Another Solid Quarter Keeps Barrick On Track for Full-Year Production Targets

All amounts expressed in US dollars

Barrick Gold Corporation (NYSE:GOLD)(TSX:ABX) ("Barrick" or the "company") today reported preliminary third quarter sales of 1.25 million ounces of gold and 116 million pounds of copper, as well as preliminary third quarter production of 1.16 million ounces of gold and 103 million pounds of copper. Group gold production for the first nine months of 2020 was 3.6 million ounces, and the company remains on track to achieve full-year production guidance 1 .

The average market price for gold in the third quarter was $1,909 per ounce, while the average market price for copper in the third quarter was $2.96 per pound.

Preliminary third quarter gold production was slightly higher than the second quarter of 2020, notwithstanding the fact that there was no third quarter production at Porgera in Papua New Guinea which was placed on care and maintenance on April 25, 2020. Excluding Porgera, third quarter gold production was 3% higher than the second quarter mainly due to stronger performances from Carlin and Pueblo Viejo following the completion of scheduled plant maintenance in the prior quarter. Preliminary third quarter gold sales were slightly higher than the previous quarter, and exceeded third quarter production following the export of the remaining stockpiled concentrate in Tanzania. Third quarter gold cost of sales per ounce 2 is expected to be in line, total cash costs per ounce 3 are expected to be 2-4% lower and gold all-in sustaining costs per ounce 3 are expected to be 5-7% lower, than in the second quarter of 2020.

Preliminary third quarter copper production and sales were both lower than the previous quarter, primarily as a result of lower throughput at Lumwana following plant maintenance completed in the quarter. Third quarter copper cost of sales per pound 2 is expected to be 4-6% lower and C1 cash costs per pound 3 are expected to be 5-7% lower than the prior quarter. Copper all-in sustaining costs per pound 3 are expected to be 6-8% higher than the second quarter of 2020 as a result of higher capitalized stripping at Lumwana.

Barrick will provide additional discussion and analysis regarding its third quarter production and sales when the company reports its quarterly results before North American markets open on November 5, 2020.

The following table includes preliminary gold and copper production and sales results from Barrick's operations:

Three months ended Nine months ended
September 30, 2020 September 30, 2020
Production Sales Production Sales
Gold (equity ounces (000))
Carlin 4 (61.5%) 276 275 764 765
Cortez (61.5%) 113 115 373 375
Turquoise Ridge (61.5%) 76 76 239 242
Phoenix (61.5%) 30 31 100 100
Long Canyon (61.5%) 43 45 109 110
Nevada Gold Mines (61.5%) 538 542 1,585 1,592
Loulo-Gounkoto (80%) 139 136 421 416
Pueblo Viejo (60%) 129 129 383 388
Kibali (45%) 91 91 272 275
North Mara (84%) 67 69 200 206
Tongon (89.7%) 64 65 189 191
Hemlo 55 55 166 167
Veladero (50%) 44 43 168 135
Buzwagi (84%) 21 73 63 153
Bulyanhulu (84%) 7 46 21 83
Porgera (47.5%) 0 0 86 87
Total Gold 1,155 1,249 3,554 3,693
Copper (equity pounds (millions))
Lumwana 62 74 198 212
Zaldívar (50%) 24 21 83 81
Jabal Sayid (50%) 17 21 57 56
Total Copper 103 116 338 349

Third Quarter 2020 Results

Barrick will release its Q3 2020 results before market open on November 5, 2020. President and CEO Mark Bristow will again host an interactive webinar on the results at 11:00 EST / 16:00 UTC. The presentation will be linked to the webinar and conference call. Participants will be able to ask questions.

Go to the webinar
US and Canada (toll-free) 1 800 319 4610
UK (toll-free) 0808 101 2791
International (toll) +1 416 915 3239

The Q3 2020 presentation materials will be available on Barrick's website at www.barrick.com .

The webinar will remain on the website for later viewing, and the conference call will be available for replay by telephone at 1 855 669 9658 (US and Canada) and +1 604 674 8052 (international), access code 5232.

Enquiries:

Claudia   Pitre
Analyst, Investor Relations and Corporate Access
+1 416 307 5105
cpitre@barrick.com

Kathy du Plessis
Investor and Media Relations
+44 20 7557 7738
barrick@dpapr.com

Technical Information

The scientific and technical information contained in this news release has been reviewed and approved by: Steven Yopps, MMSA, Manager of Growth Projects, Nevada Gold Mines; Chad Yuhasz, P.Geo, Mineral Resource Manager, Latin America and Asia Pacific; and Simon Bottoms, CGeol, MGeol, FGS, FAusIMM, Mineral Resources Manager, Africa and Middle East – each a "Qualified Person" as defined in National Instrument 43-101 – Standards of Disclosure for Mineral Projects .

