South Star Battery Metals Announces Construction and Development Update for the Santa Cruz Graphite Mine in Bahia, Brazil

South Star Battery Metals Announces Construction and Development Update for the Santa Cruz Graphite Mine in Bahia, Brazil

Highlights:

  • Civil and earthworks contractors mobilized, and Santa Cruz is on schedule to complete construction and commissioning by December 2023 .
  • Majority of major equipment contracts signed and down payments completed to lock in equipment CAPEX. All major equipment contracts scheduled to be finalized in January 2023 .
  • Owners team mobilized and preparing for 12-month construction and commissioning.
  • Field work for Phases 2 & 3 environmental permitting completed. On schedule to submit documentation in early Q1 2023.
  • Request for definitive mining concession and the Planned Economic Analysis   reports ("PAE") doubling production to 50,000 tonne per year ("tpy") of graphite concentrates for 11 of the 13 mining claims submitted to ANM for review and comment. All PAEs on schedule for submittal by January 2023 .
  • Initial field work for 3 lines of geophysics completed and in interpretation. Remaining field work expected to be completed in January 2023 and final report issued in February 2023 .

 South Star Battery Metals Corp. ("South Star" or the "Company") (TSXV: STS) (OTCQB: STSBD), is pleased to announce a construction and project development for the Santa Cruz Graphite Mine in Bahia, Brazil .

PHASE 1 CONSTRUCTION UPDATE
  • The majority of the major equipment has been contracted and down payments made to lock in largest portion of Phase 1 capital expenditures ("CAPEX"). All major equipment contracts are on schedule to be signed by January 2023 . Shop drawings are being finalized by equipment manufacturers, and final engineering documentation for construction is on schedule to be completed by February 10 th , 2023.
  • Civil and earthworks contractors are under contract and mobilized. Civil infrastructure including initial offices, showers, bathrooms and other infrastructure is 50% completed and on schedule to be completed by January 6 th 2023. The earthworks contractor is mobilized, and clearing and topsoil stockpiling operations of the plant site are underway.

Figure 1: Clearing and Topsoil Removal of Phase 1 Plant Location (CNW Group/South Star Battery Metals Corp.)

  • The owners team is complete and mobilized to oversee the 12-month construction and commissioning schedule.
PHASES 2 & 3 PERMITTING AND LICENSING UPDATE
  • The field work for the environmental permitting of Phases 2 & 3 has been completed, and the Company is on schedule to submit the permitting documentation/studies to the Municipality of Itabela, Bahia by the end of January 2023 . The terms of reference and requested studies for Phases 2 & 3 are similar in process and substance to the Phase 1 environmental permitting process.
  • Requests for definitive mining concession and the Planned Economic Analysis reports (PAE) doubling production to 50,000 tpy of graphite concentrates for 11 of the 13 mining claims have been submitted to Brazilian Mining Agency ("ANM") for review and comment. All 13 PAEs are planned to be submitted by January 2023 .
  • Permitting and licensing for Phases 2 & 3 are planned to be approved around the time the Phase 1 operations are in commissioning in Q4 of 2023.
EXPLORATION UPDATE
  • The geophysics team has completed the field work for the first three lines of electrical resistivity ("ER") with 10m electrode spacing with an estimated penetration of 80-90 meters. The lines were completed on sections with known geology and graphite grades based on recent drilling program. The results are being interpreted and then will be compared to the known geologic sections and graphitic carbon ("Cg") grade. If the ER proves effective in identifying potential targets and mineralized zones/limits, then additional 3-4 kms of ER will be completed in January 2023 . The results will be used to plan and prioritize the 2023 drilling program.

Richard Pearce , CEO of South Star, said, "We are closing out 2022 having reached another important milestone, and Phase 1 commercial production is planned for December 2023 . It is great to be fully funded for Phase 1, as well as getting equipment purchased and contractors mobilized. Civil support infrastructure construction is about 50% complete, and clearing and stripping operations of the plant site are underway. We will be working through the end of the year and look forward to hitting the ground running so that 2023 will be a watershed moment for South Star, as we transition from a development project to an operating mine. We are confident in delivering on our promise to be the first new graphite production in the Americas since 1996. We will be posting regular updates, videos and photos on our social media and website, so that shareholders, stakeholders and potential clients have a clear vision of our path to production."

