NextSource Materials Provides Progress Update on Molo Graphite Mine in Madagascar

NextSource Materials Provides Progress Update on Molo Graphite Mine in Madagascar

NextSource Materials Inc. (TSX:NEXT)(OTCQB:NSRCF) ("NextSource" or the "Company") is pleased to provide a progress update for Phase 1 of the Molo Graphite Mine in Madagascar

The Processing Plant has arrived and been unloaded at the local port of Fort Dauphin in Madagascar and has cleared customs. Company-appointed logistics specialists have now commenced transporting all modules of the Processing Plant, including two mobile cranes, to the mine site. Earthworks at the mine site are complete and civil works are on schedule to be completed by the time the Processing Plant arrives.

It is expected to take approximately 45 days to re-assemble the Processing Plant, which was previously erected and underwent Factory Acceptance Testing prior to shipment. Once re-assembled, the Processing Plant will undergo Site Acceptance Testing, which is the final step before mine commissioning.

The pre-fabricated units for the camp accommodations and auxiliary buildings have also arrived at site and assembly of these support structures will commence shortly.

https://storage.googleapis.com/accesswire/media/711353/PHOTO-2022-08-08-11-34-57.jpg

President and CEO, Craig Scherba commented,

"Now that the processing plant has arrived in-country, on-site activity will ramp up significantly over the next several weeks as we begin re-assembly of the processing plant and the auxiliary buildings".

https://storage.googleapis.com/accesswire/media/711353/PHOTO-2022-08-08-11-57-50.jpg

Construction Update of Solar and Battery Hybrid Power Plant

As announced on May 24, 2022, CrossBoundary Energy's Madagascar subsidiary commenced construction of a solar thermal hybrid energy power plant ("Hybrid Plant") that will power Phase 1 of the Molo mine. Construction of the Hybrid Plant is on schedule with the thermal portion of the hybrid solution expected to be installed and operational at the time of commissioning of the Processing Plant, with the renewable energy portion following thereafter.

The Hybrid Plant will be located adjacent to the Molo mine site and when fully operational, will provide up to 33% of the mine's total Phase 1 electricity needs from renewable solar energy, with the remainder coming from thermal generators.

About NextSource Materials Inc.

NextSource Materials Inc. is a strategic materials development company based in Toronto, Canada that is intent on becoming a fully integrated, global supplier of critical battery and technology materials needed to power the sustainable energy revolution.

The Company's Molo graphite project in Madagascar is one of the largest known and highest-quality graphite deposits globally, and the only one with SuperFlake® graphite. Construction of Phase 1 of the Molo Project is underway, with commissioning expected in the autumn of 2022.

NextSource Materials is listed on the Toronto Stock Exchange (TSX) under the symbol "NEXT" and on the OTCQB under the symbol "NSRCF".

Safe Harbour: This press release contains statements that may constitute "forward-looking information" or "forward-looking statements" within the meaning of applicable Canadian and United States securities legislation. Readers are cautioned not to place undue reliance on forward-looking information or statements. Forward looking statements and information are frequently characterized by words such as "plan", "expect", "project", "intend", "believe", "anticipate", "estimate", "potential", "possible" and other similar words, or statements that certain events or conditions "may", "will", "could", or "should" occur. Forward-looking statements include any statements regarding, among others, timing of on-site construction including completion of the civil and earthworks, timing of the on-site arrival of the processing plant and installation thereof, delivery and installation of the auxiliary buildings and structures, delivery and construction of the Solar Hybrid Battery System, shipping of all plant infrastructure to site, all re-assembly and commissioning of the Molo Project, initiation of a Feasibility Study and timing of its completion, production capacity, NPV, IRR and life of mine of the Molo mine, timing of the FEED Study and Feasibility Study, as well as the Company's intent on becoming a fully integrated global supplier of critical battery and technology materials. These statements are based on current expectations, estimates and assumptions that involve a number of risks, which could cause actual results to vary and, in some instances, to differ materially from those anticipated by the Company and described in the forward-looking statements contained in this press release. No assurance can be given that any of the events anticipated by the forward-looking statements will transpire or occur or, if any of them do so, what benefits the Company will derive there from. The forward-looking statements contained in this news release are made as at the date of this news release and the Company does not undertake any obligation to update publicly or to revise any of the forward-looking statements, whether because of new information, future events or otherwise, except as may be required by applicable securities laws. Although the forward-looking statements contained in this news release are based on what management believes are reasonable assumptions, the Company cannot assure investors that actual results will be consistent with them. These forward-looking statements are made as of the date of this news release and are expressly qualified in their entirety by this cautionary statement. Subject to applicable securities laws, the Company does not assume any obligation to update or revise the forward-looking statements contained herein to reflect events or circumstances occurring after the date of this news release.

SOURCE: NextSource Materials Inc.



