White Metal Resources Corp. (TSXV: WHM) ( FRA: CGK1 ) ( OTCMKTS: TNMLF) ("White Metal" or the "Company") today announced a new mineral resource estimate on the Okohongo Cu-Ag Deposit located within it 95% owned Taranis (Okohongo) Cu-Ag Project (the "Project" or "Property"), as defined by Exclusive Prospecting Licence ("EPL") 7071 which covers about 19,850 hectares and is located in the Kaoko Copperbelt, northwestern Namibia.

Michael Stares, President & CEO of White Metal, stated, "We believe the results from the new Mineral Resource Estimate demonstrate core value of the Okohongo and this resource, coupled with the more recent exploration work showing very positive copper and silver results both north and south of the Okohongo, really outline the incredible upside to this Project. We believe there is significant opportunity to expand the Okohongo along strike, which at this stage of exploration shows potential along a prospective horizon of more than 20 kilometres. Although White Metal remains focussed on progressing its flagship project, the Tower Stock Gold Project in Ontario, Canada, the Company will continue to advance the Okohongo Copper-Silver Project as one of its primary assets."

Mineral Resource Estimate
White Metal is very pleased to announce a new Mineral Resource Estimate ("MRE") for the Taranis (Okohongo) Cu-Ag Project. A total of 3,226 metres of Reverse Circulation ("RC") drilling in 28 drill holes (518 chip samples in resource) and 781.70 metres of historical diamond drill core in 4 holes (63 core samples in resource) were used to calculate the Mineral Resources in the Inferred category (Table 1). The area covered by the resource is about 740 m (east-west) and 720 m (north-south). Using a cut-off grade of 0.30% Cu and assuming 10% geological loss, the study reported approximately 7.7 million tonnes grading 1.55% Cu and 26.77 g/t Ag with a calculated copper equivalent (CuEq) of 1.82% Cu. A grade-tonnage sensitivity analysis is provided in Table 2. Example cross-sections/ block model views of the MRE are provided in Figures 1 and 2, and 3D image of the conceptual open pit and resource is provided in Figure 1.

The MRE was prepared by Caracle Creek International Consulting MINRES (Pty) Ltd. ("CCIC MINRES"), South Africa, in accordance with current CIM Definition Standards on Mineral Resources and Reserves. A Technical Report in support of the MRE will be filed on SEDAR ( www.sedar.com ) within 45 days of this news release. The MRE is effective as at August 11, 2021.

Table 1. Mineral Resource Estimate Statement for the Okohongo Cu-Ag Deposit, Namibia (0.30% Cu cut-off).

Classification Tonnes 5 Cu (%) Ag (g/t) CuEq 3 Cu (t) Ag (oz) CuEq (t)
Inferred 7,706,732 1.55 26.77 1.82 119,256 6,634,133 139,891

1. The independent Qualified Person for the Mineral Resource Estimate, as defined by NI 43-101, is Mr. Sivanesan (Desmond) Subramani (Pri. Sci. Nat - 400184/06), Caracle Creek International Consulting MINRES (Pty) Ltd. (CCIC MINRES), South Africa. The effective date of the Mineral Resource Estimate is August 11, 2021.
2. These Mineral Resources are not Mineral Reserves as they do not have demonstrated economic viability. The quantity and grade of reported Inferred Resources in this Mineral Resource Estimate are uncertain in nature and there has been insufficient exploration to define these Inferred Resources as Indicated or Measured, however it is reasonably expected that the majority of Inferred Mineral Resources could be upgraded to Indicated Mineral Resources with continued exploration.
3. Copper equivalent (CuEq) was calculated using a copper price of US$3.75/lb and a silver price of US$25.00/oz and applying the formula: CuEq = Cu% + (Ag g/t * 0.01).
4. A cut-off grade of 0.30% Cu was used for the low- and high-grade domains. The cut-off grade was determined on the basis of core assay geostatistics and drill core lithologies for the deposit, and by comparison to analogous deposit types.
5. Tonnages are reported applying a geological loss of 10%, to account for unknown geological discontinuities; 10% is based on experience of other deposits in similar geological settings.
6. Geological and block models for the Mineral Resource Estimate used data from a total of 24 surface reverse circulation drill holes, completed by White Metal in January-February 2021, and four re-sampled historical diamond drill holes (completed by Teck in 2008 and INV Metals in 2011). The drill hole database was validated prior to resource estimation and QA/QC checks were made using industry-standard control charts for blanks, RC chips sample duplicates, and commercial certified reference material (standards and blanks) inserted into assay batches by White Metal and by comparison of umpire RC chip sample assays performed at a second laboratory.
7. Estimates in Table 1 have been rounded to two significant figures.
8. The Inferred Mineral Resources were constrained by a Lerchs-Grossmann conceptual open pit envelope that was developed using the following optimization parameters: i) metal prices of US$3.75/lb copper and $25/oz silver; ii) an overall pit slope of 55 degrees; iii) bulk mining costs of US$2/t (ore) and US$1/t (waste), derived from other comparative copper projects in African copper belts; iv) processing costs and G&A estimated at US$7.80/t; and v) plant recoveries assumed to be 80% copper and 80% silver.
9. The Mineral Resource Estimate was prepared following the CIM Estimation of Mineral Resources & Mineral Reserves Best Practice Guidelines (November 29, 2019).
10. The geological model as applied to the Mineral Resource Estimate comprises eight Individual wireframes that were created for each grade domain.
11. The block model was prepared using Datamine Studio RM software. A 50 m x 50 m x 5 m block model was created and samples were composited at 1.0 m intervals. Grade estimation from drill hole data was carried out for Cu and Ag using the Ordinary Kriging interpolation method.
12. Grade estimation was validated by comparison of input and output statistics, swath plot analysis, and by visual inspection of the assay data, block model, and grade shells in cross-sections.
13. The applied average specific gravity (2.45 t/m3) was determined on the basis of CCIC MINRES's in-house library of SG and bulk density measurements from similar deposits in the African copper belts.