Endnote 1

Barrick is closely monitoring the global Covid-19 pandemic and Barrick's guidance may be impacted if the operation or development of our mines and projects is disrupted due to efforts to slow the spread of the virus.

Endnote 2

Cost of sales applicable to gold per ounce is calculated using cost of sales applicable to gold on an attributable basis (removing the non-controlling interest of 40% Pueblo Viejo, 38.5% Nevada Gold Mines, 63.1% South Arturo, 20% Loulo-Gounkoto, 16% North Mara, Bulyanhulu and Buzwagi and 10.3% of Tongon and including our proportionate share of cost of sales attributable to equity method investments (Kibali) in cost of sales), divided by attributable gold ounces. Cost of sales applicable to copper per pound is calculated using cost of sales applicable to copper including our proportionate share of cost of sales attributable to equity method investments (Zaldívar and Jabal Sayid), divided by consolidated copper pounds (including our proportionate share of copper pounds from our equity method investments).

Endnote 3

Total cash costs per ounce, all-in sustaining costs per ounce and all-in costs per ounce are non-GAAP financial measures which are calculated based on the definition published by the World Gold Council (a market development organization for the gold industry comprised of and funded by gold mining companies from around the world, including Barrick). The WGC is not a regulatory organization. Management uses these measures to monitor the performance of our gold mining operations and its ability to generate positive cash flow, both on an individual site basis and an overall company basis.

Total cash costs start with our cost of sales related to gold production and removes depreciation, the non-controlling interest of cost of sales and includes by-product credits. All-in sustaining costs start with total cash costs and include sustaining capital expenditures, sustaining leases, general and administrative costs, minesite exploration and evaluation costs and reclamation cost accretion and amortization. These additional costs reflect the expenditures made to maintain current production levels.

We believe that our use of total cash costs, all-in sustaining costs and all-in costs will assist analysts, investors and other stakeholders of Barrick in understanding the costs associated with producing gold, understanding the economics of gold mining, assessing our operating performance and also our ability to generate free cash flow from current operations and to generate free cash flow on an overall company basis. Due to the capital-intensive nature of the industry and the long useful lives over which these items are depreciated, there can be a significant timing difference between net earnings calculated in accordance with IFRS and the amount of free cash flow that is being generated by a mine and therefore we believe these measures are useful non-GAAP operating metrics and supplement our IFRS disclosures. These measures are not representative of all of our cash expenditures as they do not include income tax payments, interest costs or dividend payments. These measures do not include depreciation or amortization.

Total cash costs per ounce, all-in sustaining costs and all-in costs are intended to provide additional information only and do not have standardized definitions under IFRS and should not be considered in isolation or as a substitute for measures of performance prepared in accordance with IFRS. These measures are not equivalent to net income or cash flow from operations as determined under IFRS. Although the WGC has published a standardized definition, other companies may calculate these measures differently.

C1 cash costs per pound and all-in sustaining costs per pound are non-GAAP financial measures related to our copper mine operations. We believe that C1 cash costs per pound enables investors to better understand the performance of our copper operations in comparison to other copper producers who present results on a similar basis. C1 cash costs per pound excludes royalties and production taxes and non-routine charges as they are not direct production costs. All-in sustaining costs per pound is similar to the gold all-in sustaining costs metric and management uses this to better evaluate the costs of copper production. We believe this measure enables investors to better understand the operating performance of our copper mines as this measure reflects all of the sustaining expenditures incurred in order to produce copper. All-in sustaining costs per pound includes C1 cash costs, sustaining capital expenditures, sustaining leases, general and administrative costs, minesite exploration and evaluation costs, royalties and production taxes, reclamation cost accretion and amortization and write-downs taken on inventory to net realizable value.

Barrick will provide a full reconciliation of these non-GAAP financial measures when the Company reports its quarterly results on November 5, 2020.

Endnote 4

Includes Nevada Gold Mines' 60% equity share of South Arturo.\

Cautionary Statements Regarding Preliminary Third Quarter Production, Sales and Costs for 2020, and Forward-Looking Information

Barrick cautions that, whether or not expressly stated, all third quarter figures contained in this press release including, without limitation, production levels, sales and associated costs are preliminary, and reflect our expected third quarter results as of the date of this press release. Actual reported third quarter production levels, sales and associated costs are subject to management's final review, as well as review by the Company's independent accounting firm, and may vary significantly from those expectations because of a number of factors, including, without limitation, additional or revised information, and changes in accounting standards or policies, or in how those standards are applied. Barrick will provide additional discussion and analysis and other important information about its third quarter production levels and sales and associated costs when it reports actual results on November 5, 2020. For a complete picture of the Company's financial performance, it will be necessary to review all of the information in the Company's third quarter financial report and related MD&A. Accordingly, readers are cautioned not to rely solely on the information contained herein.

