
February 13, 2024
Deepest hole to date demonstrates substantial high-grade growth potential as drilling continues to deliver exceptional results on multiple fronts
Spartan Resources Limited (“Spartan” or “Company”) (ASX: SPR) is pleased to report updated drilling and assay information from recent drilling completed towards the end of 2023 and into 2024 at its 100%- owned Dalgaranga Gold Project (“DGP”) in the Murchison region of Western Australia.
Highlights:
Never Never Gold Deposit:
- 20.5m of “typical” Never-Never-style mineralisation, with indicative heavy silicification and biotite-chlorite alteration, logged from 871.5m down-hole in DGDH052 (pending assays), including small specs of visible gold logged at 878.7m down-hole.
- The intercept is located down-plunge and more than 170m below the current 952koz MRE extent, highlighting the exceptional growth potential of the Never Never deposit at depth.
- Additional significant new Never Never assay results include:
- 25.17m @ 6.59g/t gold from 448.3m down-hole, including:
- 7.5m @ 13.52g/t – DGDH050 (de-risks key area of high-metal content in MRE)
- 170.0m @ 4.13g/t gold from surface – DGRC1396 (open-pit to underground metallurgical test-work drill-hole, drilled at 75º dip down-plunge through the Never Never orebody, not true width).
- 25.17m @ 6.59g/t gold from 448.3m down-hole, including:
Four Pillars Gold Prospect – new high-grade gold intercept:
- 15.0m @ 6.06g/t gold from 358.0m down-hole, including:
- 3.00m @ 23.65g/t – DGDH046 (outside MRE, deepest assay at Four Pillars to date)
Sly Fox Gold Deposit – new high-grade gold intercept:
- 23.83m @ 2.44g/t gold from 379.0m down-hole, including:
- 5.00m @ 5.23g/t – DGRC1382 (towards base of existing Inferred MRE)
Note: Visual estimates of mineral abundance should never be considered a proxy or substitute for laboratory analyses where concentrations or grades are the factor of principal economic interest. Visual estimates also potentially provide no information regarding impurities or deleterious physical properties relevant to valuations. Core processing is currently underway, with assay results expected in early March.
Management Comment
Spartan Managing Director and Chief Executive Officer, Simon Lawson, said: “At the start of the year, we sat down as a geology team at Dalgaranga to reflect on what had been an absolutely massive 2023 and to discuss the future! What targets did we want to drill, what did the Company need to successfully execute the next stage of its growth strategy, and where did Spartan want to be in 12 months?
“We discussed how establishing almost a million high-grade gold ounces at Never Never while doubling the ounces and tripling the resource grade for the overall project might be a hard act to follow!
“As a group we agreed that we have just scratched the surface of the potential that could exist at Dalgaranga. Given our growing understanding of the mineralising systems and the larger potential we were beginning to see at depth at several key deposits as 2023 drew to a close, for 2024 we are following those leads and keeping our strategy simple.
“Our strategy for 2024 is simple: Drill and de-risk.
“Drilling at the key high-grade Never Never Gold Deposit is targeting more rapid high-grade resource growth by mid-2024, and with our first deep hole already hitting more than 20m of typical highly silicified and altered Never-Never-style mineralisation at 878m down-hole, including specs of visible gold, I’d say we’re already well on the way towards achieving that objective!
“We are also drilling to de-risk Never Never by targeting conversion of more than 85% of the current MRE ounces to Indicated classification. This drilling is designed to provide increased grade, volume and metal content confidence to the Spartan engineering team.
“Our drilling and de-risking includes ongoing metallurgical test-work from drill-holes designed and drilled specifically for this purpose. This drilling is yielding crucial information for our ongoing Ore Reserve and Feasibility Study work.
“A recent example is metallurgical drill-hole DGRC1396, drilled inside the Never Never Gold Deposit MRE and potential open pit, which returned a spectacular gold assay of 170m @ 4.13g/t from surface to the footwall contact. This result, while not useful in a resource estimation sense due to its sub-vertical drill angle, gives a useful insight into the down-plunge gold grade variability through any number of open-pit to underground design scenarios for the Never Never Gold Deposit.
“More broadly, we are drilling and de-risking at an operational scale by targeting relatively shallow existing and historic high-grade gold prospects as near-term potential ore feed sources. The Four Pillars and West Winds Gold Prospects continue to yield wide, higher grade drill intercept grades, increasing geological confidence and de-risking open pit scenarios for the former Gilbey’s Mine Complex.