South Star Battery Metals Corp. is a Canadian battery metals project developer focused on the selective acquisition and development of near-term production projects in the Americas. South Star's Santa Cruz Graphite Project, located in Southern Bahia, Brazil is the first of a series of industrial and battery metals projects that will be put into production. Brazil is the second-largest graphite-producing region in the world with more than 80 years of continuous mining. Santa Cruz has at-surface mineralization in friable materials, and successful large-scale pilot-plant testing (>30t) has been completed. The results of the testing show that approximately 65% of Cg concentrate is +80 mesh with good recoveries and 95%-99% Cg. With excellent infrastructure and logistics, South Star is fully funded for Phase 1, and the 12-month construction and commissioning are underway. Santa Cruz will be the first new graphite production in the Americas since 1996 with Phase 1 commercial production projected in Q4 2023.

South Star's next project in the development pipeline is a project in Alabama located in the middle of a developing electric vehicle, aerospace and defense hub in the southeastern United States.  The Project is a historic mine active during World Wars I & II.  Trenching, phase 1 drilling, sampling, analysis and preliminary metallurgic testing has been completed.  The testing indicated a traditional crush/grind/flotation concentration circuit achieved grades of approximately 94-97% with approximately 86% recoveries. South Star is executing on its plan to create a multi-asset, diversified battery metals company with near-term operations in strategic jurisdictions.  South Star trades on the TSX Venture Exchange under the symbol STS, and on the OTCQB under the symbol STSBF.

South Star is committed to a corporate culture, project execution plan and safe operations that embrace the highest standards of ESG principles based on transparency, stakeholder engagement, ongoing education and stewardship. To learn more, please visit the Company website at https://www.southstarbatterymetals.com .

This news release has been reviewed and approved by Richard Pearce, P.E., a "Qualified Person" under National Instrument 43-101 and President and CEO of South Star Battery Metals Corp.

On behalf of the Board,

Mr. Richard Pearce
Chief Executive Officer

Twitter: https://twitter.com/southstarbm
Facebook: https://www.facebook.com/southstarbatterymetals
LinkedIn: https://www.linkedin.com/company/southstarbatterymetals/
YouTube: South Star Battery Metals - YouTube

CAUTIONARY STATEMENT

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this press release.

Forward-Looking Information

This press release contains "forward-looking statements" within the meaning of applicable securities legislation. Forward-looking statements relate to information that is based on assumptions of management, forecasts of future results, and estimates of amounts not yet determinable. Any statements that express predictions, expectations, beliefs, plans, projections, objectives, assumptions or future events or performance are not statements of historical fact and may be "forward-looking statements". Forward-looking statements in this press release include, but are not limited to, statements regarding: moving Santa Cruz into production and scaling operations as well as advancing the Alabama project;   and   the Company's plans and expectations.

Forward-looking statements are subject to a variety of risks and uncertainties which could cause actual events or results to differ from those reflected in the forward-looking statements, including, without limitation: risks related to failure to obtain adequate financing on a timely basis and on acceptable terms; risks related to the outcome of legal proceedings; political and regulatory risks associated with mining and exploration; risks related to the maintenance of stock exchange listings; risks related to environmental regulation and liability; the potential for delays in exploration or development activities or the completion of feasibility studies; the uncertainty of profitability; risks and uncertainties relating to the interpretation of drill results, the geology, grade and continuity of mineral deposits; risks related to the inherent uncertainty of production and cost estimates and the potential for unexpected costs and expenses; results of prefeasibility and feasibility studies, and the possibility that future exploration, development or mining results will not be consistent with the Company's expectations; risks related to commodity price fluctuations; and other risks and uncertainties related to the Company's prospects, properties and business detailed elsewhere in the Company's disclosure record. Should one or more of these risks and uncertainties materialize, or should underlying assumptions prove incorrect, actual results may vary materially from those described in forward-looking statements. Investors are cautioned against attributing undue certainty to forward-looking statements. These forward-looking statements are made as of the date hereof and the Company does not assume any obligation to update or revise them to reflect new events or circumstances. Actual events or results could differ materially from the Company's expectations or projections.

South Star Battery Metals Corp. Logo (CNW Group/South Star Battery Metals Corp.)

