Kamoa-Kakula Copper mines 300,000 tonnes of ore in January grading 5.45% copper, including 82,000 tonnes grading 8.80% copper from the high-grade centre of the Kakula Mine

Pre-production ore stockpiles now hold 1.82 million tonnes grading 4.23% copper, containing more than 76,000 tonnes of copper

Fresh underground mining record achieved with 2,869 metres completed in January; more than 32.7 kilometres now complete - 11.6 kilometres ahead of plan

Overall progress of Kamoa-Kakula's first phase, 3.8-Mtpa mining and milling operation now approximately 71% complete; first copper concentrate production remains on track for July 2021

Ivanhoe Mines (TSX: IVN) (OTCQX: IVPAF) Co-Chairs Robert Friedland and Yufeng "Miles" Sun are pleased to announce that underground development at the Kamoa-Kakula Copper Project in the Democratic Republic of Congo (DRC) mined and stockpiled 300,000 tonnes of ore grading 5.45% copper from the Kakula and Kansoko mines in January. The tonnage was 11.5% higher than December, while the copper grade was 1.6% higher.

The 300,000 tonnes mined in January included 231,000 tonnes at an average grade of 6.20% copper, including 82,000 tonnes grading 8.80% copper from the high-grade centre of the Kakula Mine.

The project's pre-production surface stockpiles now contain approximately 1.82 million tonnes of high-grade and medium-grade ore at an estimated blended grade of 4.23% copper. Contained copper in the stockpiles increased by approximately 16,000 tonnes in January - a 25.9% increase over December's production reflecting increased mining activity in the ultra-high-grade centre of the Kakula Deposit - to a cumulative total of more than 76,000 tonnes (the current copper price is approximately US$7,940 a tonne).

Kamoa-Kakula is on track to have approximately three million tonnes of high-grade and medium-grade ore stockpiled on surface, holding more than 125,000 tonnes of contained copper, prior to the planned start of processing in July 2021.

"In the mining business, grade is king," said Mr. Friedland. "And the remarkable grade of the ore coming from Kakula is unprecedented for a major mechanized copper mine of this scale. We are just five months away from scheduled first production, which will mark the next step in the evolution of Ivanhoe Mines into a leading, diversified mining company with a development and exploration portfolio of high-value, critical green metals."

Mr. Friedland and Mr. Sun also congratulated the project team for establishing yet another new monthly record for underground mine development in January with a total of 2,869 metres of advancement.

"A very strong operational and safety performance by our mining teams in January, and overall a terrific start to 2021," said Mr. Friedland. "We are immensely proud of the more than 6,000 colleagues on site who are delivering this exceptional project on time and on budget. As we rapidly approach initial production, the project is busy recruiting and training the team that will operate the brand new concentrator plant, creating hundreds of additional permanent, well-paying jobs for local Congolese women and men."

Underground mine development remains well ahead of schedule, providing the confidence to push forward with Kamoa-Kakula's Phase 2 construction

January's record-setting advancement brings total underground development to approximately 32.7 kilometres - around 11.6 kilometres ahead of schedule. The monthly underground development in January was comprised of 2,544 metres at the Kakula Mine and 325 metres at the Kansoko Mine.

Drift-and-fill stoping operations recently commenced at the Kakula Mine, with more than 66% of January's ore production coming from stoping operations and the remaining coming from mine development activities. Stoping is a highly-productive mining method of extracting underground ore, leaving behind an open space known as a stope.

Mark Farren, Kamoa Copper's CEO, commented: "The achievement of 300,000 tonnes mined in January is significant as Kamoa-Kakula is fast approaching the mining rate needed to sustain the project's Phase 1 concentrator plant."

"It will be important to balance mining volumes and surface stockpiles to meet the requirements of both the Phase 1 and Phase 2 concentrators. We now have nearly two million tonnes of medium- and high-grade ore on surface stockpiles, which should grow to approximately three million tonnes ahead of the scheduled start-up of the concentrator in July, significantly minimizing the ramp-up risk as well as streamlining the commissioning phase," he continued.

