Galena Mining

Positive Operating Cash Flows Achieved For September Quarter

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) advises that the Abra mine has generated positive operating cash flows for the quarter ended 30 September 2023 (the “Quarter”) and has achieved new quarter production highs as the mine continues to ramp-up. Subject to September end of month reconciliation the following key operation highlights and significant milestones were achieved.


HIGHLIGHTS

  • Three lead concentrate shipments totalling ~22kt were completed, more than doubling revenue from the previous quarter to ~A$45 million and generating positive operating cash flows.
  • New quarterly mining and production records:
    • Total ore milled of ~283kt (~49% increase from previous quarter);
    • Lead concentrate production of ~19kt (~50% increase from previous quarter);
    • Total ore mined of ~292kt (~50% increase from previous quarter), with underground stope production of ~202kt;
    • Mining of first core vein stope commenced and paste-fill plant commissioned; and
    • Underground development of ~2,100m, including a new monthly record of ~800m in September.
  • Lead grade continues to improve as new work areas are established and the ratio of stoping ore to development ore continues to increase.
  • The official Abra mine opening ceremony was held on 13 September 2023. The mine was officially opened by the President of Toho Zinc (Mr. Masahito Ito) and the Galena/Abra Chairman (Mr. Adrian Byass).
Managing Director, Tony James commented, “The Abra mine was able to achieve new quarterly production highs as we continue to move through the ramp-up process. During this time, we continued to improve the mine’s production levels as we endeavour to become more consistent with our mining and processing. The result was positive operating cash flows for the Quarter.

The mine delivered 202kt of stope ore for the Quarter. Operational and technical issues associated with mining two stopes in September and the commissioning of the paste-fill plant generated stope production delays which were resolved. The plant processed 283kt of stoping and development ore during the Quarter. Ore processed was ~5% less than target due to 13 days of non-processing time over the Quarter, mainly associated with some unplanned and planned maintenance work. Unplanned maintenance included conveyor replacement following rockbolt damage and a primary crusher blockage. Planned maintenance included the mine’s first shutdown for various maintenance activities including the first mill reline.

Achieving higher development rates in the mine of 2,100m (target 2,000m) is significant as it enables us to continue to open new work areas which will allow access to multiple higher-grade stoping blocks. With this, we expect grades to continue to improve as mining progresses and we are very pleased with the strong correlation between the stope grades and the processing reconciliation for the stopes. In steady-state, stoping is expected to account for 80% of the feed stocks which allows the mine to be less reliant on the generally lower grade ore development which is associated with the ramp-up period of operations.

The Abra team continues to be resilient and busy during the mine’s ramp-up and it’s nice to see everyone being rewarded with the continuous improvement we are achieving. We look forward to taking the next ramp-up step in the December quarter, which should see Abra reaching close to its full potential.”

Figures 5-11 (below) show recent photographs of the Abra mine.

Figure 5 – Traditional Japanese opening ceremony conducted on site on 13 September. Participants left to right included, Ms. Belinda Riley (Jidi Jidi Corporation), Mr. Steve Coughlan (Executive Chairman Byrnecut Group),Mr. Masahito Ito (President Toho Zinc), Mr. Adrian Byass (Galena/Abra Chairman) and Mr. Charles Loxton (Taurus Funds Management).

Figure 6 – Abra mine opening ceremony (photo 13 September 2023).


Click here for the full ASX Release

This article includes content from Galena Mining, licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.


G1A:AU
Galena Mining

Galena Mining Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

The Conversation (0)
Galena Mining (ASX:G1A)

Galena Mining


Keep reading...Show less
Galena Mining

Abra Construction At 97% Complete – First Ore Stockpiled For January Processing

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 97% complete as of 30 November 2022. Processing plant commissioning is progressing quickly with practical completion now expected in December 2022. Ore currently being mined from underground is being stockpiled in readiness for processing to begin in January 2023. Concentrate production will commence January 2023.

