Horizonte Minerals PLC Announces Araguaia Nickel Project Operational Update

 

Horizonte Minerals Plc, (AIM:HZM)(TSX:HZM) ('Horizonte' or 'the Company') the nickel company focused on Brazil, is pleased to provide an operational update for the Araguaia Nickel Project ('Araguaia' or 'the Project

 

Highlights:

 
  • Significant progress on key project execution preparation activities, including competitive tendering for supply of key processing equipment, electric furnace and project management (EPCM) services
  •  
  • Operational Readiness Plan well advanced with all key permits in place for commencement of construction
  •  
  • Financing discussions remain on track. Credit committee approval for the senior debt facility expected in Q3 2021 as previously announced
  •  
  • Key environmental and social programmes continuing in preparation for construction phase
  •  
  • Mobilisation of Head of Projects to Brazil and appointment of Engineering, Community, Health and Safety Managers continues the build out of the project execution team
  •  

Horizonte's CEO, Jeremy Martin, commented: 'In the six months since the completion of the value engineering work, significant progress has been made on plans to implement the project. Tenders have been completed for approximately US$230M of key equipment and services to be supplied under contract with industry-leading vendors. This progress has enabled the project execution plan to be further advanced and to better reflect the current context in Brazil, allowing us to successfully deliver a tier-one nickel project. We have made progress with the senior debt facility following completion of due diligence by the lending syndicate, with credit committee approval on track for Q3 2021.

 

Mike Drake, our newly appointed Head of Projects has arrived in Brazil safely, successfully reopened the office in Belo Horizonte and is rapidly building out our project execution team.Together with the excellent progress being made on our financing initiatives and the recent strength in the nickel price, it is exciting to see an increase of activity on the ground in Brazil as our preparation to start construction in the coming months intensifies.'

 

Project Execution Readiness

 

Based on the optimised scope and execution plan that was generated by the Value Engineering work (see announcement 4 December 2020), the past six months have focused on final preparations for project execution.

 

The objectives of this project readiness process has been to:

 
  • Define the final process equipment specification and suppliers that will be used by the Project, particularly the electric furnace and rotary kiln;
  •  
  • Identify and partner with the best-placed Engineering, Procurement and Construction Management (EPCM) contractor to deliver the Project;
  •  
  • Update and detail the Project Execution Plan to reflect these inputs; and
  •  
  • Optimise the Operational Readiness Plan.
  •  

Key outcomes of the work include:

 
  • Prioritising procurement of linked process equipment as 'process island packages' where possible, to reduce interface risk;
  •  
  • Contract negotiations being well advanced with all key vendors following the completion of a detailed and rigorous assessment process of all technical and commercial proposals received and subsequent proposal optimisation process;
  •  
  • Competitive tenders completed and significant progress made on the following key packages:
  •  
  • Process equipment including crushers, conveyors, electrical, dryer, kiln, dust collection and refinery;
  •  
  • Electric furnace and calcine transfer system;
  •  
  • Overland powerline and main electrical infrastructure EPC; and
  •  
  • Construction contracts, including bulk earthworks, temporary construction infrastructure and services, and civil works;
  •  
  • Updated market proposals for key opex inputs; and
  •  
  • Capital expenditure and operational expenditure remain in line with the Value Engineering work.
  •  

Environmental and Social

 

Horizonte's environmental and social workstreams are critical to our social licence to operate. As part of the financing due diligence phase and in preparation for the construction of the Project, the sustainability team has further de-risked Araguaia by completing a number of management plans to ensure Araguaia remains compliant with Equator Principles (IV) and IFC Performance Standards with input by consulting groups ERM and Kienbaum.

 

The Company has permitted all infrastructure components of Araguaia, including the award of construction licences for the transmission line and the water pipeline in early 2021.

 

A full suite of social and environmental control plans were developed as part of Araguaia's Brazilian environmental construction licences, and a number of programmes have commenced prior to construction. Some examples of work commenced include the resettlement action plan, social communication programme, safety improvements for school communities located along the PA-449 highway, and the Local Development Agenda programme.

 

Team

 

The Company's newly appointed Head of Projects, Michael Drake, (see announcement 1 March 2021) has mobilised in Brazil and is working from Horizonte's Belo Horizonte office. Mike is building out the execution team. Roles including project controls, contracts and procurement, human resources, industrial relations, and construction managers planned to mobilise in July 2021, supplementing Horizonte's existing strong technical, environmental and permitting team.

 

The Company's offices in Belo Horizonte and London are now fully open, operating with strict Covid compliant health and safety measures.

 

For further information, visit www.horizonteminerals.com or contact:

 
        
 

Horizonte Minerals plc

 

Jeremy Martin (CEO)

 

Anna Legge (Corporate Communications)

 
 

info@horizonteminerals.com

 

+44 (0) 203 356 2901

 
 
 

Peel Hunt (NOMAD & Broker)

 

Ross Allister

 

David McKeown

 
+44 (0)20 7418 8900
 

BMO (Joint Broker)

 

Thomas Rider

 

Pascal Lussier Duquette

 

Andrew Cameron

 
+44 (0) 20 7236 1010
  
 

About Horizonte Minerals:

 

Horizonte Minerals plc is an AIM and TSX-listed nickel development company focused in Brazil. The Company is developing the Araguaia project, as the next major ferronickel mine in Brazil, and the Vermelho nickel-cobalt project, with the aim of being able to supply nickel and cobalt to the EV battery market. Both projects are 100% owned.

