LaFleur Minerals Inc. (CSE: LFLR) (OTCQB: LFLRF) (FSE: 3WK0) ("LaFleur Minerals" or the "Company") is pleased to provide the following corporate updates.

BEACON GOLD MILL RESTART AND SWANSON GOLD PROJECT UPDATES

The Beacon Mill is a fully refurbished and permitted gold mill situated in Val-d'Or, Québec, on the mineral-rich Abitibi Greenstone Belt, where LaFleur Minerals is laser focused on restarting gold production using large bulk samples and mineralized material from nearby gold deposits. With the price of gold in excess of USD$3,000 per ounce, many nearby deposits can be quickly monetized using the Company's 100%-owned Beacon Mill. The mill's operating capacity exceeds 750 tons per day and is strategically located in a highly prospective mining region for gold exploration and development, within an area that is host to over 100 historical and currently operating mines. The advancement of operations at the Beacon Mill has transformational qualities for the Company, evolving it from explorer to a near term gold producer in a Tier 1 jurisdiction with significant upside potential.

Cannot view this image? Visit: https://images.newsfilecorp.com/files/6526/245435_44764ad25410f882_001.jpg

Figure 1: Photo of interior of Beacon Mill currently undergoing detailed inspections for restart

To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/6526/245435_44764ad25410f882_001full.jpg

Cannot view this image? Visit: https://images.newsfilecorp.com/files/6526/245435_44764ad25410f882_002.jpg

Figure 2: Photo of exterior of Beacon Mill in Val-d'Or, Québec

To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/6526/245435_44764ad25410f882_002full.jpg

Equipment inspections, parts inventory, and maintenance work continues on a full-time basis at the Company's Beacon Gold Mill as part of its restart program (Figure 1 and Figure 2). A final plan and budget to restart the mill will be completed by ABF Mines by late April once final inspections are complete. The Company has also engaged an environmental services company based in Val-d'Or, Québec to complete a federal government requirement to assess and monitor the environmental effects on the tailings and finishing ponds at the Beacon tailings storage facility ("TSF"). In addition, the Company will be engaging an engineering firm to complete a geotechnical assessment/inspection of the TSF and complete any required repairs or upgrades prior to commencing production at the mill. The Company remains committed to restart production at the Beacon Mill to process bulk samples and/or for custom milling purposes prior to the end of 2025, or once all required restart work has been completed and final approvals have been received by the Québec government.

SWANSON GOLD PROJECT UPDATES

The Swanson Gold Project holds a large position in an attractive mining jurisdiction, extending over 16,000 hectares in size and includes several prospects rich in gold and critical metals, previously held by Monarch Mining, Abcourt Mines, and Globex Mining. The consolidated Swanson Gold Project covers a major structural break that hosts the Swanson, Bartec, and Jolin gold targets along with numerous other significant gold showings. The Swanson Gold Project is easily accessible by road with a rail line running through the property, allowing direct access to the Beacon Gold Mill, further enhancing its development potential. The Swanson Gold Project has had in excess of 36,000 metres of historical drilling, which underscores the advanced exploration and development potential of the project, which includes several favourable gold bearing regional structures and deformation corridors extending across the property. Since acquiring the Swanson deposit and consolidating the large claims package, the Company has deployed in excess of $1 million in flow-through funds, completed detailed soil geochemistry and prospecting across several gold targets, completed a very-high resolution airborne magnetic and VLF-EM geophysical survey, and is currently in the process of completing a ground IP survey over the Swanson, Jolin, and Bartec gold deposits. All of this work has allowed the Company to refine priority drill-ready targets and help derisk the upcoming diamond drilling program. Several new promising gold targets have been identified from the recent surface exploration and geophysics programs, highlighting the potential for mineral resource growth and new discoveries at Swanson.

The Company has submitted an application for a diamond drilling permit to the Québec government for the Swanson Gold Project and will be sending Requests for Quotes (RFQ) to local drilling contractors, with drilling expected to commence in the spring at the Swanson, Bartec, Jolin and other recently delineated gold targets.