“We have also re-commenced drilling in earnest at the Sly Fox Gold Deposit which, prior to the discovery of the high-grade Never Never Gold Deposit, was the highest-grade gold prospect at Dalgaranga. Sitting less than 2km from the process plant and on granted Mining Leases, we drilled a couple of test holes into Sly Fox late in 2023.
“One of those holes, DGRC1382-DT, which was designed to test the veracity of previous geological interpretations, recently returned 23.83m @ 2.44g/t gold, including 5m @ 5.23g/t from near the very base of the declared Mineral Resource. This latest assay result, along with several recently completed 2024 drill-holes currently awaiting assays, have tested the previous geological interpretation, intersecting wide mineralised intervals well outside any previous resource interpretation and validating Sly Fox as a legitimate high-grade priority target for 2024.
“Spartan has a full set of priority drill targets for 2024. Our strategy is to drill and de-risk our assets through increased geological confidence and orebody knowledge. As we continue this process, we not only grow the potential value of our existing high-grade gold assets in front of our 100%-owned process plant and infrastructure, we also increase confidence in and de-risk the Spartan investment proposition for all our shareholders.”
Click here for the full ASX Release
This article includes content from Spartan Resources Limited, licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.
SPR:AU
The Conversation (0)
16h
Horn Island Mining Lease Application Registered
23h
Gold Majors Ride Price Surge to Strong Q2 Earnings
The world’s top gold producers delivered a string of robust second-quarter results, buoyed by record prices and resilient operations as investors continue to seek refuge in the yellow metal amid growing economic uncertainty.
With spot gold trading above US$3,400 per troy ounce, just shy of its April all-time high of US$3,448.50, the world’s largest gold producers posted higher earnings and stronger cash flow in their recent Q2 results.
Below is a breakdown of how a few major players fared in Q2.
Barrick nearly doubles profit margins
Barrick Mining (TSX:ABX,NYSE:B) formerly Barrick Gold, reported a 97 percent year-on-year jump in net income to US$1.25 billion for the quarter, compared to US$634 million a year earlier.
Earnings per share rose to US$0.47 while operating cash flow in the first half reached US$2.5 billion, up 32 percent from 2024. Free cash flow more than doubled to US$770 million, supported by higher commodity prices.
Gold production climbed 5 percent from the first quarter, while copper output surged 34 percent, led by strong performance at Zambia’s Lumwana mine. Nevada Gold Mines boosted output by 11 percent, while Pueblo Viejo in the Dominican Republic posted a 28 percent increase as expansion work in the site advanced.
“From the ramp-up at Goldrush to the progress at Pueblo Viejo, Lumwana and Reko Diq, not to mention the transformational potential of Fourmile, we’re demonstrating the strength and depth of our portfolio,” president and chief executive Mark Bristow said in the recent Q2 report.
The company also recently agreed to sell its Alturas Project in Chile to a Boroo subsidiary for US$50 million upfront plus a royalty, with proceeds earmarked for funding future ventures
Kinross outpaces gold price gains
Kinross Gold Corporation (TSX:K,NYSE:KGC) posted record attributable free cash flow of US$646.6 million in the second quarter, alongside operating cash flow of US$992.4 million. Adjusted net earnings jumped to US$541 million from US$174.7 million a year earlier.
Further, the company achieved a 21 percent margin increase from the first quarter, outpacing the 15 percent rise in gold prices over the same period.
“Our portfolio of mines continued to perform well during the quarter contributing to a strong first half of the year and positioning us well to achieve our full-year guidance,” CEO J. Paul Rollinson said.
Kinross said that it expects to produce 2 million gold-equivalent ounces in 2025 at an average production cost of US$1,120 per ounce.
Paracatu in Brazil was the company’s top-producing asset, while Tasiast in Mauritania began mining the Fennec satellite deposit. US-based Bald Mountain also reported higher output at lower costs.
The company also advanced key projects, including its Great Bear exploration program in Ontario, engineering work at Round Mountain Phase X in Nevada, and drilling at the Curlew Basin project in Washington.
Agnico Eagle delivers, shares gain
Agnico Eagle's (TSX:AEM,NYSE:AEM) operational consistency and cost control helped drive a six-day share price rally, culminating in a 10.06 percent gain over the past week.