Cision View original content to download multimedia: https://www.prnewswire.com/news-releases/south-star-battery-metals-announces-construction-and-development-update-for-the-santa-cruz-graphite-mine-in-bahia-brazil-301710491.html

SOURCE South Star Battery Metals Corp.

Cision View original content to download multimedia: https://www.newswire.ca/en/releases/archive/December2022/28/c6279.html

News Provided by Canada Newswire via QuoteMedia

STS:CA
The Conversation (0)
South Star Announces Additional Sales of Natural Flake Graphite Concentrate to U.S. Customer

South Star Announces Additional Sales of Natural Flake Graphite Concentrate to U.S. Customer

Advancing the First New Natural-Flake Graphite Mine in the Americas this Century

South Star Battery Metals CORP. ("South Star" or the "Company") (TSXV:STS)(OTCQB:STSBF) is pleased to announce that, further to the Company's May 6, 2024 announcement ("South Star Battery Metals Announces the First Sale of Natural Flake Graphite Concentrate from its Santa Cruz Graphite Mine in Brazil") and its August 1, 2024 announcement ("South Star Announces Successful Product Qualification and 100-Tonne Sale of Natural Flake Graphite Concentrate to U.S. Customer"), South Star has executed another binding commercial sales agreement (the "Agreement") for an initial 40 tonnes (more than 88,000 pounds) of natural-flake graphite concentrate from the Company's flagship Santa Cruz Graphite Mine("Santa Cruz"), located in northeastern Brazil's Bahia state. This most recent sales Agreement was formally executed with a prominent American industrial graphite customer (the "U.S. Client

News Provided by ACCESSWIRE via QuoteMedia

Keep reading...Show less
South Star Announces Successful Product Qualification and 100-Tonne Sale of Natural Flake Graphite Concentrate to U.S. Customer

South Star Announces Successful Product Qualification and 100-Tonne Sale of Natural Flake Graphite Concentrate to U.S. Customer

South Star advancing the first new natural-flake graphite mine in the Americas this century.

South Star Battery Metals CORP. ("South Star" or the "Company") (TSXV:STS)(OTCQB:STSBF) is pleased to announce that further to the Company's May 6, 2024 announcement ("South Star Battery Metals Announces the First Sale of Natural Flake Graphite Concentrate from its Santa Cruz Graphite Mine in Brazil"), South Star has executed another binding commercial sales agreement (the "Agreement") for the initial purchase of 100 tonnes (more than 220,000 pounds) of graphite concentrate from the Company's flagship Santa Cruz Graphite Mine ("Santa Cruz"), located in northeastern Brazil's Bahia state

News Provided by ACCESSWIRE via QuoteMedia

Keep reading...Show less
South Star Announces Substantial Completion and Commissioning of the Santa Cruz Phase 1 Graphite Mine in Brazil

South Star Announces Substantial Completion and Commissioning of the Santa Cruz Phase 1 Graphite Mine in Brazil

Highlights

  • Mine prestrip, preliminary dump foundations and ramps are complete, and approximately 50,000 tonnes of ore is being placed on the ore pad by end of August for commissioning and initial operations.

News Provided by ACCESSWIRE via QuoteMedia

Keep reading...Show less
South Star Battery Metals Announces Successful Metallurgical Results for its BamaStar Graphite Project in Alabama, USA

South Star Battery Metals Announces Successful Metallurgical Results for its BamaStar Graphite Project in Alabama, USA

Highlights:

  • Metallurgical work completed on representative oxide, transition and fresh rock composite samples ranging in grade from 2.36% Cg for fresh rock to 3.04% Cg for oxide samples.
  • Bond abrasion and work index testing show low to medium abrasion and low energy requirements.
  • Open circuit flotation tests resulted in excellent concentrates grade ranging from 94.4% Cg for fresh rock materials to 99.5% Cg for oxide samples with a simple flowsheet that maximizes graphite recovery and minimizes flake degradation.
  • The open circuit graphite recoveries were high, ranging between 87.5% and 91.5%.
  • Given the superior response of the oxide and transitional material, the next phase of work will investigate mining pit design to maximize processing of oxide and transitional material early in the project life and postpone mining of the fresh ore in order to decrease initial CAPEX, lower OPEX and target improved project economics.
  • The NI43-101 Preliminary Economic Assessment results for BamaStar are scheduled for release in August 2024.

