Bravada Reports 38% IRR and US$46.1 Million After-Tax NPV@5% for Phase I PEA at Wind Mountain Au/Ag Project, Nevada; Additional Leach-Pad Site Being Evaluated for Phase II

Bravada Reports 38% IRR and US$46.1 Million After-Tax NPV@5% for Phase I PEA at Wind Mountain Au/Ag Project, Nevada; Additional Leach-Pad Site Being Evaluated for Phase II

Highlights

  • The Phase I PEA includes a 30.3million ton capacity leach pad, roughly 62% of the updated, Pit-constrained Resource tons, taking advantage of a leach-pad site adjacent to the modeled open pit.
  • A potential Phase II pad site directly north of Phase I is being evaluated to include additional Pit-constrained Resource as well as adjacent, under-drilled outcropping mineralization at North Hill.
  • The PEA and Pit-constrained Resource were modeled with 3-year, trailing average prices of US$1,750 for gold and $21 for silver.
  • The Pit-constrained Resource consists of:
    • 46million tons at 0.010 oz Au per ton and 0.26 oz Ag per ton containing 474,000ounces of Au and 11,807,000ounces of Ag in the Indicated Category; and
    • 2.6million tons at 0.008 oz per ton Au and 0.19 oz Ag per ton containing 21,900ounces of Au and 497,000ounces of Ag in the Inferred Category.
  • The Phase I PEA consists of 96% of the gold ounces in the Indicated ResourceCategory, acceptable for Pre-feasibility study.
  • Compared to the Company's independent 2012 Resource/PEA study, the Phase I PEA considers only a portion of the pit-constrained Resource that will fit onto a restricted area available as a close-in heap-leach pad site; 30.3million tons (31% less than the 2012 model, which utilized a pad space located much farther from the mine) and produces 227,000 ounces of Au-eq (29% less than the 2012 model pit).
  • Even with fewer tons being mined, Initial Capital increased by 3% to $46MM, with most of the Sustaining Capital in year 3.
  • The strip ratio was reduced by 23% to 0.55:1 waste to ore and the payback period was reduced 15% to 1.9 years in the current Phase I study.
  • Higher grades predicted and then verified by 2021 drilling resulted in better grades in early years and conversion of certain Inferred blocks into Indicated blocks, improving economics.
  • The strip ratio may be reduced further with additional test work as 1.1million tons of historic "waste rock" that must be removed in Phase I can be removed and stored on a low-grade stockpile. The material is currently not considered part of the Resource but limited sampling and drilling suggest it may contain recoverable gold, which may be processed on the Phase I heap pad.
  • The economics of the Phase I PEA have improved significantly compared to the 2012 PEA despite higher costs for capital and many operating costs. The AFTER-TAX IRR is 38% (an 81% improvement over the 2012 IRR of 21%) and the AFTER-TAX NPV @5% discount is $46.1million (a 74% improvement over the earlier NPV @5% of $26.5MM).

Bravada Gold Corporation (TSXV: BVA) (the "Company" or "Bravada") reports the results of an updated, independent Resource and Phase I Preliminary Economic Assessment (PEA) for its Wind Mountain GoldSilver Property in Washoe County, Nevada.

Economics have improved significantly compared to the Company's 2012 study due to utilizing a near-mine, heap-leach pad site for a portion of the Pit-constrained resource and higher grades for early mining, which were predicted and then verified by drilling during 2021. To add additional mine life, a Phase II pad site has been identified due north of the Phase I site, and although somewhat farther from the currently identified Pit-constrained resource, it is located very close to outcropping mineralization at the North End target area, which has only been tested with minor drilling. Other potential additions to mine life that the Phase I PEA did not consider include mineralization at the South End deposit and historic "waste rock piles" where the Company has identified potentially recoverable gold and silver.

