakers reassessed its role in global markets, allowing silver to reassert itself as not only an industrial metal, but also... Keep Reading...
Silver bars in front of newspaper showing high price performance.

What Was the Highest Price for Silver?

Like its sister metal gold, silver has been attracting renewed attention as a safe-haven asset. Although silver continues to exhibit its hallmark volatility, a silver bull market is well underway in 2025. Experts are optimistic about the future, and as the silver price's momentum continues in... Keep Reading...

Interactive Chart

Latest Press Releases

Related News