In the second quarter, the company produced 866,029 ounces of gold, maintaining full-year guidance of 3.3 to 3.5 million ounces. Adjusted earnings per share came in at US$1.94, prompting analysts to raise 2025 profit forecasts by US$0.70 to US$6.94.
Analysts cited the company’s steady performance despite rising unit costs, noting its appeal as a defensive play in the sector. Bank of America raised its price target to US$173 due to rising optimism about the firm’s growth prospects.
Newmont rides sector momentum
Newmont (TSX:NGT,NYSE:NEM) posted higher sales and net income for the quarter while authorizing a new share repurchase program and declaring a quarterly dividend.
The miner also renewed a key lease in Ghana. Shares rose 36 percent over the last quarter, outpacing the US Metals and Mining industry’s 24.1 percent return.
The performance came despite a drop in the company’s gold production. Rather, Newmont underscored the role of shareholder returns and strategic asset moves in supporting investor sentiment. Over the past three years, Newmont has delivered a total shareholder return of 63.75 percent.
Gold outlook: Gold shines during volatility
The sector’s strong quarter unfolded against a favorable macro backdrop.
Gold, which has gained about 30 percent year-to-date, has been buoyed by safe-haven flows. The metal’s latest rally began after spot prices dipped to US$3,311.80 in early August, then climbed back above US$3,418 by the first week of August..
The Federal Reserve cut rates by a full percentage point in late 2024 but has held steady this year, citing the need for more data on how tariffs affect inflation. Lower rates generally enhance gold’s appeal by reducing the opportunity cost of holding non-yielding assets..
Don't forget to follow us @INN_Resource for real-time news updates!
Securities Disclosure: I, Giann Liguid, hold no direct investment interest in any company mentioned in this article.
Keep reading...Show less
14 August
High-Grade Channel Samples at Antimony Canyon Project - Utah
13 August
GMV Minerals Inc. Announces Updated PEA Results at Mexican Hat Gold Project in S.E. Arizona
GMV Minerals Inc. (the "Company" or "GMV") (TSXV:GMV)(OTCQB:GMVMF) is pleased to announce positive results from the updated Preliminary Economic Assessment ("PEA") study of the Mexican Hat Gold Project (the "Mexican Hat Project"), located in Cochise County, southeastern Arizona.
A National Instrument 43-101 -Standards of Disclosure for Mineral Projects ("NI 43-101") compliant technical report (the "Report") entitled "Updated NI 43-101 Technical Report Preliminary Economic Assessment, Mexican Hat Project" with an effective date of August 8, 2025 will be filed on SEDAR+ at www.sedarplus.ca under the Company's profile within 45 days of this news release. All amounts are stated in second quarter 2025 US dollars (US$).
The Mexican Hat hosts a shallow oxide gold resource with excellent metallurgy and high recoveries, supported by a low strip ratio and minimal pre-stripping. Infrastructure is in place and the Mexican Hat Project demonstrates a robust NPV and IRR. With fast leach kinetics and low reagent consumption, the Company believes the Mexican Hat Project offers exceptional potential economics.
Highlights:
- The Base Case generates a pre-tax Internal Rate of Return ("IRR") of 66.1% (after-tax 50.2%) and a pre-tax net present value ("NPV") at a 5% discount rate of US$390.2 million (after-tax US$268.3 million) with a 1.53 year payback (1.82 year after-tax) of invested capital using a US$2,500 per ounce gold price.
- Based on price sensitivity analysis at approximately the current price of US$3,350 per ounce of gold, the project returns a pre-tax IRR of 106.8% (after-tax 82.5%) and a pre-tax NPV at a 5% discount rate of US$767 million (after-tax US$538.1 million) with a payback period of 1.10 years (1.3 years after-tax).
- Base Case mine life of 10 years with total production of 597,841 ounces, averaging approximately 60,000 ounces per year.
- Crushed mineralized material will be conveyor stacked at a rate of approximately 10,000 tonnes/day on a conventional heap leach pad.
- Capex: US$89,997,000 (including US$15.4 million contingency).
- Opex: US$788 million LOM with Low LOM Strip Ratio of 2.05
- Estimated cash cost of production is US$1,354 per ounce with an all-in-sustaining cost of $1,545 per ounce inclusive of sustaining capital and additional overhead support.
- Engineering design analysis indicates the potential to increase pit size and contained ounces with increased gold prices.
FINANCIAL INDICATORS
The following table summarizes the financial indicators for the Mexican Hat Project for both before and after taxes.
