Galena Mining

Activities and Cashflow Report For Quarter Ended 31 December 2022

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) reports on its activities for the quarter ended 31 December 2022 (the “Quarter”), primarily focused on construction of its 60%- owned Abra Base Metals Mine (“Abra” or the “Project”) located in the Gascoyne region of Western Australia.


HIGHLIGHTS:

  • Abra Project construction completed on time in December 2022. Project construction expenditure within 1% of budget.
  • Ore commissioning commenced and first concentrate produced in January 2023.
  • Focus now on completing plant commissioning and ramping up production.
  • Underground development achieved a record 1,122m advance during the Quarter with the decline reaching 1,268mRL. (282m vertical below the surface and 45m below top of the orebody).
  • Cash balance at Quarter-end A$41.0M.
ABRA BASE METALS MINE (60%-OWNED)

Abra comprises a granted Mining Lease, M52/0776 and surrounding Exploration Licence E52/1455, together with several co-located General Purpose and Miscellaneous Leases. The Project is 100% owned by Abra Mining Pty Limited (“AMPL” the Abra Project joint-venture entity), which in turn is 60% owned by Galena, with the remainder owned by Toho Zinc Co., Ltd. (“Toho”) of Japan.

Abra is fully permitted, and construction of the processing plant and surface infrastructure was completed in December 2022. First production of its lead-silver concentrate occurred in January 2023 with first product shipment scheduled for the March 2023 quarter.

Project construction / development

Abra Project construction works were completed by the end of the Quarter and ore commissioning commenced with first ore feed into the plant and first concentrate produced as part of the plant commissioning process in early January 2023 (see Galena ASX announcements of 10 January 2023 and 13 January 2023). Abra construction completed within 1% of forecast construction costs.

Operational Readiness

By the end of the quarter 90% of the operational staff have been employed along with both internal and external maintenance service providers. All site critical spares have been identified and procured. Site reagents and other consumables have been established.

Underground power, ventilation, and the installation of the second egress (ladderways) have enabled multiple ore headings to be operational and the primary pumping station will be completed in the March quarter.

The site assay laboratory was nearing completion by the end of the quarter and final commissioning in January is expected to significantly improve assay turn around and controls.

Applications are being lodged for regulatory approvals, licences or permits as they are required for completion of construction, commissioning and commencement of operations.

Underground mining – During the Quarter, 1,122 metres of development was completed and at Quarter-end total development reached 3,592 metres consisting of 1,978 metres of decline development and 1,614 metres of lateral development. The decline reached 1,268mRL, 45 metres below the top of the Abra orebody and 282 metres vertically below the surface.

During December, several ore drives commenced on the 1,280 and 1,300mRL levels which will deliver the required ore for plant commissioning in January 2023. At the end of the Quarter, a total of 26,000t of ore had been stockpiled on the ROM pad in preparation for ore processing commissioning and the commencement of concentrate production.

During the quarter a total of 75 (10,777m) underground diamond holes were completed for grade control and mine planning purposes. Mine planning and scheduling work was completed with this information in preparation for the production activities in 2023.

On 24 December 2022, the primary ventilation fan motor failed, and alternative ventilation fans were installed to resume underground work. Five days of mining activities were lost during this time and this delay is not expected to delay the plant processing commissioning during January 2023.


Click here for the full ASX Release

This article includes content from Galena Mining, licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.


G1A:AU
Galena Mining

Galena Mining Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

The Conversation (0)
Galena Mining (ASX:G1A)

Galena Mining


Keep reading...Show less
Galena Mining

Abra Construction At 97% Complete – First Ore Stockpiled For January Processing

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 97% complete as of 30 November 2022. Processing plant commissioning is progressing quickly with practical completion now expected in December 2022. Ore currently being mined from underground is being stockpiled in readiness for processing to begin in January 2023. Concentrate production will commence January 2023.