RESULTS OF ANNUAL GENERAL AND SPECIAL MEETING

LaFleur Minerals also announces the results of its Annual General and Special Meeting ("AGSM") held on March 7, 2025. All matters presented at the AGSM were approved by shareholders including: (1) the Company's 10% Rolling Share Option Plan for continuation for a further three years, (2) the Company's 20% Restricted Share Unit Plan for continuation for a further three years, and (3) the Company's acquisition of an exclusive option to acquire 100% interest in and to certain mining claims and a mining lease located in the Province of Québec, pursuant to the terms and conditions of an option agreement entered into between the Company and BullRun Capital Inc. dated September 17, 2024 (refer to the Company's news release dated September 24, 2024).

EXERCISE OF WARRANTS

Additionally, the Company also announces that it has received total gross proceeds of $816,750 from the exercise of 7,425,000 warrants (the "Warrants"). The Warrants were issued in relation to a private placement completed in March 2023 and had an expiry date of March 14, 2025, which were exercised in full.

QUALIFIED PERSON STATEMENT

All scientific and technical information in this news release has been prepared and approved by Louis Martin, P.Geo., Technical Advisor to the Company and considered a Qualified Person for the purposes of NI 43-101.

About LaFleur Minerals Inc.

LaFleur Minerals Inc. (CSE: LFLR) (OTCQB: LFLRF) (FSE: 3WK0) is focused on the development of district-scale gold projects in the Abitibi Gold Belt near Val-d'Or, Québec. Our mission is to advance mining projects with a laser focus on our resource-stage Swanson Gold Project and the Beacon Gold Mill and Property, which have significant potential to deliver long-term value. The Swanson Gold Project is over 16,000 hectares (160 km2) in size and includes several prospects rich in gold and critical metals previously held by Monarch Mining, Abcourt Mines, and Globex Mining. LaFleur has recently consolidated a large land package along a major structural break that hosts the Swanson, Bartec, and Jolin gold deposits and several other showings which make up the Swanson Gold Project. The Swanson Gold Project is easily accessible by road with a rail line running through the property allowing direct access to several nearby gold mills, further enhancing its development potential. Lafleur Minerals' fully-refurbished and permitted Beacon Gold Mill is capable of processing over 750 tonnes per day and is being considered for processing mineralized material at Swanson and for custom milling operations for other nearby gold projects.

ON BEHALF OF LAFLEUR MINERALS INC.

Paul Ténière, P.Geo.
Chief Executive Officer
E: info@lafleurminerals.com

LaFleur Minerals Inc.
1500-1055 West Georgia Street
Vancouver, BC V6E 4N7

Neither the Canadian Securities Exchange nor its Regulation Services Provider accepts responsibility for the adequacy or accuracy of this news release.

Cautionary Statement Regarding "Forward-Looking" Information

This news release includes certain statements that may be deemed "forward-looking statements." All statements in this new release, other than statements of historical facts, that address events or developments that the Company expects to occur, are forward-looking statements. Forward-looking statements are statements that are not historical facts and are generally, but not always, identified by the words "expects", "plans", "anticipates", "believes", "intends", "estimates", "projects", "potential" and similar expressions, or that events or conditions "will", "would", "may", "could" or "should" occur. Forward-looking statements in this news release include, without limitation, statements related to the use of proceeds from the Offering. Although the Company believes the expectations expressed in such forward-looking statements are based on reasonable assumptions, such statements are not guarantees of future performance and actual results may differ materially from those in the forward-looking statements. Factors that could cause the actual results to differ materially from those in forward-looking statements include market prices, continued availability of capital and financing, and general economic, market or business conditions. Investors are cautioned that any such statements are not guarantees of future performance and actual results or developments may differ materially from those projected in the forward-looking statements. Forward-looking statements are based on the beliefs, estimates and opinions of the Company's management on the date the statements are made. Except as required by applicable securities laws, the Company undertakes no obligation to update these forward-looking statements in the event that management's beliefs, estimates or opinions, or other factors, should change.

To view the source version of this press release, please visit https://www.newsfilecorp.com/release/245435

News Provided by Newsfile via QuoteMedia

LFLR:CNX
LaFleur Minerals

LaFleur Minerals Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

The Conversation (0)
LaFleur Minerals (CSE:LFLR)

LaFleur Minerals

Advancing a vertically integrated gold development platform in Québec’s Abitibi Gold Belt

Advancing a vertically integrated gold development platform in Québec’s Abitibi Gold Belt Keep Reading...