Financial Indicators Before Taxes | Values |
NPV cash flow (undiscounted) | US$537.7M |
NPV @ 5% | US$390.2M |
IRR % | 66.1% |
Payback (years) | 1.53 |
Financial Indicators After Taxes | Values |
NPV cash flow (undiscounted) | US$377.9M |
NPV @ 5% | US$268.3M |
IRR % | 50.2% |
Payback (years) | 1.82 |
GOLD PRICE SENSITIVITY TABLE (US$ MILLIONS)
The following table summarizes the pre-tax and post-tax economic results to gold price sensitivity.
Pre-Tax and Post-Tax Sensitivity to Gold Price
-60% | -45% | -30% | -15% | Base | +15% | +34% | +45% | +60% | |
US$/troy oz Gold | 1,000 | 1,375 | 1,750 | 2,125 | 2,500 | 2,875 | 3,350 | 3,625 | 4,000 |
IRR (Pre-Tax) | 18.3% | 45.0% | 66.1% | 85.0% | 106.8% | 118.7% | 134.2% | ||
NPV @ 5% (Pre-Tax) US$M | -274.7 | -108.5 | 57.7 | 224.0 | 390.2 | 556.4 | 767.0 | 888.9 | 1,055.1 |
IRR (Post-Tax) | 11.3% | 33.4% | 50.2% | 65.2% | 82.5% | 91.9% | 104.2% | ||
NPV @ 5% (Post-Tax) US$M | -274.9 | -117.3 | 25.8 | 149.3 | 268.3 | 387.4 | 538.1 | 625.4 | 744.4 |
INITIAL CAPITAL EXPENDITURES (US$ MILLIONS)
Initial capital expenditures are estimated at US$89,997,000 million as detailed below:
OPERATING COSTS
The mine operating costs were calculated to average $3.49 per tonne mined as summarized below.
Mine Operating Cost Center | Unit Cost (US$/t mined) |
Owner Mining Personnel | $0.11 |
Owner Supplies & Misc. | 0.03 |
Contractor Mining | 3.35 |
Total Cost (Rounded) | $3.49 |
The life-of-mine operating costs were calculated to average US$20.44/tonne resource processed as summarized below.
Operating Cost | Cost per Tonne of Crushed Material Processed (US$/t) |
Mining | $10.60 |
Processing | $8.79 |
G&A | $1.05 |
Total Site Operating Cost | $20.44 |
MINERAL RESOURCES
An updated Mineral Resource Estimate prepared by DRW Geological Consultants Ltd., with an effective date of August 8, 2025, was used in the PEA. Details of the Mineral Resource Estimate can be found in the Report to be filed on SEDAR+ within 45 days of this release.
Category | Cut-off (g/t Au) | Grade (Au, g/t) | Tonnes | Gold Oz | Strip Ratio |
Inferred | 0.20 | 0.58 | 36,733,000 | 688,000 | 2.36 |
- The Mineral Resource Estimate has been constrained to a preliminary optimized pit shell, using the following parameters: SG = 2.57 gm/cc based on testwork, mining costs = $3.00/tonne, mining recovery = 98%, mining dilution = 2%, process cost = $5.00 per tonne, G&A = $1.05 per tonne, gold price = $2,500 per troy ounce, throughput at 10,000 tpd., discount rate = 5%. A cost of $0.03 was added per bench to the mining cost below the existing level surface.
- A top cut of 32 gpt gold is applied to all zones except Zone 6 which has a top cut of 50 gpt gold.
- Mineral Resources have been calculated using the Inverse Distance Squared method.
- Mineral Resources constrained to optimized pit shells are not Mineral Reserves and do not have demonstrated economic viability.
- Conforms to NI 43-101, Companion Policy 43-101CP, and the CIM Definition Standards for Mineral Resources and Mineral Reserves. Inferred Resources have been estimated from geological evidence and limited sampling and must be treated with a lower level of confidence than Measured and Indicated Resources.
- All numbers are rounded. Overall numbers may not be exact due to rounding.
- There are no known legal, political, environmental, or other risks that could materially affect the potential development of the mineral resources.
