Lucara Announces Final Board Project Sanction for the Karowe Underground Expansion Project and Financial Close of Project Finance Facilities

TSX: LUC) (BSE: LUC) (Nasdaq Stockholm: LUC)

Lucara Diamond Corp. ("Lucara" or the "Company") is pleased to announce that the Board of Directors has formally approved the Karowe underground expansion project (the "UGP"), following the Financial Close and satisfaction of all Conditions Precedent pursuant to the previously announced senior secured project financing debt package of US$220 million (the "Facilities") signed July 12, 2021 ( link to news release ). The Facilities include two tranches: A project finance facility of US$170 million to fund the development of the underground project, and a US$50 million working capital facility to re-finance the Company's existing debt and to support on-going operations. A utilization notice from the US$170 million project loan facility has been accepted and first funding for the Karowe underground expansion is expected to be received in mid-September. Capital costs for the UGP totaling US$534 million , will be met with funds from a combination of the Facilities, the projected cash flows from the Karowe open pit mine during the underground construction period, and the equity financings totaling C$41.4 million closed July 15 ( link to news release ), resulting in the UGP being fully financed. A full update on the UGP was released August 10 and can be found here . View PDF version .

Zara Boldt , CFO & Corporate Secretary commented: "We are delighted to have completed this significant milestone following the signing of loan documentation in mid-July. We would like to thank our Lenders and advisors for their efforts towards achieving Financial Close of the Facilities."

Construction efforts have ramped up since the Facilities documentation was executed in mid-July. Ventilation shaft pre-sinking has commenced with the completion of the first set of cover holes, and a total of 4 blasts occurring to date with continued drilling, mucking, and installation of ground support on a 24 hour basis. The ventilation shaft depth below the shaft collar is currently at approximately 17 meters. Mobilization to site of the remaining pre-sinking equipment and contractors is underway. Civil work on the remaining ventilation and production shaft infrastructure is progressing well, with mobilization of temporary generators and civils works associated with the generator pad completed.

Eira Thomas
President and Chief Executive Officer

Follow Lucara Diamond on Facebook , Twitter , Instagram , and LinkedIn

ABOUT LUCARA

Lucara is a leading independent producer of large exceptional quality Type IIa diamonds from its 100% owned Karowe Mine in Botswana . The Company has an experienced board and management team with extensive diamond development and operations expertise. The Company operates transparently and in accordance with international best practices in the areas of sustainability, health and safety, environment and community relations.

The information in this release is accurate at the time of distribution but may be superseded or qualified by subsequent news releases.

This information is information that the Company is obliged to make public pursuant to the EU Market Abuse Regulation. The information was submitted for publication, through the agency of the contact persons set out above at 2:00pm Pacific Time on September 8, 2021 .

CAUTIONARY NOTE REGARDING FORWARD LOOKING STATEMENTS

Certain of the statements made and contained herein and elsewhere constitute forward-looking statements as defined in applicable securities laws. Generally, these forward-looking statements can be identified by the use of forward-looking terminology such as "expects", "anticipates", "believes", "intends", "estimates", "potential", "possible" and similar expressions, or statements that events, conditions or results "will", "may", "could" or "should" occur or be achieved and include, without limitation, projected revenues from production at the Karowe mine, diamond pricing assumptions and diamond market trends, the ultimate use of proceeds from the Facilities; the estimated capital cost and the duration of the construction period; the timing of any drawdowns under the Facilities; and, that the combination of funds from the Facilities, projected cash flows from open pit operations and funds from the equity financing in July will be sufficient to fully fund the UGP.

Forward-looking statements are based on the opinions and estimates of management as of the date such statements are made. These assumptions, opinions and estimates are subject to a number of known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of the Company to be materially different from any future results, performance or achievement expressed or implied by such forward-looking statements. The Company believes that expectations reflected in this forward-looking information are reasonable, but no assurance can be given that these expectations will prove to be accurate and such forward-looking information included herein should not be unduly relied upon. There can be no assurance that such forward looking statements will prove to be accurate, as the Company's results and future events could differ materially from those anticipated in this forward-looking information as a result of those factors discussed in or referred to under the heading "Risks and Uncertainties" in the Company's most recent Annual Information Form and under the heading "Risk Factors" in the Prospectus, a preliminary version of which is available at https://www.sedar.com , as well as changes in general business and economic conditions, changes in interest and foreign currency rates, the supply and demand for, deliveries of and the level and volatility of prices of rough diamonds, costs of power and diesel, acts of foreign governments and the outcome of legal proceedings, inaccurate geological and recoverability assumptions (including with respect to the size, grade and recoverability of mineral reserves and resources), and unanticipated operational difficulties (including failure of plant, equipment or processes to operate in accordance with specifications or expectations, cost escalations, unavailability of materials and equipment, government action or delays in the receipt of government approvals, industrial disturbances or other job actions, adverse weather conditions, and unanticipated events relating to health safety and environmental matters).

