Galena Mining

Activities and Cashflow Report For Quarter Ended 31 December 2022

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) reports on its activities for the quarter ended 31 December 2022 (the “Quarter”), primarily focused on construction of its 60%- owned Abra Base Metals Mine (“Abra” or the “Project”) located in the Gascoyne region of Western Australia.


HIGHLIGHTS:

  • Abra Project construction completed on time in December 2022. Project construction expenditure within 1% of budget.
  • Ore commissioning commenced and first concentrate produced in January 2023.
  • Focus now on completing plant commissioning and ramping up production.
  • Underground development achieved a record 1,122m advance during the Quarter with the decline reaching 1,268mRL. (282m vertical below the surface and 45m below top of the orebody).
  • Cash balance at Quarter-end A$41.0M.
ABRA BASE METALS MINE (60%-OWNED)

Abra comprises a granted Mining Lease, M52/0776 and surrounding Exploration Licence E52/1455, together with several co-located General Purpose and Miscellaneous Leases. The Project is 100% owned by Abra Mining Pty Limited (“AMPL” the Abra Project joint-venture entity), which in turn is 60% owned by Galena, with the remainder owned by Toho Zinc Co., Ltd. (“Toho”) of Japan.

Abra is fully permitted, and construction of the processing plant and surface infrastructure was completed in December 2022. First production of its lead-silver concentrate occurred in January 2023 with first product shipment scheduled for the March 2023 quarter.

Project construction / development

Abra Project construction works were completed by the end of the Quarter and ore commissioning commenced with first ore feed into the plant and first concentrate produced as part of the plant commissioning process in early January 2023 (see Galena ASX announcements of 10 January 2023 and 13 January 2023). Abra construction completed within 1% of forecast construction costs.

Operational Readiness

By the end of the quarter 90% of the operational staff have been employed along with both internal and external maintenance service providers. All site critical spares have been identified and procured. Site reagents and other consumables have been established.

Underground power, ventilation, and the installation of the second egress (ladderways) have enabled multiple ore headings to be operational and the primary pumping station will be completed in the March quarter.

The site assay laboratory was nearing completion by the end of the quarter and final commissioning in January is expected to significantly improve assay turn around and controls.

Applications are being lodged for regulatory approvals, licences or permits as they are required for completion of construction, commissioning and commencement of operations.

Underground mining – During the Quarter, 1,122 metres of development was completed and at Quarter-end total development reached 3,592 metres consisting of 1,978 metres of decline development and 1,614 metres of lateral development. The decline reached 1,268mRL, 45 metres below the top of the Abra orebody and 282 metres vertically below the surface.

During December, several ore drives commenced on the 1,280 and 1,300mRL levels which will deliver the required ore for plant commissioning in January 2023. At the end of the Quarter, a total of 26,000t of ore had been stockpiled on the ROM pad in preparation for ore processing commissioning and the commencement of concentrate production.

During the quarter a total of 75 (10,777m) underground diamond holes were completed for grade control and mine planning purposes. Mine planning and scheduling work was completed with this information in preparation for the production activities in 2023.

On 24 December 2022, the primary ventilation fan motor failed, and alternative ventilation fans were installed to resume underground work. Five days of mining activities were lost during this time and this delay is not expected to delay the plant processing commissioning during January 2023.


Click here for the full ASX Release

This article includes content from Galena Mining, licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.


G1A:AU
Galena Mining

Galena Mining Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

The Conversation (0)
Galena Mining (ASX:G1A)

Galena Mining


Keep reading...Show less
Galena Mining

Abra Construction At 97% Complete – First Ore Stockpiled For January Processing

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 97% complete as of 30 November 2022. Processing plant commissioning is progressing quickly with practical completion now expected in December 2022. Ore currently being mined from underground is being stockpiled in readiness for processing to begin in January 2023. Concentrate production will commence January 2023.

Keep reading...Show less
Galena Mining

Abra Construction At 92% Complete – Reaches First Ore Underground

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 92% complete as of 31 October 2022. Underground mine has reached the first ore (see ASX announcement 14 November 2022) and plant commissioning continues in several key areas with the project focussed on achieving first concentrate production in Q1 2023.
Keep reading...Show less
Galena Mining

Abra Mine Reaches Ore

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the underground development at its Abra Base Metals Mine (“Abra” or the “Project”) has reached the Abra orebody. Commissioning has commenced in several key areas of the processing facility and the Power Station (Pacific Energy) completed full integration of the hybrid gas/solar/battery energy storage system (BESS) power station on 10 November. The project remains on track for first concentrate production in Q1 2023.
Keep reading...Show less
Galena Mining

Galena Mining Activities Report For Quarter Ended 30 September 2022

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) reports on its activities for the quarter ended 30 September 2022 (the “Quarter”), primarily focused on construction of its 60%- owned Abra Base Metals Mine (“Abra” or the “Project”) located in the Gascoyne region of Western Australia.