Table 2. Grade-Tonnage sensitivity analysis for the Okohongo Cu-Ag Deposit, Namibia.

Cut-off
(%Cu)
Original
Tonnes
Adjusted
Tonnes 5
SG Cu
(%)
Ag
(g/t)
CuEq 3 Cu Metal
(t)
Ag Metal
(oz)
CuEq
Metal (t)
0.0 8,647,675 7,782,908 2.45 1.53 26.54 1.80 119,459 6,641,266 140,115
0.1 8,647,675 7,782,908 2.45 1.53 26.54 1.80 119,459 6,641,266 140,115
0.2 8,647,675 7,782,908 2.45 1.53 26.54 1.80 119,459 6,641,266 140,115
0.3 8,563,035 7,706,732 2.45 1.55 26.77 1.82 119,256 6,634,133 139,891
0.4 7,729,289 6,956,360 2.45 1.68 29.09 1.97 116,681 6,506,902 136,920
0.5 7,631,602 6,868,442 2.45 1.69 29.40 1.99 116,320 6,491,169 136,510
0.6 7,602,738 6,842,464 2.45 1.70 29.44 1.99 116,182 6,476,379 136,326
0.7 7,435,124 6,691,612 2.45 1.72 29.71 2.02 115,197 6,392,448 135,080
0.8 7,083,401 6,375,061 2.45 1.77 30.31 2.07 112,772 6,212,486 132,095

Figure 1: Cross-section (looking north) through the middle region of the Okohongo Cu-Ag Deposit (see inset plan map) showing the copper grade distribution in the block model and locations of five RC drill holes completed by the Company (OK20 series) and one re-sampled historical diamond drill hole (TCD series) (coordinate system: WGS84 Z33S). https://www.globenewswire.com/NewsRoom/AttachmentNg/798bcbe7-0954-4d3f-9ae4-66164674100b

Figure 2: Cross-section (looking east) through the middle region of the Okohongo Cu-Ag Deposit (see inset plan map) showing the copper grade distribution in the block model and locations of four RC drill holes completed by the Company (OK20 series) (coordinate system: WGS84 Z33S). https://www.globenewswire.com/NewsRoom/AttachmentNg/2cdc5255-e817-46fd-aa88-6ec7669f313a

Figure 3: Lerchs-Grossmann conceptual pit shell (shaded orange) constraining the Inferred Mineral Resource Estimate (oblique section looking down and north-northwest). The conceptual pit shell opening is about 950 m in length, 615 m in width, and extends to a depth of about 200 m below surface. The deeper, down-dip mineral resources that fall outside of the pit envelope amount to approximately 3% of the total mineral resources inventory calculated. https://www.globenewswire.com/NewsRoom/AttachmentNg/d7d9126e-3047-432b-83b5-9cb773af6010

Additional figures and information about the Mineral Resource Estimate and recent results from the copper exploration programs at Okohongo can be viewed on the Company's website ( https://www.whitemetalre s .com/taranis-oko h ongo-cu-ag.html ).

