Nomgon CBM Operations Update

Elixir Energy Limited (“Elixir” or the “Company”) is pleased to provide an operations update on the work currently underway in its 100% owned Nomgon IX Coal Bed Methane (CBM) Production Sharing Contract (PSC) in the South Gobi Basin, Mongolia.


HIGHLIGHTS

  • Nomgon Pilot Project returns to managed flare
  • Nomgon-10 pilot well to spud at end of month
  • Big Slope-7 intersects thick coals with good desorption and DST completed
Operations at the Nomgon Pilot Project continue, with the pilot plant now returning to managed gas production. During the last month, both wells have been produced intermittently whilst the production team varied casing pressures, pump rates and water levels. Water production throughout this has remained relatively static at rates of 110-120 barrels of water per day. Whilst the gas rate is still lower than the original flowrates at the beginning of the test, a clear increasing trend is now emerging.

The previously announced additional pilot well, called Nomgon-10, will spud towards the end of this month, using international drilling contractor Major Drilling. The existing pilot wells will be shut in during the drilling operation. At the completion of this new pilot drilling, the lesser performing Nomgon- 8 will be temporarily suspended, with the Nomgon-10 production well to replace it in the production system.

Recent flare at the Nomgon Pilot

The Big Slope-7 appraisal corehole has now been completed. The well was drilled to a depth of 666 metres, with drilling curtailed slightly ahead of the originally planned total depth due to difficult hole conditions. A total of 35 metres of coal and 7m of silty coal was intersected, with 1 Drill Stem Test (DST) conducted. The interpretation of the results of the DST will be announced in due course.

The well was drilled by Mongolian drilling contractor Erdene Drilling LLC and is the first of a number of wells it is contracted to Elixir for drilling in the region. The rig has now moved to a nearby location to the West of the previous well to drill a corehole: Big Slope Shallow-1, where it will appraise the shallower coals at deeper locations.

Erdene drilling rig at Big Slope 7

Erdene Drilling has also brought a second rig into the basin and will replace Top Diamond Drilling as the Company’s primary exploration drilling contractor. Top Diamond Drilling completed the drilling of the Bluebill-1S exploration well recently, with the well intersecting gaseous coal in cuttings.


Click here for the full ASX Release

This article includes content from Elixir Energy, licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.

EXR:AU
Elixir Energy

Elixir Energy Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

The Conversation (0)
Elixir Energy

Elixir Energy


Keep reading...Show less
Industrial Minerals Limited

Maiden Mukinbudin Quartz Processing Testwork Achieves Premium HPQ Product

Industrial Minerals Ltd (ASX: IND or the Company) is pleased to announce that it has received results from High Purity Ǫuartz Processing Testwork1 completed by North Carolina State University’s Mineral Research Laboratory (“NCSU-MRL”).

Keep reading...Show less
Auric Mining (ASX:AWJ)

Quarterly Appendix 5B Cash Flow Report

Auric Mining Limited (ASX: AWJ) (Auric or the Company) is pleased to release its Quarterly Cash Flow Report for the period ended June 30, 2024.

Keep reading...Show less
Auric Mining (ASX:AWJ)

Quarterly Activities Report 30 June 2024

Auric Mining Limited (ASX: AWJ) (Auric or the Company) is pleased to report on its activities during the 30 June 2024 Quarter.

Keep reading...Show less
Miramar Resources (ASX:M2R)

Quarterly Report - Quarter Ending in 30 June 2024

Miramar Resources Limited (ASX:M2R, Miramar or “the Company”) is pleased to provide a summary of activities completed during the Quarter ending 30 June 2024.

Keep reading...Show less
Auric Mining (ASX:AWJ)

Jeffreys Find Gold Mine Toll Milling of 150,000 Tonnes Commenced, Second 2024 Campaign

Auric Mining Limited (ASX: AWJ) (Auric or the Company) is pleased to announce the second gold milling campaign for 2024 of 150,000 dry metric tonnes from the Jeffreys Find Gold Mine (the Project) near Norseman, WA, commenced on 24 July 2024.

Keep reading...Show less
Alice Queen Limited

Viani - Low Sulphidation Epithermal Gold Project License Renewed

Advanced gold and copper explorer, Alice Queen Limited (ASX:AQX) (Alice Queen or the Company), is pleased to advise that it has received notification from the Mineral Resources Department (MRD) of Fiji that its highly prospective low sulphidation epithermal (LSE) gold project, Viani (SPL1513) located on the Pacific Rim of Fire, on Fiji’s second biggest island Vanua Levu, has been renewed for a further three years, commencing on 3 July 2024.

Keep reading...Show less
Elixir Energy

Elixir Energy Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

Latest Press Releases

Related News

×