MINE PLAN
The mine plan is conceived as a conventional open pit tuck and shovel/loader operation. There are two independent pits which are developed with five-phase or pushback designs. Pit shells were designed using 6.0-meter benches with a catch bench installed every 18 meters. A bench face angle of 66° was used, resulting in an inner-ramp angle of 45° when catch benches were included. An 88% overall gold recovery has been used in this study, which was based on bottle roll and column leach test results. Base case haulage ramps are 26 meters wide and have a design gradient of 10%. Processing rates are based on a daily crushing rate of approximately 10,000 tonnes per day utilizing two stage crushing
The mine and crushing will be operated by contractors with oversight by GMV mine management. The mine plan produces a nominal tonnage to the crushing and heap leach of 3,500 Ktonnes per year (10,000 tpd) from a total material movement of 93.8 Ktonnes for the life of mine (26,106 tpd LOM average).
The PEA is preliminary in nature; it includes inferred Mineral Resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as Mineral Reserves, and there is no certainty that the PEA will be realized. There is no Mineral Reserve at the Mexican Hat Project at this time. Mineral resources that are not mineral reserves do not have demonstrated economic viability. Over the course of the mine life, 38.6 Mtonnes of Mineralized Resource is planned for processing out of a total material movement of 117.8 Mtonnes.
INFRASTRUCTURE & PROCESS PLANT
The Mexican Hat Project is located in the southeastern part of the State of Arizona, approximately 72 miles east-southeast of Tucson, and can be accessed from the Old Ghost Town Road., a gravel road extending south of the Town of Pearce or north from Gleeson Road.
Groundwater will be used as the source of water for mining operations. No permitting restrictions or quantity issues are anticipated.
A 69 kV powerline to site will be supplied by Sulphur Springs Valley Electric Cooperative from their power plant located 30 km north of the project site.
The crushing plant will be operated by a contractor to produce a crushed product for heap leaching with a 25 mm top size. Pregnant solution from the heap leach will be processed in a conventional adsorption desorption recovery (ADR) plant. The process plant will produce doré gold bars.
TECHNICAL REPORT AND QUALIFIED PERSONS
The Report entitled Updated Preliminary Economic Assessment, Mexican Hat Project", with an effective date of August 8, 2025 and which was prepared by the following Qualified Persons (as defined under NI 43-101), all of whom are independent of the Company, will be filed by the Company within 45 days of this release on www.sedarplus.com:
- Mr. Brian Olson, Q.P., Samuel Engineering, Inc. (Metallurgical Test Work and Recovery, Process Plant and Process Operating Costs)
- Mr. Steven Pozder, P.E., Samuel Engineering, Inc. (Project Economics and Infrastructure)
- Dr. Dave Webb, Ph.D., P.Eng., P.Geo., DRW Geological Consultants Ltd. (Mineral Resource Estimate, Property Description and Location, Accessibility, Climate, Local Resource, Infrastructure and Physiography, History, Geological Setting and Mineralization, Deposit Types, Exploration, Drilling, Sample Preparation, Analysis and Security, Data Verification).
- Mr. Thomas L. Dyer, P.E., RESPEC LLC. (Mine Design, Production Schedule, Capital and Operating Costs)
- Mr. Francisco J. Barrios, P.E., BBA Consultants International LP (Pad Design and Loading)
- Ms. Dawn Garcia, CPG, PG, Stantec Consulting Services Inc. (Environmental)
All Qualified Persons have contributed to their corresponding sections in Interpretation, and Recommendations. The Qualified Persons have reviewed and approved the scientific, technical, and economic information obtained in this news release.
For a description of the data verification process and limitations, underlying assumptions and the results of surveys and quality assurance program regarding exploration information, please refer to the Company's existing NI 43-101 Technical Report filed on SEDAR+ entitled "Preliminary Economic Assessment, Mexican Hat Project" with an effective date of October 20, 2020.
Ian Klassen, President & CEO remarked that "The robust PEA confirms our contention that the project's strong economic potential de-risks the development pathway, providing a solid foundation for advancement. The results validate the open-pit, heap-leach concept, demonstrate excellent metallurgy and recoveries, and outline a simple mining and processing strategy. With high margins, rapid payback, and straightforward engineering, the PEA positions the project well for the future, where detailed design, capital optimization, and permitting can advance with confidence."
2025-2026 Forward Looking Plan
The Mexican Hat Project PEA economics justify continued investment in project development. The forward-looking plan for Mexican Hat includes work required to advance the project through Feasibility Study and into the permitting process.