Assays, Quality Assurance/Quality Control and Assay Procedures
Mr. Nico Scholtz was responsible a Qualified Person as defined by NI 43-101 (Pri. Sci. Nat – 400299/07), was responsible for the RC drilling and sampling program, including quality assurance ("QA") and quality control ("QC"). The RC chip samples were collected from drill using a 3 tier riffle splitter, to split the sample and represented chip samples were collected and logged on site. Samples were taken at 1 metre intervals. Samples were securely transported to the Activation Laboratories Ltd. ("Actlabs") preparation lab in Windhoek, Namibia.

A Quality Control/Quality Assurance ("QA/QC") program consisting of the regular insertion of Certified Reference Material ("CRM") copper standards and blanks into the sample stream by the Company was in place as was the industry standard internal QA/QC practices used by Actlabs. A CRM copper standard was inserted approx. every 20 samples, a control blank was inserted every 15 samples and a duplicate taken every 30 samples. A total of 24 duplicate chip samples were analysed at referee lab ALS Global, an ISO/IEC 7025 accredited lab, based in Johannesburg, South Africa.

Once prepared, Actlabs in Windhoek, Namibia sent the sample pulps directly to Actlabs in Ancaster, Ontario, Canada for analyses. Actlabs is an ISO/IEC 7025 accredited lab and is independent of White Metal. The samples were first analysed with 4-Acid "Near Total" Digestion (1F2) with ICP-OES finish for Ag, Cu and a suite of 33 other elements. Subsequently, samples with Ag greater than 100 ppm (above Ag upper detection limit) were analysed with Fire Assay Gravimetric (8-Ag) and Cu greater than 10,000 ppm (above Cu upper detection limit) were analysed with sodium peroxide fusion with ICP-OES finish (8-Peroxide ICP). Wet sample was transported to the lab without splitting, dried at the Actlabs facility in Windhoek and split afterwards.

Qualified Persons and Data Verification
The independent Qualified Person for the Mineral Resource Estimate, as defined by NI 43-101, is Mr. Sivanesan (Desmond) Subramani (Pri. Sci. Nat - 400184/06), Caracle Creek International Consulting MINRES (Pty) Ltd. (CCIC MINRES), South Africa. Dr. Scott Jobin-Bevans (P.Geo., APGO #0183), a Qualified Person as defined by NI 43-101 and a Director and VP Exploration for White Metal, has reviewed and approved all of the scientific and technical content of this news release.

About White Metal Resources Corp:
White Metal Resources Corp. is a junior exploration company exploring in Canada and southern Africa. The company's two key properties are the Flagship Tower Stock Gold Project in Thunder Bay, Ontario, Canada and the Okohongo Copper-Silver Project in Namibia, Africa. For more information about the Company please visit www.whitemetalres.com .

On behalf of the Board of Directors

" Michael Stares "
President & CEO

For further information contact:
Michael Stares
President & CEO
White Metal Resources Corp.
Phone: +1 (807) 358-2420

Nancy Massicotte
Investor Relations
White Metal Resources Corp.
Phone: +1 (604) 507-3377
TF: +1 (866) 503-3377
ir@whitemetalres.com

THE TSX VENTURE EXCHANGE HAS NOT REVIEWED AND DOES NOT ACCEPT RESPONSIBILITY FOR THE ADEQUACY OR ACCURACY OF THIS RELEASE.

The information contained herein contains "forward-looking statements" within the meaning of applicable securities legislation. Forward-looking statements relate to information that is based on assumptions of management, forecasts of future results, and estimates of amounts not yet determinable. Any statements that express predictions, expectations, beliefs, plans, projections, objectives, assumptions or future events or performance are not statements of historical fact and may be "forward-looking statements."

Forward-looking statements are subject to a variety of risks and uncertainties which could cause actual events or results to differ from those reflected in the forward-looking statements, including, without limitation: risks related to failure to obtain adequate financing on a timely basis and on acceptable terms; risks related to the outcome of legal proceedings; political and regulatory risks associated with mining and exploration; risks related to the maintenance of stock exchange listings; risks related to environmental regulation and liability; the potential for delays in exploration or development activities or the completion of feasibility studies; the uncertainty of profitability; risks and uncertainties relating to the interpretation of drill results, the geology, grade and continuity of mineral deposits; risks related to the inherent uncertainty of production and cost estimates and the potential for unexpected costs and expenses; results of prefeasibility and feasibility studies, and the possibility that future exploration, development or mining results will not be consistent with the Company's expectations; risks related to gold price and other commodity price fluctuations; and other risks and uncertainties related to the Company's prospects, properties and business detailed elsewhere in the Company's disclosure record. Should one or more of these risks and uncertainties materialize, or should underlying assumptions prove incorrect, actual results may vary materially from those described in forward-looking statements. Investors are cautioned against attributing undue certainty to forward-looking statements. These forward-looking statements are made as of the date hereof and the Company does not assume any obligation to update or revise them to reflect new events or circumstances. Actual events or results could differ materially from the Company's expectations or projections.