View source version on accesswire.com:
https://www.accesswire.com/711353/NextSource-Materials-Provides-Progress-Update-on-Molo-Graphite-Mine-in-Madagascar

News Provided by ACCESSWIRE via QuoteMedia

NEXT:CA
NextSource Materials

NextSource Materials Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

The Conversation (0)
NextSource Materials

NextSource Materials

NextSource Materials

NextSource Materials Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

Graphite production at Molo mine with planned near-term downstream battery anode facility

NextSource Materials Announces Results of 2024 Annual Meeting of Shareholders

NextSource Materials Announces Results of 2024 Annual Meeting of Shareholders

NextSource Materials Inc. (TSX:NEXT)(OTCQB:NSRCF) ("NextSource" or the "Company") is pleased to announce the results of the Annual Meeting of Shareholders of the Company (the "Meeting") held virtually at 9:00 AM (Toronto time) on December 5, 2024 AGM ResultsThe final voting results of the... Keep Reading...
NextSource Materials Closes Final Tranche of Private Placement for Additional Gross Proceeds of CAD$720,800

NextSource Materials Closes Final Tranche of Private Placement for Additional Gross Proceeds of CAD$720,800

Not for distribution to U.S. news wire services or for dissemination in the United States or to a U.S. Person. NextSource Materials Inc. (TSX:NEXT)(OTCQB:NSRCF) ("NextSource" or the "Company") announces it has closed a second and final tranche of its previously announced non-brokered private... Keep Reading...
NextSource Materials Welcomes New President and CEO Hanré Rossouw to Deliver Next Phase of Growth

NextSource Materials Welcomes New President and CEO Hanré Rossouw to Deliver Next Phase of Growth

NextSource Materials Inc. (TSX:NEXT)(OTCQB:NSRCF) ("NextSource" or the "Company") confirms, further to the announcement on 28th May 2024, Hanré Rossouw has officially begun his role as President and CEO. His tenure begins in Madagascar, where he will visit the Molo graphite mine operations as... Keep Reading...
NextSource Materials Completes First Commercial Shipments of Graphite Concentrate to Germany and USA

NextSource Materials Completes First Commercial Shipments of Graphite Concentrate to Germany and USA

NextSource Materials Inc. (TSX:NEXT)(OTCQB:NSRCF) ("NextSource" or "the Company") is pleased to announce it has completed its first commercial shipments of SuperFlake® graphite concentrate from its Molo Graphite Mine (the "Molo mine") in southern MadagascarFull container loads of high-quality,... Keep Reading...
NextSource Materials Closes Private Placement for Gross Proceeds of CAD$14.7 Million

NextSource Materials Closes Private Placement for Gross Proceeds of CAD$14.7 Million

Not for distribution to U.S. news wire services or for dissemination in the United States or to a U.S. Person.NextSource Materials Inc. (TSX:NEXT)(OTCQB:NSRCF) ("NextSource" or the "Company") announces it has closed a non-brokered private placement offering of 27,728,100 common shares of the... Keep Reading...
Waving American flag with stars and stripes.

Titan on Track for New York Graphite Production as US Pushes for Domestic Supply Chain

Titan Mining (TSX:TI,OTCQB:TIMCF) is on track to start producing natural graphite concentrate at its Empire State operation in Gouverneur, New York, positioning itself as the first near-term US supplier.“China’s decision to tighten graphite exports underscores the importance of having a secure... Keep Reading...
NextSource Materials

NextSource Materials Announces Positive Results of Technical & Economic Study for Proposed Battery Anode Facility in the UAE and Secures Industrial Site with Building in Abu Dhabi

NextSource Materials Inc. (TSX:NEXT)(OTCQB:NSRCF) ("NextSource" or the "Company") is pleased to announce positive results of a technical and economic study (the "Study") on the construction of a proposed 30,000 tpa capacity battery anode facility ("BAF") located in the United Arab Emirates... Keep Reading...
Initial Drill Results at Orom-Cross Highlight High Grade Shallow Zones

Initial Drill Results at Orom-Cross Highlight High Grade Shallow Zones

First assay results from latest 7,750m programme confirm extensions to orebody and further high-grade zones

Blencowe Resources Plc (LSE: BRES) is pleased to announce the first batch of assay results from its Stage 7 drilling programme at its Orom-Cross graphite project in Northern Uganda. This campaign, the largest in the Company's history, included geotechnical holes, infill drilling and exploration... Keep Reading...
GreenRoc Strategic Materials

EU Commissioner Dan Jørgensen to visit Amitsoq

GreenRoc Strategic Materials Plc (AIM: GROC), a company focused on the development of critical mineral projects in Greenland, is pleased to announce that the European Union ("EU") Commissioner for Energy, Dan Jørgensen, will be visiting GreenRoc's Amitsoq graphite deposit and planned mine site... Keep Reading...
Metals Australia (ASX:MLS)

Arrowhead Sees Significant Upside in Metals Australia’s Graphite Project

Description:Market research firm Arrowhead believes Metals Australia (ASX:MLS) is positioned to benefit from surging demand for critical minerals tied to the global energy transition. In a September 2025 Due Diligence and Valuation Report, analysts Karan Mehta and Sahil Rustagi suggested a fair... Keep Reading...
NextSource Materials

NextSource Materials Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

Latest Press Releases

Related News