South Star Battery Metals Corp. ("South Star" or the "Company") (TSXV:STS)(OTCQB:STSBF) is pleased to announce successful results from the ongoing metallurgical process development program for the Bama Star graphite project in Alabama, USA

News Provided by ACCESSWIRE via QuoteMedia

Keep reading...Show less
South Star Battery Metals Announces Land Purchase, Construction Update, and the Approval of the Definitive Mining Licenses For Phases 1, 2 & 3 for its Santa Cruz Graphite Mine in Brazil

South Star Battery Metals Announces Land Purchase, Construction Update, and the Approval of the Definitive Mining Licenses For Phases 1, 2 & 3 for its Santa Cruz Graphite Mine in Brazil

Santa Cruz Graphite Mine Highlights:

  • Final payment of land purchase for Phase 1 Plant and Operations.
  • Approval of the Definitive Mining Licenses For Phases 1, 2 & 3. All mining and environmental licenses/permits are approved and in-hand for the future phased, modular expansion of Santa Cruz graphite production up to 50,000 tonnes/year.
  • Phase 1 construction is on schedule for substantial completion by the end of June 2024 followed by a 6-week plant commissioning and ramp-up period. Commercial sales are planned to start in September 2024. Name plate production capacity is expected to be reached in Q4 2024.

South Star Battery Metals Corp. ("South Star" or the "Company") (TSXV:STS)(OTCQB:STSBF) is pleased to announce the final payment of the previously announced (Aug. 02, 2022) land purchase required for construction of the Phase 1 mine and plant facilities. The farm totals approximately 325 hectares and is where all the plant facilities, mine and infrastructure installations are required for the first three years of operations at its Santa Cruz Graphite Project in Bahia, Brazil

News Provided by ACCESSWIRE via QuoteMedia

Keep reading...Show less
Battery storage power station accompanied by solar and wind turbine power plants.

Next-gen Battery Technologies for Grid Storage Ripe for Investment

As the world transitions to renewable energy sources, traditional power grids, designed for consistent fossil fuel-based generation, are ill-equipped to handle the intermittent nature of renewable energy sources like wind and solar.

This mismatch has created a pressing demand for efficient, large-scale energy storage systems, paving the way for the development of new battery technologies that can handle and ensure a stable and reliable power supply.

From investors and businesses, these new battery technologies offer a compelling opportunity to be part of the burgeoning, next-generation grid energy storage market that’s projected to grow at a CAGR of 28 percent over the next 10 years.

Keep reading...Show less
International Graphite

International Graphite


Keep reading...Show less
Businessmen signing agreement.

NOVONIX Signs Synthetic Graphite Offtake Deal with Volkswagen's PowerCo

Battery materials and technology company NOVONIX (ASX:NVX,NASDAQ:NVX) has signed a binding offtake agreement for synthetic graphite material, the company said in a Monday (November 25) press release.

The agreement is with PowerCo, a battery company set up by Volkswagen (OTC Pink:VLKAF,FWB:VOW). The company is looking to boost its battery cell output, and has identified three gigafactory locations.

The first is in Salzgitter, Germany, the second is Valencia, Spain, and the third is in St. Thomas, Canada.

Keep reading...Show less
Altech Batteries

Altech – Cerenergy® Battery Project Funding Update

Altech Batteries Limited (Altech/Company) (ASX: ATC) (FRA: A3Y) is pleased to announce an update on funding of the CERENERGY® sodium-chloride solid-state battery project in Saxony, Germany.

Keep reading...Show less
Evolution Energy Minerals Limited

Appointment of Chief Executive Officer

Evolution Energy Minerals Limited (Evolution or the Company) (ASX: EV1, FSE: P77) is pleased to announce the appointment of George Donne as Chief Executive Officer, effective immediately. Mr. Donne brings over 20 years of expertise in the mining sector, with a distinguished career spanning corporate finance advisory, private equity and executive roles in both public and private mining companies. His background includes extensive work in developing markets across multiple commodities, particularly base metals and lithium-ion battery raw materials. With hands-on experience in mergers and acquisitions, corporate financing, investor relations and governance, Mr. Donne is well-positioned to lead Evolution’s strategic growth.