"The large surface ore stockpiles will allow Kamoa-Kakula to maximize throughput once the Phase 1 concentrator is commissioned. Based on our projected mining rates over the next year and a half, we are confident that we also will have more than sufficient stockpiles ahead of the Phase 2 concentrator commissioning," Mr. Farren added.

Kakula's combined medium-grade and high-grade ore mined in January was approximately 274,000 tonnes at an average grade of 5.56% copper, including 82,000 tonnes grading 8.80% copper from the +8% copper zone in the centre of the orebody. Mining crews at Kakula are primarily focused on developing the drift-and-fill mining blocks in this high-grade centre. Opening up of the mining footprint for these high grade, drift-and-fill mining areas requires development work in areas of low-, medium- and high-grade ore, and is designed to coincide with the start-up of the processing plant in July. This will allow crews to deliver significant tonnage of high-grade ore directly from Kakula's underground workings to the processing plant.

Kansoko's combined medium-grade and high-grade ore mined in January was approximately 26,000 tonnes at an average grade of 4.31% copper. Kansoko's ore grade increased by 73% in January, compared to December. Kansoko is being developed by training crews and will be a supplemental source of ore for Phase 2 of the project's development when the Kakula concentrator processing capacity doubles to 7.6 million tonnes per annum (Mtpa) − currently planned to be commissioned in Q3 2022.

Miners drilling a 10-metre-high by 7.5-metre-wide drift near the centre of the Kakula Mine. The average grade of ore mined in this area is 8.80% copper.

Cannot view this image? Visit: https://orders.newsfilecorp.com/files/3396/73275_a9cc339924364b85_002.jpg

To view an enhanced version of this graphic, please visit:
https://orders.newsfilecorp.com/files/3396/73275_a9cc339924364b85_002full.jpg

David Nkulu, Safety Officer, conducting a mine safety drill at the Kansoko Mine's underground refuge centre.

Cannot view this image? Visit: https://orders.newsfilecorp.com/files/3396/73275_a9cc339924364b85_003.jpg

To view an enhanced version of this graphic, please visit:
https://orders.newsfilecorp.com/files/3396/73275_a9cc339924364b85_003full.jpg

Phase 1 copper production from the Kakula Mine is scheduled to begin in July 2021. Kakula is projected to be the world's highest-grade major copper mine, with an initial mining rate of 3.8 Mtpa at an estimated average feed grade of more than 6.0% copper at first, ramping up to 7.6 Mtpa in Q3 2020. Phases 1 and 2 combined are forecast to produce approximately 400,000 tonnes of copper per year. Based on independent benchmarking, the project's phased expansion scenario to 19 Mtpa would position Kamoa-Kakula as the world's second largest copper mining complex, with peak annual copper production of more than 800,000 tonnes.

A 2020 independent audit of Kamoa-Kakula's greenhouse gas intensity metrics performed by Hatch Ltd. of Mississauga, Canada, confirmed that the project will be among the world's lowest greenhouse gas emitters per unit of copper produced.

The Kamoa-Kakula Copper Project is a joint venture between Ivanhoe Mines (39.6%), Zijin Mining Group (39.6%), Crystal River Global Limited (0.8%) and the Government of the Democratic Republic of Congo (20%).

January's ore production was 11.5% higher than December, with monthly copper grade increasing from 5.36% to 5.45%; pre-production surface ore stockpiles now total approximately 1.82 million tonnes grading 4.23% copper

Chart 1: Cumulative tonnes and grade of pre-production ore stockpiles at the Kakula and Kansoko mines - May 2020 to January 2021.

Cannot view this image? Visit: https://orders.newsfilecorp.com/files/3396/73275_a9cc339924364b85_004.jpg

To view an enhanced version of Chart 1, please visit:
https://orders.newsfilecorp.com/files/3396/73275_a9cc339924364b85_004full.jpg

Chart 2: Growth in contained copper in pre-production ore stockpiles at the Kakula and Kansoko mines - May 2020 to January 2021.