Keep reading...Show less
Galena Mining

Abra Construction At 92% Complete – Reaches First Ore Underground

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 92% complete as of 31 October 2022. Underground mine has reached the first ore (see ASX announcement 14 November 2022) and plant commissioning continues in several key areas with the project focussed on achieving first concentrate production in Q1 2023.
Keep reading...Show less
Galena Mining

Abra Mine Reaches Ore

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the underground development at its Abra Base Metals Mine (“Abra” or the “Project”) has reached the Abra orebody. Commissioning has commenced in several key areas of the processing facility and the Power Station (Pacific Energy) completed full integration of the hybrid gas/solar/battery energy storage system (BESS) power station on 10 November. The project remains on track for first concentrate production in Q1 2023.
Keep reading...Show less
Galena Mining

Galena Mining Activities Report For Quarter Ended 30 September 2022

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) reports on its activities for the quarter ended 30 September 2022 (the “Quarter”), primarily focused on construction of its 60%- owned Abra Base Metals Mine (“Abra” or the “Project”) located in the Gascoyne region of Western Australia.

Keep reading...Show less
Australian flag patch on a mine site.

Western Australian METS Companies Awarded AU$1.25 Million in Funding

The Minerals Research Institute of Western Australia (MRIWA) said on Wednesday (October 30) that it is awarding five companies with research funding through its Mining Equipment, Technology and Services (METS) Innovation Program.

The funding totals AU$1.25 million, with Aquirian (ASX:AQN), Total Marine Technology, Big Roller Overland Conveyor Company, Electric Power Conversions Australia and CMG Operations receiving AU$250,000 each.

The WA government said it prioritizes “projects that will directly accelerate the development of companies, products and new markets benefiting the Western Australian economy” for the METS Innovation Program.

Aquirian, the only publicly listed company receiving the grant, will allocate the funding for developing automation for its existing Collar Keeper system. This would allow the driller to stay inside the cab, reducing personnel risk in drilling.

Keep reading...Show less
Ronin Resources

Ronin Resources Applies for Gold-Silver Project in San Juan, Argentina

Ronin Resources Ltd (ASX: RON) (Ronin or the Company) is pleased to advise that it has submitted mineral exploration applications over 23,637 hectares (236.37 km2) prospective for gold-silver mineralisation in the San Juan Province of Argentina. The La Punilla Gold-Silver Project is accessible from the San Juan town of Rodeo, via the same road intended to access BHP and Lundin Mining’s Filo de Sol and Josemaría projects.

Keep reading...Show less
Provaris

Provaris Energy Quarterly Activities Report

Provaris Energy Ltd (ASX: PV1, Provaris, the Company) is pleased to provide the following summary of the Company’s development activities for the quarter that ended 30 September 2024.

Keep reading...Show less
Basin Energy

Quarterly Activities Report for the Period Ending 30 September 2024

Basin Energy Limited (ASX:BSN) (‘Basin’ or the ‘Company’) is pleased to provide an overview of activities for the period ending 30 September 2024 (‘Quarter’, ‘Reporting Period’) and an accompanying Appendix 5B.

Keep reading...Show less
Basin Energy

Basin Energy to Acquire Scandinavian Uranium and Green Energy Metals Portfolio

Basin Energy Limited (ASX:BSN) (‘Basin’ or the ‘Company’) is pleased to announce the signing of a binding agreement (the “Agreement”) to acquire an exploration portfolio located within Scandinavia (the “Projects”).

Keep reading...Show less
IMARC

Governments Double Down on Critical Minerals and Sustainability at IMARC 2024

Increasing the supply of critical minerals, advancing technological innovation, and strengthening sustainability and ESG commitments were central themes highlighted today by the Australian and NSW Governments at the International Mining and Resources Conference and Expo (IMARC).


Keep reading...Show less
Galena Mining

Galena Mining Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

Latest Press Releases

Related News

×