Accordingly, readers are cautioned not to place undue reliance on these forward-looking statements which speak only as of the date the statements were made, and the Company does not assume any obligations to update or revise them to reflect new events or circumstances, except as required by law.

Lucara Announces Final Board Project Sanction for the Karowe Underground Expansion Project and Financial Close of Project Finance Facilities (CNW Group/Lucara Diamond Corp.)

SOURCE Lucara Diamond Corp.

Cision View original content to download multimedia: https://www.newswire.ca/en/releases/archive/September2021/08/c4654.html

News Provided by Canada Newswire via QuoteMedia

The Conversation (0)
A small circle of white diamonds.

Alrosa to Cut Production and Staff to Counter Diamond Market Slump

Alrosa (MCX:ALRS), Russia's state-owned diamond miner, plans to suspend certain operations and reduce its workforce in 2025 as it confronts falling global diamond prices and the impact of international sanctions.

CEO Pavel Marinychev outlined the measures during an interview with local media in Yakutia, the company’s primary production hub, as reported by Reuters on Thursday (November 21).

The global diamond industry is experiencing a downturn, with Marinychev describing the situation as a "deep crisis."

Keep reading...Show less

STAR DIAMOND CORPORATION ANNOUNCES THIRD QUARTER 2024 RESULTS

TSX: DIAM

Star Diamond Corporation ("Star Diamond" or the "Company") reports that the unaudited financial results for the quarter ended September 30, 2024 will be filed today on SEDAR+ and may be viewed at www.sedarplus.ca once posted.

Overview

News Provided by Canada Newswire via QuoteMedia

Keep reading...Show less
Close up of diamonds in a mine.

Rio Tinto: Phase 1 of Diavik's A21 Pipe Complete, Diamond Production Next

Mining giant Rio Tinto (ASX:RIO,NYSE:RIO,LSE:RIO) said in a press release on Thursday, October 3, that it has completed the development and construction of Phase 1 of the A21 underground mine at its 100 percent-owned Diavik diamond mine.

The company detailed the construction process, which involved over 1,800 meters of underground tunnel development.

The Diavik diamond mine is located at the bottom of Lac de Gras in Canada's Northwest Territories. A21 is the fourth diamond pipe of the project and was opened by Rio Tinto in 2018. The company made the decision to go ahead with Phase 1 in February 2023, investing US$40 million.

Phase 1 of mining at A21 is expected to produce 1.4 million carats of diamonds.

Keep reading...Show less
A locked gate.

Burgundy Diamond Pauses Ekati Development, Asks Northwest Territories for More Support

Burgundy Diamond Mines (ASX:BDM,OTC Pink:BDMMF) has paused plans for further development at the Ekati diamond mine, saying diamond prices have fallen at least 20 percent since it acquired the project.

In a letter to RJ Simpson, premier of Canada's Northwest Territories (NWT), Burgundy said that along with the decreasing prices, the diamond industry has been receiving “very little support."

“Environmental requirements are getting unnecessarily more onerous, government agencies are inflexible to change and the burden placed on the asset is increasing,” the company said, adding that it may need to revisit the viability of the Ekati asset and focus on growth elsewhere should these problems continue.

Keep reading...Show less
1,094 carat rough diamond from Lucara Diamond's Karowe mine.

Lucara Continues Streak of Big Diamond Discoveries with 1,094 Carat Find at Karowe

Only a month after the discovery of the second largest diamond ever recorded, Lucara Diamond (TSX:LUC,OTC Pink:LUCRF) has announced the recovery of another significant stone from its Karowe mine in Botswana.

The new find is 1,094 carats compared to the massive 2,942 carat rough diamond uncovered by Lucara in August, solidifying Karowe’s reputation as one of the world’s most prolific sources of large diamonds.

The rough diamond is the sixth stone over 1,000 carats that Lucara has unearthed from the mine. According to the company, the EMPKS ore type at Karowe's South Lobe hosts these large, high-value stones.

Keep reading...Show less

STAR - ORION SOUTH DIAMOND PROJECT REVISED MINERAL RESOURCES ESTIMATE TECHNICAL REPORT FILED ON SEDAR+

Star Diamond Corporation ("Star Diamond" or the "Company") is pleased to announce that the Technical Report documenting the Revised Mineral Resources Estimate (see News Release dated July 24, 2024 ) for the Star Orion South Diamond Project (the "Project") has been filed on SEDAR+ ( www.sedarplus.ca ). This Technical Report has also been posted on the Star Diamond website: Technical Report 2024 .