Cannot view this image? Visit: https://orders.newsfilecorp.com/files/3396/73275_a9cc339924364b85_005.jpg

To view an enhanced version of Chart 2, please visit:
https://orders.newsfilecorp.com/files/3396/73275_a9cc339924364b85_005full.jpg

Chart 3: Projected growth in contained copper in the pre-production stockpiles at the Kakula and Kansoko mines up to July 2021. Dotted lines denote projections based on the 2020 pre-feasibility study.

Cannot view this image? Visit: https://orders.newsfilecorp.com/files/3396/73275_a9cc339924364b85_006.jpg

To view an enhanced version of Chart 3, please visit:
https://orders.newsfilecorp.com/files/3396/73275_a9cc339924364b85_006full.jpg

The ore being mined from the northern portion of the Kakula Mine is transported to surface via the conveyor system and placed on a blended surface stockpile that now contains approximately 1.07 million tonnes grading an estimated 4.52% copper.

Additional pre-production ore stockpiles are located at the Kakula southern decline (approximately 243,000 tonnes of high-grade ore grading 5.85% copper and 303,000 tonnes of medium-grade ore grading 2.79% copper) and the Kansoko decline (approximately 12,000 tonnes of high-grade ore grading 6.19% copper and 192,000 tonnes of medium-grade ore grading 2.77% copper).

Kakula's main pre-production stockpiles at the northern declines. The blended stockpiles currently contain approximately 1.07 million tonnes grading 4.52% copper.

Cannot view this image? Visit: https://orders.newsfilecorp.com/files/3396/73275_a9cc339924364b85_007.jpg

To view an enhanced version of this graphic, please visit:
https://orders.newsfilecorp.com/files/3396/73275_a9cc339924364b85_007full.jpg

Kakula southern decline ore stockpiles containing approximately 243,000 tonnes of high-grade ore grading 5.85% copper, and 303,000 tonnes of medium-grade ore grading 2.79% copper.

Cannot view this image? Visit: https://orders.newsfilecorp.com/files/3396/73275_a9cc339924364b85_008.jpg

To view an enhanced version of this graphic, please visit:
https://orders.newsfilecorp.com/files/3396/73275_a9cc339924364b85_008full.jpg

Kansoko decline ore stockpiles containing 204,000 tonnes grading 2.97% copper, including 12,000 tonnes of high-grade ore grading 6.19% copper. 

Cannot view this image? Visit: https://orders.newsfilecorp.com/files/3396/73275_a9cc339924364b85_009.jpg

To view an enhanced version of this graphic, please visit:
https://orders.newsfilecorp.com/files/3396/73275_a9cc339924364b85_009full.jpg

Figure 1: The 13.3-kilometre-long Kakula Deposit overlain on southern Manhattan Island to provide a sense of the scale of the deposit.

Cannot view this image? Visit: https://orders.newsfilecorp.com/files/3396/73275_a9cc339924364b85_010.jpg

To view an enhanced version of Figure 1, please visit:
https://orders.newsfilecorp.com/files/3396/73275_a9cc339924364b85_010full.jpg

Figure 2: Underground development completed at Kakula Mine to January 31, 2021 (in black).

Cannot view this image? Visit: https://orders.newsfilecorp.com/files/3396/73275_a9cc339924364b85_012.jpg

To view an enhanced version of Figure 2, please visit:
https://orders.newsfilecorp.com/files/3396/73275_a9cc339924364b85_012full.jpg

Construction of the initial 3.8-Mtpa concentrator plant and other surface infrastructure on schedule; earthworks and civil works progressing well for the second 3.8-Mtpa concentrator plant

Overall progress of Kamoa-Kakula's first phase, 3.8-Mtpa mining and milling operation (covering mine infrastructure, concentrator plant and surface infrastructure) now is approximately 71% complete, up from 68% last month. Overall construction of the project's first phase, 3.8-Mtpa concentrator plant and associated facilities is advancing rapidly and is approximately 43% complete, up from 41% last month. The concentrator plant remains on track to be mechanically complete in Q2 2021, with first copper concentrate production scheduled for July 2021.

Kamoa-Kakula's first phase, 3.8-Mtpa concentrator plant, with the main 220-kilovolt electrical substation in the background.