Total Pit-constrained Resource

After verifying and slightly modifying the Wind Mountain 2012 Global Resource based on subsequent drilling, which was confirmed to within

2022 - Constrained in $1750 Gold Price Optimized Pit
Indicated
Cutoff     
oz
Au/ton
Tonsoz
Au/T
oz
Ag/T
oz Auoz Ag
variable        45,583,0000.0100.26        474,000        11,807,000
Inferred
Cutoff     
oz
Au/ton
Tonsoz
Au/T
oz
Ag/T
oz Auoz Ag
variable          2,604,0000.0080.19           21,900             497,000

 

Notes:

  • The Effective Date of the Wind Mountain mineral resources is October 4, 2022.
  • The estimate of mineral resources was done by RESPEC in Imperial tons.
  • Mineral Resources comprised all model blocks at a 0.006oz Au/ton cut-off for Oxide within an optimized pit and 0.014oz Au/ton for Mixed and Unoxidized within an optimized pit.
  • The project mineral resources are block-diluted Mineral Resources potentially amenable to open pit mining methods and reported within optimized pits using a gold price of US$1,750/oz, a silver price of US$21/oz and a throughput rate of 20,000 tonnes/day. Assumed metallurgical recoveries for gold are 62% for oxide, 20% for mixed and 15% for unoxidized. Assumed metallurgical recoveries for silver are 15% for oxide and 0% for mixed and unoxidized., Mining costs of US$2.75/tonne mined, heap leach processing costs of US$3.17/tonne processed, general and administrative costs of $0.57/tonne processed. Gold and silver commodity prices were selected based on analysis of the three-year running average.
  • Material in waste dumps and heap leach pads are NOT included in the current model and resource.
  • Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.
  • The estimate of mineral resources may be materially affected by geology, environmental, permitting, legal, title, taxation, sociopolitical, marketing, or other relevant issues.
  • Rounding may result in apparent discrepancies between tonnes, grade, and contained metal content.

Phase I PEA for a Close-in Heap-leach Site

The Phase I PEA assumes open-pit, contract mining with conventional trucks and shovels and run-of-mine leaching. The base-case economic model(1) is summarized below in US dollars and Imperial units (some values rounded):

Resource inside the pits for Phase I PEA = 29.2 million tons of Indicated Resource @ 0.011 oz Au/t & 0.267 oz Ag/t and 1.08 million tons of Inferred Resource at 0.009 oz Au/t and 0.173 oz Ag/t, both at a cut-off grade of 0.008 oz Au/t. Oxide mineralization = 30.2 million tons and Mixed oxide/sulfide = 0.01 million tons.
Gold & Silver Ounces mined = 344,000 oz Au and 7,975,000 oz Ag.
Gold & Silver Ounces produced = 213,000 oz Au (recovery 61.9%) & 1,194,000 oz Ag (recovery 15%) or 227,000 oz Au-eq(2).
Waste: Ore Strip ratio = 0.55:1
Capital = Initial capital of $46.6 million with $19.8 million sustaining capital
Mine Life = approximately 4.2 years of mining
After-tax Payback Period = 1.8 years
Life-of-mine cash cost(3) = $1,045 per ounce Au
All-in Sustaining Costs = $1,175 per ounce Au
After-tax IRR = 38%
After-tax NVP@5% = $46.1 million

(1) Canadian NI 43-101 guidelines define a PEA as follows: "A preliminary economic assessment is preliminary in nature and it includes inferred mineral resources that are considered too speculative geologically to have the economic considerations applied that would enable them to be classified as mineral reserves, and there is no certainty that the preliminary assessment will be realized. Mineral resources that are not mineral reserves do not have demonstrated economic viability."

(2)Expected recoveries were incorporated to convert silver to gold equivalent (Au-eq) at 345 Ag:1 Au ($1,750 x 61.9% divided by ($21 x 15%))

(3)Costs include estimated Nevada Net Proceeds taxes, property taxes, estimated corporate income tax, and treats silver as a by-product credit.

Sensitivity studies by RESPEC are presented in the table below. RESPEC notes that additional studies such as further metallurgical studies to evaluate crushing higher-grade portions of the deposit and grid drilling to delineate economic portions of the previously mined "waste rock", which are given no value in the current model, could further enhance the economics. For example, RESPEC notes that 1.1million tons of historic mine waste is currently classified as "waste" and must be removed during Phase I mining; however, results of limited drilling, surface sampling, and trenching by Bravada suggest the material contains potentially recoverable gold. RESPEC and Woods recommends that the material be placed in a stockpile for additional study or utilized as over liner on the leach pads; the material potentially would be added to the currently designed Phase I pad to further reduce the strip ratio and increase positive economics.