Keep reading...Show less
Galena Mining

Abra Construction At 92% Complete – Reaches First Ore Underground

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 92% complete as of 31 October 2022. Underground mine has reached the first ore (see ASX announcement 14 November 2022) and plant commissioning continues in several key areas with the project focussed on achieving first concentrate production in Q1 2023.
Keep reading...Show less
Galena Mining

Abra Mine Reaches Ore

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the underground development at its Abra Base Metals Mine (“Abra” or the “Project”) has reached the Abra orebody. Commissioning has commenced in several key areas of the processing facility and the Power Station (Pacific Energy) completed full integration of the hybrid gas/solar/battery energy storage system (BESS) power station on 10 November. The project remains on track for first concentrate production in Q1 2023.
Keep reading...Show less
Galena Mining

Galena Mining Activities Report For Quarter Ended 30 September 2022

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) reports on its activities for the quarter ended 30 September 2022 (the “Quarter”), primarily focused on construction of its 60%- owned Abra Base Metals Mine (“Abra” or the “Project”) located in the Gascoyne region of Western Australia.

Keep reading...Show less

Pan American Silver Announces the Sale of La Arena for US$245 Million Cash Upfront and US$50 Million Contingent Payment

  • retains a 1.5% gold net smelter return royalty for the La Arena II project

Pan American Silver Corp. (NYSE: PAAS) (TSX: PAAS) (" Pan American ") announces that it has agreed to sell its 100% interest in La Arena S.A. ("La Arena"), which owns the La Arena gold mine as well as the La Arena II project in Peru, to Jinteng (Singapore) Mining Pte. Ltd., a subsidiary of Zijin Mining Group Co., Ltd. (collectively, "Zijin") for US$245 million cash upfront and a US$50 million contingent payment.

"With the sale of La Arena, we continue to deliver on our strategy to optimize our portfolio, following the Yamana transaction, while maintaining future upside through the retention of royalties," said Michael Steinmann, President and Chief Executive Officer of Pan American. "Proceeds from the transaction will further strengthen our financial position and allow us to deliver on our capital allocation priorities of investing in high-quality assets, debt reduction and returning capital to our shareholders."

News Provided by Business Wire via QuoteMedia

Keep reading...Show less
Silver bar and metal.

Top 5 Canadian Silver Stocks of 2024

Silver demand is forecast to reach its second highest level ever in 2024 at 1.2 billion ounces, driven by industrial market segments such as photovoltaics and electric vehicles.

This high demand is coming alongside flat production growth, and is creating a situation that would seemingly be ripe for a price breakout. However, the first months of the year saw the metal trade in the US$22 to US$24 per ounce range.

The beginning of March brought a shift in the market, and silver started to make gains. Following its sister metal gold higher, silver hit a quarterly high of US$25.71 on March 20 before reaching an 11 year high of US$28.85 on April 14.

Keep reading...Show less

MAG Announces First Quarter 2024 Production From Juanicipio

MAG Silver Corp. (TSX NYSE American: MAG) ("MAG" or "MAG Silver") reports production from Juanicipio (56% 44% Fresnillo plc ("Fresnillo") and MAG, respectively) for the first quarter ("Q1") ended March 31, 2024.

Q1 Highlights

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
Silver bars and coins.

Silver Price Update: Q1 2024 in Review

2023 was a relatively lackluster year, silver largely traded on volatility between US$22 and US$25 per ounce.

The white metal started 2024 with less volatility and remained rangebound for the first eight weeks. Silver dropped to US$22.08 per ounce on January 21, marking its quarterly low.

Silver started seeing gains in March with the expectation that the US Federal Reserve was getting closer to lowering interest rates. Improving sentiment gave the precious metals markets momentum, causing silver to reach its quarterly high of US$25.62 on March 20, before continuing on to an 11 year high of US$29.26 on April 12.

Keep reading...Show less

Endeavour Silver Provides Q1 2024 Construction Progress Update on Terronera; Construction Progress Reaches 53% Completion

Endeavour Silver Corp. ("Endeavour" or the "Company") (NYSE: EXK; TSX: EDR) is pleased to provide a Q1 2024 construction progress update for its Terronera Project in Jalisco state, Mexico. A photo gallery presentation accompanies this news release and can be found here or on the Company website at Terronera Project Progress Photos . All dollar ($) references in this news release are United States dollars.

The Terronera project made significant progress in the first quarter, as concrete work was nearly complete on the Upper Plant Platform and erection of structural steel advanced for areas including crushing, coarse-ore storage, grinding, flotation, and thickening. Mechanical installation of major equipment continued to advance on schedule and the project remains on track for commissioning in Q4 2024.

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
Galena Mining

Galena Mining Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

Latest Press Releases

Related News

×