Finally, Barrick cautions that this press release contains forward-looking statements with respect to: (i) Barrick's production; (ii) costs per ounce for gold and per pound for copper; and (iii) Barrick's ability to achieve its guidance for the year.

Forward-looking statements are necessarily based upon a number of estimates and assumptions including material estimates and assumptions related to the factors set forth below that, while considered reasonable by the Company as at the date of this press release in light of management's experience and perception of current conditions and expected developments, are inherently subject to significant business, economic, and competitive uncertainties and contingencies. Known and unknown factors could cause actual results to differ materially from those projected in the forward-looking statements, and undue reliance should not be placed on such statements and information. Such factors include, but are not limited to: fluctuations in the spot and forward price of gold, copper, or certain other commodities (such as silver, diesel fuel, natural gas, and electricity); the speculative nature of mineral exploration and development; changes in mineral production performance, exploitation, and exploration successes; the duration of the temporary suspension of operations at Porgera; risks associated with projects in the early stages of evaluation, and for which additional engineering and other analysis is required; disruption of supply routes which may cause delays in construction and mining activities at Barrick's more remote properties; whether benefits expected from recent transactions are realized; diminishing quantities or grades of reserves; increased costs, delays, suspensions and technical challenges associated with the construction of capital projects; operating or technical difficulties in connection with mining or development activities, including geotechnical challenges and disruptions in the maintenance or provision of required infrastructure and information technology systems; failure to comply with environmental and health and safety laws and regulations; timing of receipt of, or failure to comply with, necessary permits and approvals; uncertainty whether some or all of targeted investments and projects will meet the Company's capital allocation objectives and internal hurdle rate; the impact of global liquidity and credit availability on the timing of cash flows and the values of assets and liabilities based on projected future cash flows; the impact of inflation; fluctuations in the currency markets; changes in national and local government legislation, taxation, controls or regulations and/ or changes in the administration of laws, policies and practices, expropriation or nationalization of property and political or economic developments in Canada, the United States, and other jurisdictions in which the Company or its affiliates do or may carry on business in the future; lack of certainty with respect to foreign legal systems, corruption and other factors that are inconsistent with the rule of law; damage to the Company's reputation due to the actual or perceived occurrence of any number of events, including negative publicity with respect to the Company's handling of environmental matters or dealings with community groups, whether true or not; the possibility that future exploration results will not be consistent with the Company's expectations; risks that exploration data may be incomplete and considerable additional work may be required to complete further evaluation, including but not limited to drilling, engineering and socioeconomic studies and investment; risk of loss due to acts of war, terrorism, sabotage and civil disturbances; risks associated with illegal and artisanal mining; risks associated with new diseases, epidemics and pandemics, including the effects of the global Covid-19 pandemic; litigation and legal and administrative proceedings; contests over title to properties, particularly title to undeveloped properties, or over access to water, power and other required infrastructure; business opportunities that may be presented to, or pursued by, the Company; our ability to successfully integrate acquisitions or complete divestitures; risks associated with working with partners in jointly controlled assets; employee relations including loss of key employees; increased costs and physical risks, including extreme weather events and resource shortages, related to climate change; and availability and increased costs associated with mining inputs and labor. Barrick also cautions that its 2020 guidance may be impacted by the unprecedented business and social disruption caused by the spread of Covid-19. In addition, there are risks and hazards associated with the business of mineral exploration, development and mining, including environmental hazards, industrial accidents, unusual or unexpected formations, pressures, cave-ins, flooding and gold bullion, copper cathode or gold or copper concentrate losses (and the risk of inadequate insurance, or inability to obtain insurance, to cover these risks).

Many of these uncertainties and contingencies can affect our actual results and could cause actual results to differ materially from those expressed or implied in any forward-looking statements made by, or on behalf of, us. Readers are cautioned that forward-looking statements are not guarantees of future performance. All of the forward-looking statements made in this press release are qualified by these cautionary statements. Specific reference is made to the most recent Form 40-F/Annual Information Form on file with the SEC and Canadian provincial securities regulatory authorities for a more detailed discussion of some of the factors underlying forward-looking statements and the risks that may affect Barrick's ability to achieve the expectations set forth in the forward-looking statements contained in this press release.