Investor Insight

LaFleur Minerals is advancing a vertically integrated gold development platform anchored by the PEA-stage Swanson Gold Project and its 100 percent-owned Beacon Gold Mill. The company is advancing its mine-to-mill strategy through recommissioning of the Beacon Gold Mill and proposed offtake and prepayment facility agreement with Trafigura.

Overview

LaFleur Minerals (CSE: LFLR, OTCQB: LFLRF) is a Québec-focused gold development company advancing a vertically integrated mine-to-mill platform in the Abitibi Greenstone Belt. The company’s strategy combines development of the PEA-stage Swanson Gold Project with ownership of the fully permitted Beacon Gold Mill, providing existing processing infrastructure to support a phased mine-to-mill development strategy.

LaFleur Minerals' Swanson Gold Project and Beacon Mine and Mill location within the Abitibi Gold Belt in Quebec, Canada

The Swanson Gold Project is the cornerstone of the company’s exploration and development strategy. The updated 2026 mineral resource estimate outlines 160.3 koz Au of indicated resources and 66.8 koz Au of inferred resources and is supported by extensive historical drilling and recent diamond drilling by LaFleur. The recently completed preliminary economic assessment further supports advancement of the project, outlining robust economics and a phased development strategy.

The Beacon Gold Mill provides a strategic processing asset located approximately 66 kilometres from the Swanson Gold Project. The fully permitted mill has an initial processing capacity of 750 tpd and is undergoing final recommissioning. As of September 1, 2026, the mill recommissioning program was approximately 95 percent complete with remaining tasks including repairs and upgrades to the tailings storage facility to be completed in Q4.

LaFleur Mineral's refurbished rotary drum filtration circuit

LaFleur is also progressing proposed agreements with Trafigura comprising a prepayment facility of up to C$30 million and a gold doré purchase agreement to support development of the Swanson Gold Deposit and processing operations at the Beacon Gold Mill.

The proposed agreements remain subject to definitive documentation, final due diligence, regulatory approvals, and customary closing conditions. Together with the acquisition of the McKenzie East Gold Project, multi-phase diamond drilling program at Swanson, and an experienced management and technical team, these initiatives support the company’s strategy of building a district-scale gold development platform in Québec.

Company Highlights

  • District-scale land package: Controls more than 200 square kilometres of mineral claims in Québec’s Abitibi Greenstone Belt near Val-d’Or.
  • Growing gold resource: The 2026 mineral resource estimate (MRE) for the Swanson Gold Project outlines 160.3 koz indicated resource (2.96 Mt at 1.69 g/t gold) and 66.8 koz inferred resource (1.08 Mt at 1.93 g/t gold).
  • Vertically integrated platform: Owns the 100 percent-owned Beacon Gold Mill, a fully permitted processing facility with an initial capacity of 750 tonnes per day (tpd) and expansion potential to 1,250 tpd to support future production.
  • Strong project economics: The preliminary economic assessment (PEA) outlines an after-tax net present value (5 percent) of C$101 million, a 65 percent internal rate of return, and a 1.8-year payback period, based on a conservative US$2,750 per ounce gold price.
  • Low-capital development: Initial capital expenditure estimated at C$31 million including upgrading the Beacon Gold Mill to 1,250 tpd while leveraging existing infrastructure.
  • Competitive operating costs: Estimated all-in sustaining costs (AISC) of US$1,569 per ounce.
  • Mill recommissioning nearly complete: Mechanical reconditioning and recommissioning of the Beacon Gold Mill was approximately 95 percent complete as of September 1, 2026, with the remaining tasks to be completed in Q4.
  • Proposed Trafigura agreements: LaFleur and Trafigura continue to work toward definitive documentation for a proposed prepayment facility of up to C$30 million and a gold doré purchase agreement. Trafigura completed a site visit in August as part of their due diligence. The proposed agreements remain subject to final due diligence, regulatory approvals, and customary closing conditions.
  • District expansion: Recently acquired a 100 percent interest in the McKenzie East Gold Project, strengthening its land position in the Val-d’Or district near the Beacon Gold Mill.
  • Expanded diamond drilling program at Swanson Deposit: The Company continues to drill deeper at the Swanson Deposit and below the current pit shell in the PEA, with promising gold results indicating the mineralized zones continue at much deeper depths.

