Frontier Energy

Waroona Energy Commences DFS on Solar Power Facility

Frontier Energy Limited (ASX: FHE; OTCQB: FRHYF) (Frontier or the Company) advises that Waroona Energy Inc. (TSXV: WHE) (Waroona) has commenced a Definitive Feasibility Study (DFS) for a 120MWdc solar power generation facility.


Frontier has recently announced the signing of a Letter of Intent with Waroona to acquire all the Waroona shares (the Transaction) not currently held by Frontier (Frontier already holds ~20% of Waroona) via a Canadian Plan of Arrangement (Share Plan), equivalent to an Australian Scheme of Arrangement. Frontier and Waroona have in place a collaboration agreement regarding their respective strategies for renewable energy production in Western Australia.

HIGHLIGHTS

  • Waroona has engaged electricity and solar energy specialist Incite Energy to complete a DFS for a 120MWdc Solar Facility (“Stage One”)
    • While Frontier has already completed a DFS for a 114MW solar farm, Waroona’s ground is located closer to the nearby electricity terminal and Waroona had not previously completed a DFS
  • The Waroona DFS will finalise the detailed design including site layout, equipment specification and capital cost estimate (accurate to ±15%) for Stage One development
  • Leveraging the significant work already completed, the DFS will be completed in early 2024
    • The Project has all major permits, approvals and an executed Electricity Transfer Access Contract and Interconnection Works Contract to WA’s electricity network (SWIS) in place
    • Waroona’s Study of a green hydrogen-fuelled (dual fuel) peaking power plant is also progressing and remains on track for delivery during 4Q23
  • Electricity prices continue to trend higher, averaging A$90/MWh during the September quarter, a 25% YoY increase
    • Prices during the afternoon peak interval averaged over A$150/MWh, while midday low prices averaged around $50/MWh
Frontier Managing Director, Sam Lee Mohan, commented: “The development of a solar facility is a key pillar of the Company’s long-term strategy to build a renewable energy hub. This strategy includes solar production, green hydrogen production from solar energy, as well as green hydrogen consumption in a hydrogen-fuelled peaking power plant.

Given our existing collaboration agreement with Waroona, and the recently announced transaction that will combine the two companies, it makes logical sense to prepare for construction of the Stage One solar facility on a site that is located nearest the electricity terminal. As significant work has been completed on solar power generation already (including in Frontier’s DFS), Waroona’s solar DFS can be fast tracked and completed by early 2024.

The Company remains on track to meet its target to commence solar development during 1H2024.”

Waroona DFS for 120MWdc solar farm underway

Waroona has appointed electricity and solar energy specialist Incite Energy Pty Ltd (Incite) to complete a DFS for a 120MWdc Solar Facility (“Stage One”) at the Waroona Renewable Energy Project. The Company has an approved Declared Sent Out Capacity (DSOC) of 241MWdc from Western Power, of which Stage One will be targeting to deploy 120MWdc.

While Frontier had previously completed a DFS for a 114MWdc solar farm at the Bristol Springs Project (located on the purple shaded area in Figure 1 below), the Waroona Project is located closest to the electricity terminal (only 300m away – as shown in Figure 1 - teal shaded area) and is the most cost-effective location for Stage One of a combined development. Waroona had not previously completed a DFS.

Figure 1: Frontier and Waroona’s projects and nearby infrastructure in South-West WA

Incite was selected through a competitive tender process due to its expertise in the industry and its exceptional track record, including several operational utility-scale projects across Australia (ranging from 50MW - 300MW) and multiple utility-scale solar farms and load connections currently in early-stage development in Western Australia.

The Scope of work for the DFS includes:

1. Layout – considering clearing limitations, flood studies, road servitudes, drainage channel, and allocating areas for future Peaker Plant and hydrogen plant

2. Design

3. Equipment specification and supplier quotations

4. Update and refinement of geotechnical information

5. Construction and commissioning scope and costing

6. Interfacing with Western Power

Figure 2: Artist impression of the Solar facility and peaking plant on Waroona’s landholding

A DFS was preferred to appointing an EPC contractor to carry out an early works program as had been contemplated previously1. This decision was made as it more cost effective, both in the short and long term.

This approach allows the Company to consider a more flexible approach through the construction phase, as it allows for the Company to manage procurement of key equipment, including critical path long lead items, in-house. This would likely reduce the overall capital requirement whilst having no material impact on timing to Final investment Decision (FID). The Stage One DFS will be delivered in early 2024.


Click here for the full ASX Release

This article includes content from Frontier Energy, licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.

FHE:AU
The Conversation (0)
Bigtincan Holdings Limited

Vector Capital Proposal Determined to be Superior Proposal Matching Rights Process Triggered

Further to its announcements on 30 October 2024 and 12 November 2024, Bigtincan Holdings Limited (Bigtincan) (ASX:BTH) has received a revised proposal from Vector Capital Management, L.P. (Vector) to acquire BTH by way of scheme of arrangement for cash consideration of 22 cents per share, which will be reduced (1) on a per share basis to the extent that BTH’s transaction costs in connection with the IAAC Transaction, the Vector Proposal and the director nominations at the 2024 AGM exceed $4 million, and (2) by 0.7 cents per share if the break fee becomes payable under the IAAC SID (Vector Proposal). BTH shareholders will be informed in due course should any adjustment be triggered.

Keep reading...Show less
Streamplay Studio

Streamplay Studio Enters into Agreement to Acquire North American Indie Gaming Leader, Noodlecake Studios

Streamplay Studio Limited (“Streamplay” or the “Company”) (ASX: SP8), is pleased to announce that it has entered into a binding Share Sale Agreement (“SSA”) to acquire 100% of Noodlecake Studios Inc. (“Noodlecake”), a profitable North American indie gaming company headquartered in Canada, from its parent company Zplay (HK) Technology Co. Limited (“Zplay”). The addition of Noodlecake aligns with Streamplay’s strategic direction, including the recent appointment of Silicon Valley tech advisor Paolo Privitera (ASX: 8 October 2024) to the board of directors, strengthening the Company’s North American and global gaming footprint.

Keep reading...Show less
HighCom Limited

HighCom Limited Receives A$5.6m SUAS Spare Parts Order from Defence

HighCom Limited (ASX: HCL, ‘HighCom’, ‘Group’) is pleased to announce that it has received a new spare parts order for A$5.6m (including GST) from the Commonwealth of Australia’s Department of Defence, as part of the Small Uncrewed Aerial Systems (SUAS) Support Contract. The order will be completed during H2 FY2025.

Keep reading...Show less
Opyl

Opyl Signs New Service Agreement with Commercial Eyes

Opyl Limited (ASX: OPL) a leader in clinical trial design and biostatistical validation, is pleased to announce the signing of a service agreement with Commercial Eyes Pty Ltd, a ProductLife Group company and prominent Australian pharmaceutical and medical device commercialisation company.

Keep reading...Show less
  FBR Limited

Next-generation Hadrian X® Completes US Site Acceptance Testing

Robotic technology company FBR Limited (ASX: FBR; OTCQB: FBRKF) (‘FBR’ or ‘the Company’) is pleased to announce that it has received confirmation from CRH Ventures that the first next-generation Hadrian X® has successfully met their requirements and has completed Site Acceptance Testing at the Fort Myers facility in Florida, United States.

Keep reading...Show less

Latest Press Releases

Related News

×