Cannot view this image? Visit: https://orders.newsfilecorp.com/files/3396/73275_a9cc339924364b85_013.jpg

To view an enhanced version of this graphic, please visit:
https://orders.newsfilecorp.com/files/3396/73275_a9cc339924364b85_013full.jpg

Watch a short fly-over video of the construction of the concentrator plant and other surface infrastructure: https://vimeo.com/506201742/c2965a1fcc

Civil works for the first concentrator plant effectively is complete and the civil contractor now is focusing on the Phase 2 concentrator plant, the high-pressure-grinding-rolls (HPGR) stockpile and milling areas.

Delivery of equipment for the first concentrator plant is nearing completion with more than 2,260 truckloads of equipment - including all structural steel, platework, piping and electrical cable - now on site. The sand filter plant and the last shipments of switchgear are scheduled to arrive in February and March 2021, respectively.

Structural steel erection and platework installation for the first concentrator plant is nearing completion, with only 172 tonnes of structural steel still to be erected (of a total of 4,882 tonnes) and 121 tonnes of platework (of a total of 863 tonnes). Mechanical installation is 68% complete. Piping fabrication and delivery is complete and installation is nearing 50% completion. A total of 83 kilometres of piping will be installed.

All plant areas for the first concentrator have been handed over to the electrical, control and instrumentation (EC&I) contractor for electrical installation. EC&I installation is the last activity before construction completion and subsequent commissioning. Installation of cable racking is complete in most areas and cable installation is well advanced with more than 105,000 metres of copper cable installed out of a total of 207,000 metres (207 kilometres). The installation of instrumentation has started and the energizing of the concentrator plant with medium-voltage power is scheduled for the end of March 2021.

Plumbers Daniel Mbayo (foreground) and Chronos Ilunga (background) installing piping at Kakula's Phase 1 concentrator plant.

Cannot view this image? Visit: https://orders.newsfilecorp.com/files/3396/73275_a9cc339924364b85_014.jpg

To view an enhanced version of this graphic, please visit:
https://orders.newsfilecorp.com/files/3396/73275_a9cc339924364b85_014full.jpg

Steel erection and equipment installation for Kakula's first phase, backfill paste plant effectively is complete with electrical installation well advanced. The backfill plant is scheduled to be complete well before paste backfill is required for mining operations.

The backfill plant will be used to mix tailings from the processing plant with cement to produce paste backfill. The backfill will be pumped back into the mine and used to help support mined-out areas. Approximately one half of the mine's tailings will be sent back underground, significantly reducing the surface tailings storage.

Construction of the tailings storage facility is progressing well and is scheduled to be completed well ahead of the required date. Installation of the three tailings lines and the tailings-return water line is nearing completion with 24 kilometres (of a total of 25 kilometres) complete.

Construction of the second 3.8-Mtpa concentrator plant is progressing well with the current focus on earthworks and civils. Civils works on the lower base of the ball mills and the HPGR stockpile is underway with a total of 1,720cubic metres of concrete already poured (of a Phase 2 total of 14,000cubic metres). Bulk earthworks is approximately 37% complete. With orders for all the long lead items of equipment for the Phase 2 concentrator placed in September 2020, procurement activities have focused on the remainder of the plant equipment. The contract for structural steel supply has been placed.

Work on the concrete foundations for Kakula's Phase 2 ball mills is making excellent progress, while construction of Kakula's Phase 1 ball mills (background) is nearing completion.

Cannot view this image? Visit: https://orders.newsfilecorp.com/files/3396/73275_a9cc339924364b85_015.jpg

To view an enhanced version of this graphic, please visit:
https://orders.newsfilecorp.com/files/3396/73275_a9cc339924364b85_015full.jpg

Civil works for the Phase 2 flotation cells foundations (bottom of picture).

Cannot view this image? Visit: https://orders.newsfilecorp.com/files/3396/73275_a9cc339924364b85_016.jpg

To view an enhanced version of this graphic, please visit:
https://orders.newsfilecorp.com/files/3396/73275_a9cc339924364b85_016full.jpg

Ongoing construction of Kamoa-Kakula's tailings storage facility.