  Metal Price(Cash Flow and Net Present Value in US$000)
Au PriceAg PriceUndiscounted CFNPV @ 5%NPV @ 8%NPV @ 10%IRR
 $   1,600 $        19.20 $               35,490 $         23,426 $           17,656 $        14,30222%
 $   1,650 $        19.80 $               44,419 $         30,968 $           24,509 $        20,74428%
 $   1,700 $        20.40 $               53,433 $         38,576 $           31,417 $        27,23733%
 $   1,750 $        21.00 $               62,322 $         46,077 $          38,229 $        33,63838%
 $   1,800 $        21.60 $               70,801 $         53,239 $           44,736 $        39,75543%
 $   1,850 $        22.20 $               79,280 $         60,399 $           51,242 $        45,87148%
 $   1,900 $        22.80 $               87,855 $         67,641 $           57,822 $        52,05753%
       
  Revenue    
  Undiscounted CFNPV @ 5%NPV @ 8%NPV @ 10%IRR
 70% $               62,322 $         46,077 $           38,229 $        33,63838%
 80% $               62,322 $         46,077 $           38,229 $        33,63838%
 90% $               62,322 $         46,077 $           38,229 $        33,63838%
 100% $               62,322 $         46,077 $          38,229 $        33,63838%
 110% $               62,322 $         46,077 $           38,229 $        33,63838%
 120% $               62,322 $         46,077 $           38,229 $        33,63838%
 130% $               62,322 $         46,077 $           38,229 $        33,63838%
       
  Operating Cost    
  Undiscounted CFNPV @ 5%NPV @ 8%NPV @ 10%IRR
 70% $             123,722 $         98,006 $           85,454 $        78,06174%
 80% $             103,996 $         81,368 $           70,348 $        63,86663%
 90% $               83,401 $         63,942 $           54,496 $        48,95251%
 100% $               62,322 $         46,077 $          38,229 $        33,63838%
 110% $               40,221 $         27,371 $           21,211 $        17,62625%
 120% $               17,990 $           8,559 $             4,098 $           1,52511%
 130% $               (4,240) $       (10,254) $         (13,015) $       (14,575)-3%
       
  Capital Cost    
  Undiscounted CFNPV @ 5%NPV @ 8%NPV @ 10%IRR
 70% $               81,761 $         64,349 $           55,849 $        50,84267%
 80% $               75,281 $         58,258 $           49,976 $        45,10755%
 90% $               68,801 $         52,168 $           44,102 $        39,37346%
 100% $               62,322 $         46,077$          38,229 $        33,63838%
 110% $               55,593 $         39,782 $           32,173 $        27,73331%
 120% $               48,736 $         33,380 $           26,022 $        21,74126%
 130% $               41,878 $         26,979 $           19,872 $        15,74821%

President Joe Kizis commented, "We have taken a phased approach to development at Wind Mountain. Phase I takes advantage of a pad space adjacent to the modelled mining operation. The increased grade verified in the Breeze pit area by drilling during 2021 provides increased cash flow during the early years of production, providing the benefit that cash flow should fund sustaining capital required in year 3. The 2022 Pit-constrained resource would be depleted by about 62% during Phase I and a probable Phase II pad site has been identified north of the Phase I pad. Capital costs to activate Phase II should be reasonable and potentially funded by cash flow. There are several fault blocks of outcropping mineralization based on surface sampling uphill from the Phase II pad that have not been tested by drilling except for results from several encouraging shallow drill holes at North Hill. Although the North Hill targets are not expected to contain a large number of ounces, they would be very inexpensive to mine due to being at or near surface and to transport to an adjacent Phase II pad.

We focused on the Phase I area first because it contains better-than-average grades in the early years of the mine plan and has been drill tested to mostly oxidized Indicated categories, so it could be potentially quickly upgraded to Reserve Category with a Pre-feasibility study. Operational advantages for development of Wind Mountain include its location in a sparsely populated region of northwestern Nevada (less than a 2-hour drive from Reno), county-maintained roads, power lines to the property, location six miles from a geothermal power station, and no known environmental or archaeological impediments."

RESPEC, Woods Process Services, and Debra Struhsacker, Bravada's Environmental Permitting and Government Relations Consultant, compiled the technical report. Thomas Dyer, P.E. is a Principal Engineer for RESPEC and is responsible for sections of the technical report involving mine designs and the economic evaluation; Michael Lindholm, C.P.G., is a Principal Geologist for RESPEC, and is responsible for the sections involving the Mineral Resource estimate; Jeffery Woods, SME MMSA QP, is an independent Principal Consulting Metallurgist with Woods Process Services and is responsible for the sections on process 13, 17 and 21. The PEA relies on Debra Struhsacker as an expert in permitting. Thomas Dyer, Michael Lindholm and Jeffery Woods are the Qualified Persons of the technical report for the purpose of Canadian NI 43-101, Standards of Disclosure for Economic Analyses of Mineral Projects.