Barrick disclaims any intention or obligation to update or revise any forward-looking statements whether as a result of new information, future events or otherwise, except as required by applicable law.

Primary Logo

News Provided by GlobeNewswire via QuoteMedia

The Conversation (0)
larry lepard, gold, silver, bitcoin

Lawrence Lepard: "Big Print" Coming — Fully Expect US$5,000 Gold, US$200,000 Bitcoin

Speaking to the Investing News Network, Lawrence Lepard, managing director at EMA, voiced his thoughts on the outlook for gold and Bitcoin as the debt doom loop intensifies in the US.

"I call it a doom loop — it's a vicious circle in the wrong direction, which I believe will ultimately lead to the government having to say, 'Okay, this isn't going to work. We are going to institute yield curve control or QE, or we're going to buy the bonds,'" he explained on the sidelines of the New Orleans Investment Conference.

Lepard believes it's important to hold both gold and Bitcoin, noting that the only wrong allocation is zero.

Keep reading...Show less
Chris Temple, uranium symbol and gold bars.

Chris Temple: Gold's Next Leg Higher, Plus Uranium and Natural Gas in 2025

Chris Temple, founder, editor and publisher of the National Investor, outlined the main factors he sees impacting the gold price heading into 2025, saying the yellow metal will undoubtedly move higher.

In his view, its rise will come as market participants realize how many problems the US economy is facing.

"I think that once that reality sets in, gold will get its next big lease on life and the stock market is going to bog down. I think we're going to see a lot of rotation in the market that will start to favor real assets and real value — away from everybody chasing the same relative handful of stocks as we've seen," Temple explained.

Keep reading...Show less
Gold bars stacked in ascending order.

WGC: Gold to Face Complex Drivers in 2025, Price Likely to Cool After Record-Breaking Year

The World Gold Council (WGC) has released its 2025 gold outlook, highlighting various macroeconomic factors, geopolitical risks and central bank activity as pivotal forces influencing demand and prices.

While 2024 saw gold achieve a stellar performance with a 28 percent annual increase, the outlook for 2025 is characterized by a mix of opportunities and challenges stemming from both global and regional developments.

The yellow metal has benefited from its historical role as a hedge against uncertainty, but the WGC forecasts that its performance next year will depend on other key variables as well.

Keep reading...Show less
Brightstar Resources Managing Director Alex Rovira.

Increased M&A Activity a Win-Win for Gold Sector, Brightstar Resources Exec Says

Following the completion of its acquisition of Alto Metals, Brightstar Resources (ASX:BTR) plans to conduct 50,000 metres of reverse-circulation and diamond drilling, beginning next year, at Alto Metals' approximately 900 square kilometre Sandstone gold project in Western Australia.

In an interview with the Investing News Network, Brightstar Managing Director Alex Rovira outlined the next steps for merging Alto Metals with Brightstar’s assets and the strategy for moving forward.

“From an exploration perspective … it's really focusing on the Sandstone package. We will do near-mine brownfields exploration at our Menzies and Laverton gold projects. And really, the aspiration there is to take a number of those mines toward development decisions,” he said.

Keep reading...Show less
Horizon Minerals

Horizon Minerals

Keep reading...Show less

Agnico Eagle and O3 Mining Welcome Gold Fields' Support of Their Friendly Premium Transaction

(All amounts expressed in Canadian dollars unless otherwise noted)

Agnico Eagle Mines Limited (NYSE: AEM) (TSX: AEM) (" Agnico Eagle ") and O3 Mining Inc. (TSXV: OIII) (OTCQX: OIIIF) (" O3 Mining ") are pleased to jointly announce that Gold Fields Limited, through a 100% indirect Canadian subsidiary (" Gold Fields "), O3 Mining's largest shareholder, has agreed to a lock-up agreement with Agnico Eagle to tender its common shares of O3 Mining (" Common Shares ") into Agnico Eagle's offer to acquire all of the outstanding Common Shares for $1.67 per Common Share in cash by way of a take-over bid (the " Offer "). See O3 Mining and Agnico Eagle's joint news release of December 12, 2024 for a detailed description of the Offer. A copy of the December 12, 2024 joint news release is available at: https:www.agnicoeagle.comEnglishinvestor-relationsnews-and-eventsnews-releasesnews-release-details2024Agnico-Eagle-to-Acquire-O3-Mining-in-Friendly-Transactiondefault.aspx .

News Provided by Canada Newswire via QuoteMedia

Keep reading...Show less

Latest Press Releases

Related News

×