Cannot view this image? Visit: https://orders.newsfilecorp.com/files/3396/73275_a9cc339924364b85_017.jpg

To view an enhanced version of this graphic, please visit:
https://orders.newsfilecorp.com/files/3396/73275_a9cc339924364b85_017full.jpg

A 3D overhead illustration of the finished Phase 1, 3.8-Mtpa concentrator plant. The picture below shows the current construction progress.

Cannot view this image? Visit: https://orders.newsfilecorp.com/files/3396/73275_a9cc339924364b85_018.jpg

To view an enhanced version of this graphic, please visit:
https://orders.newsfilecorp.com/files/3396/73275_a9cc339924364b85_018full.jpg

A 3D illustration of Kakula's initial 3.8-Mtpa concentrator plant, with the recently-initiated Phase 2, 3.8-Mtpa processing plant shown in magenta. The picture below shows the current construction progress.

Cannot view this image? Visit: https://orders.newsfilecorp.com/files/3396/73275_a9cc339924364b85_019.jpg

To view an enhanced version of this graphic, please visit:
https://orders.newsfilecorp.com/files/3396/73275_a9cc339924364b85_019full.jpg

A 3D illustration of Kakula's first phase, finished backfill plant, with the current construction and the initial 3.8-Mtpa concentrator plant in the background shown immediately below.

Cannot view this image? Visit: https://orders.newsfilecorp.com/files/3396/73275_a9cc339924364b85_020.jpg

To view an enhanced version of this graphic, please visit:
https://orders.newsfilecorp.com/files/3396/73275_a9cc339924364b85_020full.jpg

Watch a short fly-over video of construction of the backfill plant: https://vimeo.com/506202840/1f2a57c9df

Watch a time-lapse video of the installation of a disk filter at the backfill plant:https://vimeo.com/506202587/1e4c5c01ff

Advanced, detailed discussions for the marketing of Kakula's copper concentrates

Kamoa-Kakula is in advanced, detailed discussions with a number of parties with respect to the sale of its copper concentrates. Kakula is expected to produce an extremely high-grade and clean copper concentrate (containing over 55% copper) that will be highly coveted by copper smelters around the world. Metallurgical test work indicates that the Kakula concentrates contain extremely low arsenic levels by world standards - approximately 0.01%.

Kamoa-Kakula now connected to 220-kV national electrical grid; the first of six turbines at the refurbished Mwadingusha hydropower plant now synchronized to the national electrical grid, providing clean, renewable hydropower

In December 2020, the 35-kilometre-long double circuit 220-kilovolt (kV) power line feeding into Kamoa-Kakula was connected to the national electrical grid through the New Western Dispatch (NRO) substation in Kolwezi. Kamoa-Kakula's main 220-kV substation is nearing completion and is expected to be energized by the end of March.

Electricians installing electrical cables at Kakula's main 220-kV substation that will provide power from the national grid to the entire Kamoa-Kakula project.

Cannot view this image? Visit: https://orders.newsfilecorp.com/files/3396/73275_a9cc339924364b85_021.jpg

To view an enhanced version of this graphic, please visit:
https://orders.newsfilecorp.com/files/3396/73275_a9cc339924364b85_021full.jpg

Watch a short fly-over video of the construction the main electrical substation: https://vimeo.com/506203269/c2d24785c2

Ivanhoe Mines Energy DRC also announced that the first of six new turbines at the Mwadingusha hydropower plant was synchronized to the national electrical grid in December 2020. The commissioning of the hydropower plant's remaining five generating units, in sequence, is in progress. This will ensure that Kamoa-Kakula's power requirements are met ahead of the commissioning of the concentrator plant.

The fully-refurbished Mwadingusha hydropower plant now is expected to deliver approximately 78 megawatts of power to the national electrical grid.

Ivanhoe Mines Energy DRC achieved a significant milestone in December when the first of six turbines at the Mwadingusha hydropower plant began delivering clean, hydropower to the national electrical grid.