A Technical Report covering both the Phase I PEA and the updated Pit-constrained Resource will be filed with SEDAR within 45 days, as per NI-43-101 regulations.

About Wind Mountain

The past-producing Wind Mountain gold/silver project is located approximately 160km northeast of Reno, Nevada in a sparsely populated region with excellent logistics, including county-maintained road access and a power line to the property. AMAX Gold/Kinross Gold recovered nearly 300,000 ounces of gold and over 1,700,000 ounces of silver between 1989 and 1999 from two small open pits and a heap-leach operation (reported data based on Kinross Gold files). Rio Fortuna Exploration (U.S.) Inc., a wholly owned US subsidiary of Bravada Gold Corporation, acquired 100% of the property through an earn-in agreement with Agnico-Eagle (USA) Limited, a subsidiary of Agnico-Eagle Mines Limited, which retains a 2% NSR royalty interest, of which 1% may be purchased for $1,000,000 at any time prior to commencement of production (purchase to reduce royalty is assumed in PEA calculations). The resource and PEA for Wind Mountain were updated in April 2012 and further updated in November 2022.

About Bravada

Bravada is an exploration company with a portfolio of high-quality properties in Nevada, one of the best mining jurisdictions in the World. Bravada has successfully identified and advanced properties with the potential to host high-margin deposits while successfully attracting partners to fund later stages of project development. Bravada's value is underpinned by a substantial gold and silver resource with a positive PEA at Wind Mountain, and the Company has significant upside potential from possible new discoveries at its exploration properties.

Since 2005, the Company entered into 32 earn-in joint-venture agreements for its properties with 19 publicly traded companies, as well as a similar number of property-acquisition agreements with private individuals. Bravada currently has 10 projects in its portfolio, consisting of 810 claims for approximately 6,500 ha in the Battle Mountain/Eureka and Walker Lane Trends, two of Nevada's most prolific gold trends. Most of the projects host encouraging drill intercepts of gold and already have drill targets developed. Several videos are available on the Company's website that describe Bravada's major properties, responding to investor's commonly asked questions. Simply click on this link https://bravadagold.com/projects/project-videos/.

Joseph Anthony Kizis, Jr. (AIPG CPG-11513) is the qualified person for the Company and is responsible for reviewing and preparing the technical data presented in this release and has approved its disclosure.

-30-

On behalf of the Board of Directors of Bravada Gold Corporation

"Joseph A. Kizis, Jr."

Joseph A. Kizis, Jr., Director, President, Bravada Gold Corporation

For further information, please visit Bravada Gold Corporation's website at bravadagold.com or contact the Company at 604.684.9384 or 775.746.3780.

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

This news release may contain forward-looking statements including but not limited to comments regarding the timing and content of upcoming work programs, geological interpretations, receipt of property titles, potential mineral recovery processes, etc. Forward-looking statements address future events and conditions and therefore involve inherent risks and uncertainties. Actual results may differ materially from those currently anticipated in such statements. These statements are based on a number of assumptions, including, but not limited to, assumptions regarding general economic conditions, interest rates, commodity markets, regulatory and governmental approvals for the company's projects, and the availability of financing for the company's development projects on reasonable terms. Factors that could cause actual results to differ materially from those in forward looking statements include market prices, exploitation and exploration successes, the timing and receipt of government and regulatory approvals, and continued availability of capital and financing and general economic, market or business conditions. Bravada Gold Corporation does not assume any obligation to update or revise its forward-looking statements, whether as a result of new information, future events or otherwise, except to the extent required by applicable law.