Star Diamond Corporation logo (CNW Group/Star Diamond Corporation)

The scientific and technical information contained in this press release has been prepared and verified by A.C.A. Howe International Limited ("Howe"), under the supervision of Mr. Daniel C. Leroux, M.Sc., P. Geo. and the Mineral Resource estimation methodology under the supervision of Peter Ravenscroft , FAusIMM, of Ravenscroft Mining Advisors, an independent mining consultant, and a Qualified Person ("QP") within the meaning of National Instrument 43-101 – Standards of Disclosure for Mineral Projects ("NI 43-101") of the Canadian Securities Administrators. This Revised Mineral Resources estimate uses diamond industry standard methods which are rigorously applied to the Star and Orion South evaluation data, acknowledging the significant control that fundamental kimberlite geology has on the distribution of diamonds within these deposits.

The Revised Mineral Resources estimate will now be incorporated into a re-optimized open pit mine plan for the Project, which will include a re-evaluation of Mineral Reserves and an economic assessment based thereon. It is anticipated this work will be completed during 2024-25 and will result in an updated Pre-feasibility Study including a revised statement of Mineral Reserves for the Project, if warranted, and an economic assessment based thereon. Accordingly, the Mineral Resources and economic assessment previously disclosed by Star Diamond for the Project should no longer be relied upon.

All technical information in this press release has been prepared under the supervision of George Read , Senior Vice President Corporate Development, a registered Professional Geoscientist in the Provinces of Saskatchewan and British Columbia and Mark Shimell , Vice President Exploration, a registered Professional Geoscientist in the Provinces of Saskatchewan and Alberta , who are Star Diamond's QP's under the definition of NI 43-101.

About Star Diamond Corporation

Star Diamond is a Canadian-based corporation engaged in the acquisition, exploration and development of mineral properties. Shares of Star Diamond trade on the Toronto Stock Exchange under the trading symbol "DIAM".   Star Diamond's most significant asset is its 100% interest in the Fort à la Corne Project in central Saskatchewan.  These kimberlites are located in close proximity to established infrastructure, including paved highways and the electrical power grid, which provide significant advantages for future mine development.

Stay Connected with Us:
X (Twitter) - https://twitter.com/StarDiamondCorp
LinkedIn - https://www.linkedin.com/company/star-diamond-corp/
Facebook - https://web.facebook.com/stardiamondcorp
Instagram - https://www.instagram.com/stardiamondcorp
YouTube - https://youtube.com/@StarDiamondCorp

Caution Regarding Forward-looking Statements

This press release contains "forward-looking statements" and/or "forward-looking information" (collectively, "forward-looking statements") within the meaning of applicable securities legislation. All statements, other than statements of historical fact, are forward-looking statements. Forward-looking information is often, but not always, identified by the use of words such as "anticipate", "believe", "expect", "plan", "intend", "forecast", "target", "project", "guidance", "may", "will", "should", "could", "estimate", "predict" or similar words suggesting future outcomes or language suggesting an outlook. In particular, statements regarding Star Diamond's future operations, future exploration and development activities or other development plans constitute forward-looking statements. By their nature, statements referring to mineral reserves or mineral resources constitute forward-looking statements.

Forward-looking statements in this press release include but are not limited to statements with respect to the Revised Mineral Resources Estimate; improvement in the Mineral Resource estimate; the re-optimization of the Star and Orion South open pits; the publication of the Technical Report; and the aim of the Company to undertake a PFS and Feasibility Study and timelines.

These forward-looking statements are based on Star Diamond's current beliefs as well as assumptions made by and information currently available to Star Diamond and involve inherent risks and uncertainties, both general and specific. Risks exist that forward-looking statements will not be achieved due to a number of factors including, but not limited to, developments in world diamond markets, changes in diamond prices, risks relating to fluctuations in the Canadian dollar and other currencies relative to the US dollar, changes in exploration, development or mining plans due to exploration results and changing budget priorities of Star Diamond, the impact of changes in the laws and regulations regulating mining exploration, development, closure, judicial or regulatory judgments and legal proceedings, operational and infrastructure risks and the additional risks described in Star Diamond's most recently filed Annual Information Form, annual and interim MDA.

SOURCE Star Diamond Corporation

Cision View original content to download multimedia: http://www.newswire.ca/en/releases/archive/September2024/05/c1009.html

News Provided by Canada Newswire via QuoteMedia

Keep reading...Show less