Cannot view this image? Visit: https://orders.newsfilecorp.com/files/3396/73275_a9cc339924364b85_022.jpg

To view an enhanced version of this graphic, please visit:
https://orders.newsfilecorp.com/files/3396/73275_a9cc339924364b85_022full.jpg

Refurbished and upgraded generating units 1 and 2 at the Mwadingusha hydropower plant. Unit 1 is operational and delivering clean, hydropower to the national electrical grid, while number 2 will begin commissioning shortly.

Cannot view this image? Visit: https://orders.newsfilecorp.com/files/3396/73275_a9cc339924364b85_023.jpg

To view an enhanced version of this graphic, please visit:
https://orders.newsfilecorp.com/files/3396/73275_a9cc339924364b85_023full.jpg

COVID-19 prevention initiatives continue to focus on risk mitigation

Kamoa-Kakula's prevention measures remain strictly enforced, with further prevention being the focus while the world responds to the latest COVID-19 strains. Rigorous testing, physical distancing, wearing of face masks, frequent hand washing and contact-tracing measures still are in place to protect the safety and health of the workforce and community members.

The project has a well-established COVID-19 isolation facility at the Kamoa Camp. Suspected cases and symptomatic patients are moved to this facility, where they are isolated, tested and treated. Once patients have recovered and are deemed no longer infectious, they can return to work only after an additional quarantine period determined by the project's medical staff.

Kamoa-Kakula has successfully sourced the latest COVID-19 rapid diagnostic tests (RDT) that test for antigens (the presence of viral particles). The tests are being used by the medical team at Kamoa-Kakula to screen all site arrivals and travellers. Test results are received within an average of 20 minutes, which further enhances the preventative measures already in place.

As the pandemic evolves, the medical team at Kamoa-Kakula continues to review and update its risk mitigation protocols. The project's preventative measures are at the highest international standards, and should there be a case internally, the risk of spreading or cross-contamination is considered to be very low.

Mark Farren, Kamoa Copper CEO (centre), visiting the Kamoa-Kakula Sustainable Livelihoods sewing project. In addition to sewing Kamoa Copper safety uniforms, face masks also are produced for mine workers and local community members as part of the project's COVID-19 safety initiatives.

Cannot view this image? Visit: https://orders.newsfilecorp.com/files/3396/73275_a9cc339924364b85_024.jpg

To view an enhanced version of this graphic, please visit:
https://orders.newsfilecorp.com/files/3396/73275_a9cc339924364b85_024full.jpg

Members of Kamoa's senior management, sustainability and community development teams visit a local maize farm. Left to right: Christos Ioannou, Senior Enterprise Development; Paul Kabengele, Sustainable Livelihoods Advisor; Mark Farren, Kamoa Copper CEO; Chief Musokantanda Kafweku Sabuni; Dr. Guy Muswil, Head of Sustainability; Brett Watson, HSE Managerial Leader; and Tuhan Steyn, Head of Biodiversity.

Cannot view this image? Visit: https://orders.newsfilecorp.com/files/3396/73275_a9cc339924364b85_025.jpg

To view an enhanced version of this graphic, please visit:
https://orders.newsfilecorp.com/files/3396/73275_a9cc339924364b85_025full.jpg

Alain Mukoj (centre) of Kamoa Copper's sustainability team overseeing a pineapple crop with farmers from the local community of Mupenda.

Cannot view this image? Visit: https://orders.newsfilecorp.com/files/3396/73275_a9cc339924364b85_026.jpg

To view an enhanced version of this graphic, please visit:
https://orders.newsfilecorp.com/files/3396/73275_a9cc339924364b85_026full.jpg

Qualified Persons

Disclosures of a scientific or technical nature regarding development scenarios at the Kamoa-Kakula Project in this news release have been reviewed and approved by Steve Amos, who is considered, by virtue of his education, experience and professional association, a Qualified Person under the terms of NI 43-101. Mr. Amos is not considered independent under NI 43-101 as he is the Head of the Kamoa Project. Mr. Amos has verified the technical data disclosed in this news release.