Primary Logo

News Provided by GlobeNewswire via QuoteMedia

The Conversation (0)
Juggernaut Announces Strategic Investment by Crescat Capital Funds for 28.95% Ownership - Dr. Quinton Hennigh Technical Advisor

Juggernaut Announces Strategic Investment by Crescat Capital Funds for 28.95% Ownership - Dr. Quinton Hennigh Technical Advisor

(TheNewswire)

Juggernaut Exploration Ltd.

Vancouver, British Columbia TheNewswire - April 14 th, 2025 Juggernaut Exploration Ltd. (TSX-V: JUGR) (OTCQB: JUGRF) (FSE: 4JE) (the "Company" or "Juggernaut") is pleased to announce a non-brokered financing of up to $2,650,000. Crescat Capital Funds LLC ("Crescat") has agreed to make a strategic investment representing a 28.95% ownership of the Company post-funding on a partially diluted basis. Juggernaut welcomes this strategic investment from Crescat Capital and technical support from Dr Quinton Hennigh. Juggernaut's Big One Project is garnering strong interest and support from leading institutions and miners globally, confirming the quality of the newly discovered 11 km Highway of Gold surrounding the Eldorado porphyry system on the Big One property. The exciting discovery is in an area of glacial and snowpack abatement next door to the world-class gold-rich porphyry systems at Newmont Mining's Galore Creek. The Big One Property is a discovery with assays up to 79.01 gt gold (2.54 ozt gold) and 3157.89 gt silver (101.5 ozt silver) from over 200 gold-silver-copper rich polymetallic veins up to 8 m wide and striking for up to 500 m that all remain open at surface. The Big One Project covers 33,693 hectares in a world-class geologic terrane with tremendous additional discovery potential in the heart of the Golden Triangle, British Columbia.

News Provided by TheNewsWire via QuoteMedia

Keep reading...Show less
Rising copper bars against a financial graph background.

Copper Price Update: Q1 2025 in Review

The copper price began 2025 on a rebound, spending time above US$5 per pound during Q1 after trading within the US$4 to US$4.50 per pound range for most of 2024's second half.

Starting strong, the red metal climbed from US$3.99 on January 2 to reach US$4.40 by mid-month.

It then eased slightly, ending January at US$4.25. February once again brought momentum as copper climbed steadily to US$4.76 on February 13. However, the price retreated and ended the month at US$4.53.

Keep reading...Show less
World Copper

World Copper Provides Update

World Copper Ltd. ("World Copper" or the "Company"; TSXV: WCU, OTCQB: WCUFF, FSE:7LY0) is pleased to provide an update on the proposed sale of its Zonia Copper project in Arizona ("Zonia" or the "Project") to an arms length third party (the "Purchaser") for CAD $26M in cash (the "Purchase Price"), payable in tranches, as previously announced on February 19, 2025 (the "Proposed Transaction").

The Purchaser is a metals and mining investment manager with two decades of leadership in investing in and developing mining projects. Pursuant to the terms of the binding letter agreement among the Purchaser, World Copper and World Copper's Arizona subsidiary ("Subco"), the Purchaser has approximately 35 days remaining in the 90-day due diligence period, and the Company continues to work diligently with the Purchaser to assist with the completion of the Purchaser's due diligence on the Project.

Keep reading...Show less
Traffic light showing green against a cloudy blue sky.

Celsius Hits Regulatory Milestone at Philippine Copper-Gold Project, Plans Next Steps

Celsius Resources (ASX:CLA) announced that the Philippine Department of Environment and Natural Resources (DENR) has confirmed the financial capability of its local affiliate, Makilala Mining Company.

The confirmation comes with the approval of a binding term sheet between Makilala and Maharlika Investment. It includes a US$76.4 million bridge loan facility to fund the Maalinao-Caigutan-Biyog (MCB) copper-gold project.

The mineral production sharing agreement for MCB is now locked in for 25 years and is renewable for another 25.

Keep reading...Show less
American West Metals

Strategic Partnership secures long-term future for the Storm Copper Project, Canada

Major offtake and funding deal to advance development and exploration activities

American West Metals Limited (American West or the Company) ( ASX: AW1) is pleased to announce that the Company has entered into a binding agreement with global metal trading and advisory group Ocean Partners Holding Ltd (OP or Ocean Partners) which will comprise an equity investment in American West as well as project development funding and copper-silver offtake to OP for the Storm Copper Project.

Keep reading...Show less

Latest Press Releases

Related News

×