To view the source version of this press release, please visit https://www.newsfilecorp.com/release/147331

News Provided by Newsfile via QuoteMedia

BVA:CA
The Conversation (0)
Bravada Gold Announces the Extension of the Expiry Date of Certain Common Share Purchase Warrants

Bravada Gold Announces the Extension of the Expiry Date of Certain Common Share Purchase Warrants

Bravada Gold Corporation (TSXV: BVA) (the "Company" or "Bravada") announces that it intends to apply to the TSX Venture Exchange ("TSXV") for approval to extend the original expiry dates of an aggregate 27,611,285 share purchase warrants (the "Warrants") as follows:

Number of WarrantsExercise Price per ShareClosing Date of Private PlacementOriginal Expiry DateProposed Amended Expiry Date
7,555,000$0.12May 13, 2019May 13, 2023May 13, 2024
4,552,142$0.12July 17, 2019July 17, 2023July 17, 2024
8,305,000$0.15June 11, 2020June 11, 2023June 11, 2024
4,260,000$0.12August 6, 2021August 6, 2023August 6, 2024
2,757,143$0.12October 1, 2021October 1, 2023October 1, 2024
182,000$0.12October 25, 2021October 25, 2023October 25, 2024

 

News Provided by Newsfile via QuoteMedia

Keep reading...Show less
Bravada Announces a Phase II Pad Site Sufficient to Process the Remaining 2022 In-Pit Gold/Silver Resource, Potentially Adding to Wind Mountain's Mine Life

Bravada Announces a Phase II Pad Site Sufficient to Process the Remaining 2022 In-Pit Gold/Silver Resource, Potentially Adding to Wind Mountain's Mine Life

Bravada Gold Corporation (TSXV: BVA) (OTCQB: BGAVF) (FSE: BRTN) (the "Company" or "Bravada") reports that it has received the results of an evaluation of a second pad site, not considered in its recent technical report (the "Report", see news release dated January 23, 2023). The Report may be found under the Company's profile at www.sedar.com and on Bravada's website https:bravadagold.com.

Economics reported in the Report improved significantly compared to the Company's 2012 PEA due to utilizing a near-mine, heap-leach Pad I site, which is of limited size, for a portion of the Pit-constrained resource and due to higher grades for early mining, which were predicted and then verified by drilling during 2021. To add additional mine life, a Phase II pad site was identified due north of the Phase I site (see Figure 1) but was not considered in the January 20th PEA. An internal evaluation by RESPEC demonstrates that the Pad II site is sufficient in size to process the remainder of the In-pit Resource, adding approximately 45% more resource tons and potentially increasing mine life by more than 2 years. Although Pad II is somewhat farther from the currently identified Pit-constrained resource than the Pad I site, it is located very close to outcropping mineralization at the North Hill target, which has only been tested with minor drilling. Other potential additions to mine life that the Phase I PEA did not consider, but which might be added to a Phase II or later Pad, include mineralization at the South End target, historic "waste rock piles" and partially spent heaps where the Company has identified potentially recoverable gold and silver.

News Provided by Newsfile via QuoteMedia

Keep reading...Show less
Bravada Files Technical Report for the Wind Mountain Au/Ag Project, Nevada, Including Phase I PEA Results of 38% IRR and US$46.1 Million After-Tax NPV@5%

Bravada Files Technical Report for the Wind Mountain Au/Ag Project, Nevada, Including Phase I PEA Results of 38% IRR and US$46.1 Million After-Tax NPV@5%

Bravada Gold Corporation (TSXV: BVA) (OTCQB: BGAVF) (FSE: BRTN) (the "Company" or "Bravada") reports today that it has filed a technical report (the "Report") prepared in accordance with Canadian Securities Administrators' National Instrument 43-101 ("NI 43-101"). The Report may be found under the Company's profile at www.sedar.com and on Bravada's website https:bravadagold.com.

The Report dated January 20, 2023 and entitled "Updated Technical Report and Preliminary Economic Assessment, Wind Mountain Gold-Silver Project", located in Washoe County, Nevada, was prepared by RESPEC Company LLC ("RESPEC", formerly Mine Development Associates), Woods Process Services, and Debra Struhsacker, Bravada's Environmental Permitting and Government Relations Consultant.

News Provided by Newsfile via QuoteMedia

Keep reading...Show less
Bravada Reports Results of Recent Drilling and Status of Updated PEA at Wind Mountain Au/Ag Project, Nevada

Bravada Reports Results of Recent Drilling and Status of Updated PEA at Wind Mountain Au/Ag Project, Nevada

Bravada Gold Corporation (TSXV: BVA) (FSE: BRTN) (OTCQB: BGAVF) (the "Company" or "Bravada") has received assay results for the three deep reverse-circulation holes drilled during 2022. The holes tested below a banded vein zone discovered in Q4 2020 beneath mine waste and other overburden at the Feeder target, located approximately 450m south of the Wind Open Pit and where hole WM20-102 intersected 1.5 metres of 269.0gt Ag and 0.404gt Au within a thicker interval of banded quartz veining with anomalous gold and silver. The three 2022 holes intersected zones of low-grade disseminated gold and silver within the Truckee Formation, which is the host for the current resource of disseminated oxide gold north of the Feeder target. However, the banded quartz vein zone did not persist to the depths tested. Below disseminated mineralization in the Truckee Formation, however, many vein zones were encountered in the holes which are enriched in manganese, barium, tungsten, nickel, and zinc.