Key Projects

Swanson Gold Project

Regional map of the Abitibi Gold Belt in Quebec, Canada, highlighting LaFleur Minerals' Swanson Gold Project and the Beacon Gold Mill

The Swanson Gold Project is LaFleur Minerals’ flagship asset and the foundation of its vertically integrated development strategy. Located in Québec’s prolific Abitibi Greenstone Belt near Val-d’Or, the Swanson Gold Project includes a total of 481 claims and 1 mining lease (200.7 km2 in size) along a major gold-bearing structural corridor. The property benefits from excellent infrastructure, including excellent road access, and proximity to the CN rail line.

The updated 2026 mineral resource estimate (MRE) outlines 160.3 koz of indicated resources (2.96 Mt at 1.69 g/t gold) and 66.8 koz of inferred resources (1.08 Mt at 1.93 g/t gold), representing approximately 30 percent growth in indicated resources compared to the 2024 historical estimate. The mineralized zone measures approximately 475 metres long, 425 metres wide and extends to approximately 500 metres depth, remaining open in all directions. Drilling continues at deeper depths to confirm continuity and gold grades below the existing pit shell.

The project is supported by more than 36,000 metres of historical drilling completed at the Swanson Deposit and over 20,000 metres completed by LaFleur on the Swanson Deposit, and Jolin, Bartec, and Jackson targets. Existing infrastructure includes a decline portal and underground ramp extending to approximately 80 metres below surface. The company is also in the process of permitting a 100,000-tonne open-pit bulk sample within the Swanson mining lease representing approximately 3 percent of the current resource.

The recently completed preliminary economic assessment outlines robust project economics while leveraging the nearby Beacon Gold Mill. Together, the Swanson Gold Project and Beacon Gold Mill form the foundation of LaFleur’s integrated mine-to-mill development strategy.

Beacon Gold Mill & Property

Beacon Gold Mill operated by LaFleur Minerals

The Beacon Gold Mill is a key component of LaFleur’s vertically integrated development strategy. Located approximately 20 kilometres east of the city of Val-d’Or and 66 kilometres from the Swanson Gold Project, the fully permitted processing facility has an initial capacity of 750 tonnes per day (tpd) and is expected to process mineralized material from the Swanson Gold Project while providing long-term potential for custom milling as part of a regional hub-and-spoke strategy.

The preliminary economic assessment includes an expansion to 1,250 tpd as part of the project’s C$31 million initial capital expenditure, with longer-term expansion potential to more than 3,000 tpd through the addition of a parallel processing circuit. Direct access to the CN Rail line provides a low transportation cost compared to hauling by trucks, supporting the project’s operating cost profile.

As of September 1, 2026, recommissioning of the Beacon Gold Mill was approximately 95 percent complete with remaining tasks including maintenance and upgrades to the tailings storage facility to be completed in Q4 2026. Major processing circuits, including crushing, grinding, filtration, ore storage, thickening and reagent systems, were substantially complete. The company plans to complete the remaining mechanical work and proceed to staged commissioning and restart, subject to the timely delivery of the remaining long-lead equipment and completion of maintenance and upgrade work on the tailings storage facility.

Ball and rod mills within the grinding circuit at the Beacon Gold Mill operated by LaFleur Minerals

LaFleur is also progressing proposed agreements with Trafigura comprising a proposed prepayment facility of up to C$30 million and a gold doré purchase agreement to support development of the Swanson Gold Deposit and processing operations at the Beacon Gold Mill. The proposed agreements remain subject to definitive documentation, final due diligence, regulatory approvals, and customary closing conditions.

McKenzie East Gold Project

The McKenzie East Gold Project expands LaFleur’s district-scale presence in Québec’s Val-d’Or mining camp. The property is adjacent to Fresnillo’s McKenzie Break deposit and is located near established infrastructure, including the Beacon Gold Mill.

The acquisition strengthens the company’s regional land position and complements its strategy of building a district-scale gold development platform. Its proximity to both the Swanson Gold Project and the Beacon Gold Mill provides opportunities to leverage existing infrastructure while advancing exploration across the broader portfolio.

Management Team

Andrew Elinesky - CEO

Andrew Elinesky is an experienced senior executive and financial leader who has worked on building and leading companies in Canada, the United States, and the United Kingdom. With over two decades in financing, acquisitions, operational development and corporate growth, he previously held roles in companies such as Sabre Gold Mines Corp and McEwen Mining.