Keep reading...Show less
  Unico Silver Limited

Cerro Leon drill results

Further high-grade mineralisation identified at the Karina prospect

Unico Silver Limited (“USL” or the “Company”) is pleased to announce first assay results from ongoing drilling at the Cerro Leon project, located in the Santa Cruz province of Argentina.

Keep reading...Show less

First Majestic Announces Mailing of Materials for Special Meeting

First Majestic Silver Corp. (NYSE: AG) (TSX: AG) (FSE: FMV) (the "Company" or "First Majestic") is pleased to announce that it has commenced mailing of its meeting materials for the special meeting of the Company's shareholders (the "Special Meeting") that will be held on Tuesday, January 14, 2025 at 11:00 a.m. (Pacific Time) at the offices of Bennett Jones LLP, located at Suite 2500 - 666 Burrard Street, Vancouver, British Columbia V6C 2X8.

At the Special Meeting, pursuant to the requirements of the rules of the Toronto Stock Exchange and the New York Stock Exchange, First Majestic shareholders will be asked to approve an ordinary resolution (the "Share Issuance Resolution") approving the issuance of up to 190,000,000 common shares of First Majestic ("First Majestic Shares") to stockholders of Gatos Silver, Inc. ("Gatos") in connection with the previously announced acquisition by First Majestic of all of the shares of common stock of Gatos (the "Transaction"). First Majestic's Board of Directors unanimously recommends that the Company's shareholders vote FOR the Share Issuance Resolution.

News Provided by Newsfile via QuoteMedia

Keep reading...Show less

Pan American Silver Provides Annual Exploration Update

Pan American Silver Corp. (NYSE: PAAS) (TSX: PAAS) ("Pan American" or the "Company") provides an annual exploration update and releases new exploration drill results for its Jacobina, El Peñon, La Colorada, Huaron, Minera Florida and Timmins mines, as well as its La Colorada Skarn project.

"The success of our exploration program highlights the potential for long-term organic growth at many of our assets," said Christopher Emerson, Vice President of Exploration and Geology at Pan American. "Based on the results we were achieving in exploration this year, we increased our drill budget to over 450,000 metres for 2024. This exploration update highlights these results, and showcases the ongoing discovery of new mineralized structures in and around our existing mining operations."

News Provided by Business Wire via QuoteMedia

Keep reading...Show less
Boab Metals

Boab Metals Limited (ASX: BML) – Trading Halt

Boab Metals Limited (ASX:BML) (the “Company”) hereby requests a trading halt of its securities be granted by the ASX effective immediately, pending a release of an announcement regarding an Offtake and Project Finance Agreement. The trading halt will last until the earlier of commencement of trading on Wednesday, 11 December 2024 or the release to the market of an announcement as specified above. The Company is not aware of any reason why the trading halt should not be granted or of any other information necessary to inform the market about the trading halt. This request was authorised for release by the Board of the Company.

Keep reading...Show less

First Majestic Announces Effectiveness of Registration Statement on Form F-4 and Record & Meeting Dates of Special Meeting for Gatos Silver Acquisition

First Majestic Silver Corp. (NYSE: AG) (TSX: AG) (FSE: FMV) (the "Company" or "First Majestic") is pleased to announce that the Registration Statement on Form F-4 (the "F-4") filed by the Company with the United States Securities and Exchange Commission (the "SEC") in connection with the Company's previously announced acquisition of Gatos Silver, Inc. ("Gatos") (the "Transaction") has become effective under the U.S. Securities Act of 1933. The effectiveness of the F-4 is a condition to closing of the Transaction.

The Company is also pleased to announce that it has set the date of the special meeting of First Majestic shareholders (the "Special Meeting") to approve the issuance of First Majestic common shares to Gatos stockholders in connection with the Transaction. The details of the First Majestic Special Meeting are as follows:

News Provided by Newsfile via QuoteMedia

Keep reading...Show less
Galena Mining

Galena Mining Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

Latest Press Releases

Related News

×