News Provided by Newsfile via QuoteMedia

Keep reading...Show less
Bravada Announces the Extension of the Expiry Date of Certain Common Share Purchase Warrants and Updates Wind Mountain Program

Bravada Announces the Extension of the Expiry Date of Certain Common Share Purchase Warrants and Updates Wind Mountain Program

Bravada Gold Corporation (TSXV: BVA) (FSE: BRTN) (OTCQB: BGAVF) (the "Company" or "Bravada") reports that the Company will be extending the exercise period of a total of 6,434,000 share purchase warrants, all of which are exercisable at $0.12 per share (collectively, the "Warrants"). The Warrants were issued on July 23, 2018, pursuant to a private placement (see news release NR-07-18) and are scheduled to expire on July 23, 2022. The Company proposes to extend the expiry by one (1) year, and accordingly, the new expiry date for the warrants will be July 23, 2023.

All other terms and conditions of the Warrants remain unchanged. The Warrant extension is subject to acceptance by the TSX Venture Exchange.

News Provided by Newsfile via QuoteMedia

Keep reading...Show less
Grande Portage Announces Non-Brokered Private Placement Pursuant to the Listed Issuer Financing Exemption

Grande Portage Announces Non-Brokered Private Placement Pursuant to the Listed Issuer Financing Exemption

Not for distribution to United States newswire services or for dissemination in the United States.

Grande Portage Resources Ltd. (TSXV:GPG)(OTCQB:GPTRF)(FSE:GPB) ("Grande Portage" or the "Company") is pleased to announce a non-brokered private placement of up to 10,000,000 units (each, a "Unit") at a price of C$0.30 per Unit for aggregate gross proceeds of up to C$3,000,000 (the "Offering"). The Offering is being carried out pursuant to Part 5A of National Instrument 45-106 - Prospectus Exemptions (the "LIFE Exemption") to purchasers resident in Canada, and in jurisdictions outside of Canada in compliance with the applicable securities laws of those jurisdictions. The Company has an offering document (the "Offering Document") related to the Offering that can be accessed under Grande Portage's profile at www.sedarplus.ca and on the Company's website at https:grandeportage.com. Prospective investors should read the Offering Document before making an investment decision

News Provided by ACCESSWIRE via QuoteMedia

Keep reading...Show less
Element79 Gold Corp to Update Investors on the Emerging Growth Conference on October 31, 2024

Element79 Gold Corp to Update Investors on the Emerging Growth Conference on October 31, 2024

(TheNewswire)

Element79 Gold Corp.

Element79 Gold Corp invites individual and institutional investors as well as advisors and analysts, to attend its real-time, interactive presentation on the Emerging Growth Conference.

News Provided by TheNewsWire via QuoteMedia

Keep reading...Show less
Presenting on the Emerging Growth Conference 76 Day 1 on October 30 Register Now

Presenting on the Emerging Growth Conference 76 Day 1 on October 30 Register Now

EmergingGrowth.com a leading independent small cap media portal announces the schedule of the 76 th Emerging Growth Conference on October 30 & 31, 2024.

The Emerging Growth Conference identifies companies in a wide range of growth sectors, with strong management teams, innovative products & services, focused strategy, execution, and the overall potential for long-term growth.

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
Pinnacle Signs Letter of Intent for Option to Acquire High-Grade Gold-Silver Project in Sierra Madre Trend of Mexico.

Pinnacle Signs Letter of Intent for Option to Acquire High-Grade Gold-Silver Project in Sierra Madre Trend of Mexico.

(TheNewswire)

Pinnacle Silver and Gold Corp.

Highlights:

News Provided by TheNewsWire via QuoteMedia

Keep reading...Show less
Pinnacle Signs Letter of Intent for Option to Acquire High-Grade Gold-Silver Project in Sierra Madre Trend of Mexico

Pinnacle Signs Letter of Intent for Option to Acquire High-Grade Gold-Silver Project in Sierra Madre Trend of Mexico

(TheNewswire)

Pinnacle Silver and Gold Corp.