 

CAUTIONARY STATEMENT REGARDING FORWARD LOOKING INFORMATION

 

Except for statements of historical fact relating to the Company, certain information contained in this press release constitutes 'forward-looking information' under Canadian securities legislation. Forward-looking information includes, but is not limited to, the ability of the Company to complete the Acquisition as described herein, statements with respect to the potential of the Company's current or future property mineral projects; the success of exploration and mining activities; cost and timing of future exploration, production and development; the estimation of mineral resources and reserves and the ability of the Company to achieve its goals in respect of growing its mineral resources; the ability of the Company to complete the Placing as described herein, and the realization of mineral resource and reserve estimates. Generally, forward-looking information can be identified by the use of forward-looking terminology such as 'plans', 'expects' or 'does not expect', 'is expected', 'budget', 'scheduled', 'estimates', 'forecasts', 'intends', 'anticipates' or 'does not anticipate', or 'believes', or variations of such words and phrases or statements that certain actions, events or results 'may', 'could', 'would', 'might' or 'will be taken', 'occur' or 'be achieved'. Forward-looking information is based on the reasonable assumptions, estimates, analysis and opinions of management made in light of its experience and its perception of trends, current conditions and expected developments, as well as other factors that management believes to be relevant and reasonable in the circumstances at the date that such statements are made, and are inherently subject to known and unknown risks, uncertainties and other factors that may cause the actual results, level of activity, performance or achievements of the Company to be materially different from those expressed or implied by such forward-looking information, including but not limited to risks related to: the inability of the Company to complete the Acquisition as described herein, exploration and mining risks, competition from competitors with greater capital; the Company's lack of experience with respect to development-stage mining operations; fluctuations in metal prices; uninsured risks; environmental and other regulatory requirements; exploration, mining and other licences; the Company's future payment obligations; potential disputes with respect to the Company's title to, and the area of, its mining concessions; the Company's dependence on its ability to obtain sufficient financing in the future; the Company's dependence on its relationships with third parties; the Company's joint ventures; the potential of currency fluctuations and political or economic instability in countries in which the Company operates; currency exchange fluctuations; the Company's ability to manage its growth effectively; the trading market for the ordinary shares of the Company; uncertainty with respect to the Company's plans to continue to develop its operations and new projects; the Company's dependence on key personnel; possible conflicts of interest of directors and officers of the Company, the inability of the Company to complete the Placing on the terms as described herein, and various risks associated with the legal and regulatory framework within which the Company operates. Although management of the Company has attempted to identify important factors that could cause actual results to differ materially from those contained in forward-looking information, there may be other factors that cause results not to be as anticipated, estimated or intended. There can be no assurance that such statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements.

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.

 

SOURCE: Horizonte Minerals PLC

 

View source version on accesswire.com:
https://www.accesswire.com/655654/Horizonte-Minerals-PLC-Announces-Araguaia-Nickel-Project-Operational-Update

News Provided by ACCESSWIRE via QuoteMedia

The Conversation (0)
Closeup of periodic table highlighting nickel with a nickel block on its symbol.

South32 Announces Up to US$100 Million Sale of Cerro Matoso, Shifts Focus to Critical Minerals

South32 (ASX:S32,OTC Pink:SHTLF) said on Monday (July 7) that it has agreed to sell the Cerro Matoso nickel mine in Colombia to a subsidiary of CoreX Holding following recent changes in the nickel market.

South32 now plans to focus on critical minerals, describing its flagship Hermosa project in Patagonia as a “next generation mine.” Hermosa hosts the zinc-lead-silver Taylor sulphide deposit, and the zinc-manganese-silver Clark oxide deposit.

"The Transaction is consistent with our strategy and will further streamline our portfolio toward higher margin businesses in minerals and metals critical to the world’s energy transition,” said South32 CEO Graham Kerr.

Keep reading...Show less
FPX Nickel (TSXV:FPX)

FPX Nickel Completes Production Run of Battery-Grade Nickel Sulphate to Support Discussions with Prospective EV Battery Supply Chain Partners

FPX Nickel Corp. (TSXV: FPX) (OTCQB: FPOCF) ("FPX" or the "Company") is pleased to announce successful production of additional battery-grade nickel sulphate from its Baptiste Nickel Project ("Baptiste" or the "Project"). Building on the success of previous testing campaigns, a production run was completed to produce larger quantities of nickel sulphate crystals. The nickel sulphate samples, which meet the strict target specifications for battery applications, will be provided to selected prospective downstream partners including pCAM producers, battery companies, and automakers pursuing supply security, traceable sourcing, and low carbon intensity production.

"The production of high-purity nickel sulphate further positions us to engage in strategic discussions with prospective downstream partners across the global EV supply chain," commented Martin Turenne, FPX Nickel's President and Director. "This milestone further demonstrates the strategic flexibility of the Baptiste awaruite concentrate and the technical maturity of the awaruite refining process."

Keep reading...Show less
Nickel bars in front of a world map.

Top 9 Nickel-producing Countries

The top nickel producing countries list has been shaken in recent years by Indonesia's rapid rise to the top, beating the Philippines and New Caledonia.

Demand for nickel is mounting. Stainless steel accounts for the vast majority of nickel demand, but electric vehicle (EV) batteries represent a growing application for the base metal as the shift toward a greener future gains steam.

But while nickel's long-term outlook appears bright, it may face headwinds in the short term. Nickel prices have been trending down since breaking US$20,000 per metric ton in May 2024 as weak usage coincides with strong output from top producer Indonesia.

Keep reading...Show less
Ni-Co Energy

Ni-Co Energy Set to Mobilize Critical Minerals Exploration just 90 km from Montreal

Ni-Co Energy Inc. announces that its technical team will be mobilized to the Kremer property around mid-June 2025. The project is located approximately 90 km north of downtown Montreal and about 15 km from the nearest municipality, in a remote forested area with access via an existing road and close proximity to the hydroelectric grid.

Meet The Team:

Keep reading...Show less

Latest Press Releases

Related News

×