These tasks include:
- Approx. 7000 meters of in-fill drilling to increase confidence in the current geological understanding and mineral resource estimation to sufficient level to support mineral reserve development
- Metallurgical column, hardness, and grinding tests to further optimize and improve heap leach gold recovery, and to provide information for feasibility design work
- Performing a trade-off study for self-mining and crushing versus contract mining and crushing
- Geotechnical drilling and analysis to optimize pit slope design parameters
- Conduct base-line water sampling, and update of hydrologic, cultural, and environmental studies for permitting
About GMV Minerals Inc.
GMV Minerals Inc. is a publicly traded exploration company focused on developing precious metal assets in Arizona. GMV, through its 100% owned subsidiary, has a 100% interest in a Mining Property Lease commonly referred to as the Mexican Hat Project, located in Cochise County, Arizona, USA. The project was initially explored by Placer Dome (USA) in the late 1980's to early 1990's. GMV is focused on developing the asset and realizing the full mineral potential of the property through near term gold production.
PEA Information and Cautionary Note Regarding Inferred Mineral Resources
The mine plan evaluated in the PEA is preliminary in nature and includes Inferred Mineral Resources, as defined by NI 43-101 that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be converted to Mineral Reserves. Additional drilling and technical studies will need to be completed in order to fully assess its viability. There is no certainty that a production decision will be made to develop the Mexican Hat Project or that the economic results described in the PEA will be realized. Mine design and mining schedules, metallurgical flow sheets and process plant designs will require additional detailed work and economic analysis and internal studies to ensure satisfactory operational conditions and decisions regarding future targeted production.
Cautionary Note to U.S. Investors
The United States Securities and Exchange Commission permits U.S. mining companies, in their filings with the SEC, to disclose only those mineral deposits that a company can economically and legally extract or produce. We use certain terms in this report, such as "measured," "indicated," "inferred," and "resources," that the SEC guidelines strictly prohibit U.S. registered companies from including in their filings with the SEC.
Cautionary Statement Regarding Forward-Looking Information
This news release includes certain "forward-looking information" under applicable Canadian securities legislation. Forward-looking information include estimates and statements that describe the Company's future plans, objectives or goals, including words to the effect that the Company or management expects a stated condition or result to occur. Forward-looking information may be identified by such terms as "believes", "anticipates", "expects", "estimates", "may", "could", "would", "will", or "plan". Forward-looking information contained in this news release include, but are not limited to, statements or information with respect to: the results of the PEA, including the IRR and NPV, life of mine and production, capital and operating expenditures, cost estimates; permitting restrictions, and the mine plan, including infrastructure requirements and future plans; the filing of the PEA, including timing thereof, mineral resources; and future gold prices. Since forward-looking information are based on assumptions and address future events and conditions, by their very nature they involve inherent risks and uncertainties as described in the Company's filings with Canadian securities regulators. Assumptions upon which forward-looking information contained in this news release is based, without limitation, include: results of future exploration; gold prices; accuracy of the results of the PEA, including key assumptions and methods used to determine mineral resources and the results of the PEA; the ability to obtain required permits and approvals; the ability to execute future plans; exchange rates; ability to obtain funding; and changes in regulatory or community environment; Risks, and uncertainties include: results of further exploration; risks related to mineral tenure, permits and approvals; risks related to the execution of future plans; changes in gold price and exchange rates; risks related to obtaining financing; foreign country risks; regulatory risks and liabilities; and those risks and uncertainties as further described in the Company's filings with Canadian securities regulators which can be found on SEDAR+ at www.sedarplus.ca under the Company's profile. There can be no assurance that such information will prove to be accurate, as actual results and future events could differ materially from those anticipated in such information. Accordingly, readers should not place undue reliance on forward-looking information. The Company disclaims any intention or obligation to update or revise any forward-looking information, whether as a result of new information, future events or otherwise, other than as required by law.
Dr. D.R. Webb, Ph.D., P.Geo., P.Eng. is the Q.P. responsible for this release within the meaning of NI 43-101 and has reviewed the technical content of this release and has approved its content.
ON BEHALF OF THE BOARD OF DIRECTORS
Ian Klassen, President
For further information please contact:
GMV Minerals Inc.
Ian Klassen
Tel: (604) 899-0106
Email: info@gmvminerals.com
Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.
Keep reading...Show less
Latest News
Latest Press Releases
Related News
TOP STOCKS
American Battery4.030.24
Aion Therapeutic0.10-0.01
Cybin Corp2.140.00