Paul Ténière – President and Director

Paul Ténière has more than 25 years of experience in mine development, geology and project management. He has held senior leadership roles across multiple mining companies, is a former Senior Listings Manager and Mining Expert at the TSX and TSX Venture, and is a recognized expert in NI 43-101 compliance and technical reporting.

Harry Nijjar – CFO

Harry Nijjar is a financial expert with extensive experience in corporate finance, regulatory compliance, and capital markets. Harpreet has advised numerous public and private mining companies on strategic financial planning and investor relations.

Kal Malhi – Chairman

A successful entrepreneur and the founder of Bullrun Capital, Kal Malhi has raised over $300 million for various public and private companies across multiple industries, including mining, biotechnology and technology.

Jean Lafleur – Senior Advisor

A highly respected geologist with over 40 years of experience in the mining sector, Jean Lafleur has led multiple exploration programs and mining projects, contributing to major gold discoveries worldwide.

Silverco Mining Ships First Cusi Concentrate, Provides Cusi Restart Update

Silverco Mining Ships First Cusi Concentrate, Provides Cusi Restart Update

Silverco Mining Ltd. (TSXV: SICO) (OTCQB: SICOF) ("Silverco" or the "Company") is pleased to provide an update on the restart of its 100% owned Cusi Property ("Cusi") in Chihuahua, Mexico. First concentrate was shipped from the project on schedule, and restart capital remains on budget.Mark... Keep Reading...
OUTSTANDING HIGH-GRADE RESULTS FROM MAIDEN ARMIDALE DRILLING

OUTSTANDING HIGH-GRADE RESULTS FROM MAIDEN ARMIDALE DRILLING

Red Mountain Mining (RMX:AU) has announced OUTSTANDING HIGH-GRADE RESULTS FROM MAIDEN ARMIDALE DRILLINGDownload the PDF here. Keep Reading...
LaFleur Minerals Continues to Expand Swanson Gold Deposit Mineralization Near Surface and Along Strike with 2.52 g/t Au over 14.35 Metres

LaFleur Minerals Continues to Expand Swanson Gold Deposit Mineralization Near Surface and Along Strike with 2.52 g/t Au over 14.35 Metres

LaFleur Minerals Inc. (CSE: LFLR) (OTCQB: LFLRF) (FSE: 3WK0) ("LaFleur Minerals" or the "Company") is pleased to report assay results from the Fall 2026 Swanson Gold Deposit drill program, which is within the much larger Swanson Gold Project ("Swanson" or the "Project") drill program. This... Keep Reading...
Brixton Metals Drills its Highest Silver Grades Ever in a New Shallow Brownfields Discovery at its Langis Project, Ontario

Brixton Metals Drills its Highest Silver Grades Ever in a New Shallow Brownfields Discovery at its Langis Project, Ontario

Hole 477 Yields 142,770 g/t Silver or 4,164 oz/t Silver over 0.3 m Within 1.1 m of 39,675 g/t Silver, All Within 3.0 m of 14,559 g/t Silver Hole 480 Returned 5.0 m of 704 g/t Silver Including 1.4 m of 2,479 g/t Silver Brixton Metals Corporation (TSX-V: BBB, OTCQX: BBBXF) (the "Company" or... Keep Reading...
Sranan Gold Discovers New Gold Zone at Lawatino 300 m Northeast of the 101 Zone

Sranan Gold Discovers New Gold Zone at Lawatino 300 m Northeast of the 101 Zone

Sranan Gold Corp. (CSE: SRAN) (OTCQB: SRANF) (FSE: P84) (Tradegate: P84) ("Sranan" or the "Company") announces the discovery of a new showing of gold mineralization, the RB Zone, located approximately 300 metres northeast of the 101 Zone within its 18,468-hectare Lawatino Gold Project in... Keep Reading...
Brixton Metals Announces Closing of Final Tranche of Non-Brokered Private Placement

Brixton Metals Announces Closing of Final Tranche of Non-Brokered Private Placement

Not for distribution to United States Newswire Services or for dissemination in the United States Brixton Metals Corporation (TSX- V: BBB, OTCQX: BBBXF) (the "Company" or "Brixton") is pleased to announce that it has closed a third and final tranche of a non-brokered private placement offering... Keep Reading...
LaFleur Minerals

LaFleur Minerals Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

Interactive Chart

Latest Press Releases

Related News