Highlights:

News Provided by TheNewsWire via QuoteMedia

Keep reading...Show less
Lode Gold Submits Application for Exchange Approval to Form Spin Co, Gold Orogen - a Yukon  & New Brunswick Exploration Company

Lode Gold Submits Application for Exchange Approval to Form Spin Co, Gold Orogen - a Yukon & New Brunswick Exploration Company

Lode Gold Resources Inc. (TSXV: LOD) (OTCQB: SBMIF) ("Lode Gold " or the "Company") is pleased to announce that it has submitted application to the TSX Venture exchange for approval of the Spin-out of Gold Orogen, as described on its August 27, 2024 and October 22, 2024 news release. The details regarding the Lode Gold shareholder's meeting that is expected to be held in early December 2024 will follow with an information circular to be filed by early November 2024. Lode Gold will seek the approval from shareholders on the Plan of Arrangement, and upon Exchange approval, set the Record Date for distribution of the shares of the new company to shareholders of Lode Gold.

The Company also announces that pursuant to a director resolution passed on July 26, 2024, and a special resolution passed by shareholders of the Company on July 6, 2023, the Company has consolidated its capital on a ten for one (10:1) basis. Post-consolidation, the Company's capitalization composes of unlimited common shares with no par value, of which 38,032,970 shares are issued and outstanding.

Effective at the opening, Tuesday October 29, 2024, the common shares of Lode Gold Resources Inc. will commence trading on the TSX Venture Exchange on a consolidated basis. The Company is classified as a mining company.

Name of Company: No change.
Escrow shares: None
Transfer agent: Odyssey Trust Company.
Trading symbol: LOD (unchanged)
CUSIP number: 540196 20 1 (new)

"The Company has been contemplating share consolidation for sometime. With significant milestones achieved in the last 12 months and more upcoming catalysts, it makes strategic sense now to execute the consolidation. A key catalyst upcoming in a few months is share distribution of Gold Orogen to shareholders of Lode Gold, a significant step in unlocking value.

With a tight capital structure we can more effectively attract new investors. Of note, four shareholders hold over 60% shares of 38 million post-consolidated shares." states Wendy T. Chan, CEO and Director of Lode Gold.

About Lode Gold

Lode Gold (TSXV: LOD) is an exploration and development company with projects in highly prospective and safe mining jurisdictions in Canada and the United States.

Its Golden Culvert and WIN Projects in Yukon, covering 99.5 km2 across a 27-km strike length, are situated in a district-scale, high-grade-gold-mineralized trend within the southern portion of the Tombstone Gold Belt. Gold deposits and occurrences within the Belt include Fort Knox, Pogo, Brewery Creek and Dublin Gulch, and Snowline Gold. A NI 43-101 technical report entitled "Technical Report on the WIN-Golden Culvert Property for Lode Gold" with an effective date of May 15, 2024, summarizing the work to date on these properties is available on the Company's profile on SEDAR+ (www.sedarplus.ca) and on the Company's website (www.lode-gold.com).

In New Brunswick, Lode Gold has created one of the largest land packages with a 42km strike within 420km2. Its McIntyre Brook Project, New Brunswick, covering 111 km2 and a 17-km strike length in the emerging Appalachian/Iapetus Gold Belt, is surrounded by Puma Exploration's Williams Brook Project (5.55 g/t Au over 50m)1 and is hosted by orogenic rocks of similar age and structure as New Found Gold's Queensway Project. The Fancamp's Riley Brook is a 309 km2 package covering a 25 km strike of Wapske formation with its numerous felsic units. Previous exploration efforts have focused on just VMS-style mineralization hosted in the felsic intrusions, and mostly focused on the base metals - the Company is the first to focus on and assay for gold. This transaction will close upon Exchange's acceptance.

The Company is also advancing its Fremont Gold development project in the historic Mother Lode Gold Belt of California where 50,000,000 oz of gold has been produced. Fremont, located 500km north of Equinox Gold's Castle Mountain and Mesquite mines, has a Preliminary Economic Assessment(" PEA") with an after-tax NPV (5%) of USD $217M, a 21% IRR, 11-year LOM, averaging 118,000 Oz per annum at USD $1,750 gold. A sensitivity to the March 31, 2023, PEA at USD $2,000/oz gold gives an after-tax NPV (5%) of USD $370M and a 31% IRR over an 11-year LOM. The project hosts an NI 43-101 resource of 1.16 MOz at 1.90 g/t Au within 19.0 MT Indicated and 2.02 MOz at 2.22 g/t Au within 28.3 MT Inferred. The MRE evaluates only 1.4 km of the 4 km strike length of the Fremont property which features five gold-mineralized zones. Significantly, three step-out holes at depth hit the mineralized structure, typical of orogenic deposits that often occur at depth. Fremont is located on 3,351 acres of 100% owned private land in Mariposa, the original Gold Rush County, and is 1.5 hours from Fresno, California. The property has year-round road access and is close to airports and rail.

Please refer to the Fremont Gold project NI 43-101 PEA technical report dated March 31, 2023, which is available on the Company's profile on SEDAR+ (www.sedarplus.ca) and on the Company's website (www.lode-gold.com). The PEA technical report has been reviewed and approved by independent "Qualified Persons" Eugene Puritch, P.Eng., FEC, CET, and Andrew Bradfield, P.Eng. both of P&E, and Travis Manning, P.E. of KCA.

QUALIFIED PERSON STATEMENT

The scientific and technical information contained in this press release has been reviewed and approved by Jonathan Victor Hill, Director, BSc (Hons) (Economic Geology - UCT), FAusIMM, and who is a "qualified person" as defined by NI-43-101.

ON BEHALF OF THE COMPANY

Wendy T. Chan, CEO & Director

Information Contact

Winfield Ding
CFO
info@lode-gold.com
+1-416-320-4388

Kevin Shum
Investor Relations
kevin@lode-gold.com
+1 (647) 725-3888 ext. 702

Cautionary Note Related to this News Release and Figures

This news release contains information about adjacent properties on which the Company has no right to explore or mine. Readers are cautioned that mineral deposits on adjacent properties are not indicative of mineral deposits on the Company's properties.

Cautionary Statement Regarding Forward-Looking Information

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

All statements, trend analysis and other information contained in this press release about anticipated future events or results constitute forward-looking statements. Forward-looking statements are often, but not always, identified by the use of words such as "seek", "anticipate", "believe", "plan", "estimate", "expect" and "intend" and statements that an event or result "may", "will", "should", "could" or "might" occur or be achieved and other similar expressions. All statements, other than statements of historical fact, included herein, including, without limitation, statements regarding the anticipated use of proceeds from the Special Warrant financing, additional proceeds from the exercise of the warrants underlying the Special Warrants, and the receipt of final acceptance from the TSX Venture Exchange with respect to the transactions, are forward-looking statements. Although Lode Gold believes that the expectations reflected in such forward-looking statements and/or information are reasonable, undue reliance should not be placed on forward-looking statements since Lode Gold can give no assurance that such expectations will prove to be correct. These statements involve known and unknown risks, uncertainties and other factors that may cause actual results or events to differ materially from those anticipated in such forward-looking statements, including the risks, uncertainties and other factors identified in Lode Gold's periodic filings with Canadian securities regulators, and assumptions made with regard to: the ability of Lode Gold to obtain final acceptance from the TSX Venture Exchange with respect to the transactions; that the Company will be able to use the proceeds of the Special Warrant financing as anticipated; and the ability of the Company to continue with its stated business objectives and its ability to obtain required approvals and raise additional capital to proceed. Forward-looking statements are subject to business and economic risks and uncertainties and other factors that could cause actual results of operations to differ materially from those contained in the forward-looking statements. Important factors that could cause actual results to differ materially from expectations include risks associated with the business of Lode Gold and Fancamp; risks related to the Company's ability to obtain final acceptance from the TSX Venture Exchange with respect to the transactions; the risk that the use of proceeds from the Special Warrant financing may differ from management's expectations; and other risk factors as detailed from time to time and additional risks identified in the Companies' filings with Canadian securities regulators on SEDAR+ in Canada (available at www.sedarplus.ca). Forward-looking statements are based on estimates and opinions of management at the date the statements are made. The Company does not undertake any obligation to update forward-looking statements except as required by applicable securities laws. Investors should not place undue reliance on forward-looking statements.

News Provided by Newsfile via QuoteMedia

Keep reading...Show less

Latest Press Releases

Related News

×