Other disclosures of a scientific or technical nature regarding the stockpiles in this news release have been reviewed and approved by George Gilchrist, who is considered, by virtue of his education, experience and professional association, a Qualified Person under the terms of NI 43-101. Mr. Gilchrist is not considered independent under NI 43-101 as he is the Vice President, Resources of Ivanhoe Mines. Mr. Gilchrist has verified the other technical data disclosed in this news release.

The stockpile grade estimates contained in this release are based upon bulk ore sampling from earlier underground headings, and vertical channel sample profiles from recent development. Bulk ore sampling was done on each heading every second blast and three 5-kilogram samples were taken. Since the beginning of October 2020, channel sample profiles are the primary data informing the stockpile grade estimates. These are cut approximately 15 metres apart in 1-metre vertical increments across the full vertical exposure using a handheld grinder, with a 100-to-150-gram sample collected. The samples are pulverized at the project's onsite laboratory and analyzed using a portable XRF (pXRF) instrument. Kamoa Copper has routinely analyzed its exploration drill core for copper using pXRF, in addition to analysis at a commercial laboratory using four acid digest and ICP-OES. This data has demonstrated that pXRF results can be relied upon for grade control and run-of-mine sampling.

Ivanhoe has prepared an independent, NI 43-101-compliant technical report for the Kamoa-Kakula Project, which is available on the company's website and under the company's SEDAR profile at www.sedar.com:

  • Kamoa-Kakula Integrated Development Plan 2020 dated October 13, 2020, prepared by OreWin Pty Ltd., China Nerin Engineering Co., Ltd., DRA Global, Epoch Resources, Golder Associates Africa, KGHM Cuprum R&D Centre Ltd., Outotec Oyj, Paterson and Cooke, Stantec Consulting International LLC, SRK Consulting Inc., and Wood plc.

The technical report includes relevant information regarding the assumptions, parameters and methods of the mineral resource estimates on the Kamoa-Kakula Project cited in this news release, as well as information regarding data verification, exploration procedures and other matters relevant to the scientific and technical disclosure contained in this news release.

About Ivanhoe Mines

Ivanhoe Mines is a Canadian mining company focused on advancing its three principal joint-venture projects in Southern Africa: the development of major new, mechanized, underground mines at the Kamoa-Kakula copper discoveries in the DRC and at the Platreef palladium-platinum-nickel-copper-rhodium-gold discovery in South Africa; and the extensive redevelopment and upgrading of the historic Kipushi zinc-copper-germanium-silver mine, also in the DRC. Kamoa-Kakula is expected to begin producing copper in July 2021 and, through phased expansions, is positioned to become one of the world's largest copper producers. Kamoa-Kakula and Kipushi will be powered by clean, renewable hydro-generated electricity and will be among the world's lowest greenhouse gas emitters per unit of metal produced. Ivanhoe also is exploring for new copper discoveries on its wholly-owned Western Foreland exploration licences in the DRC, near the Kamoa-Kakula Project.

Information contacts

Investors: Bill Trenaman +1.604.331.9834 / Media: Matthew Keevil +1.604.558.1034

Forward-looking statements

Certain statements in this release constitute "forward-looking statements" or "forward-looking information" within the meaning of applicable securities laws. Such statements and information involve known and unknown risks, uncertainties and other factors that may cause the actual results, performance or achievements of the company, its projects, or industry results, to be materially different from any future results, performance or achievements expressed or implied by such forward-looking statements or information. Such statements can be identified by the use of words such as "may", "would", "could", "will", "intend", "expect", "believe", "plan", "anticipate", "estimate", "scheduled", "forecast", "predict" and other similar terminology, or state that certain actions, events or results "may", "could", "would", "might" or "will" be taken, occur or be achieved. These statements reflect the company's current expectations regarding future events, performance and results and speak only as of the date of this release.

Such statements include without limitation, the timing and results of: (i) statements regarding the Kamoa-Kakula Project is on track to have approximately three million tonnes of high-grade and medium-grade ore stockpiled on surface, containing more than 125,000 tonnes of copper, prior to the planned start of production in July 2021; (ii) statements regarding the Phase 1 concentrator plant remains on track to be mechanically complete in Q2 2021, with first copper concentrate production scheduled for July 202; (iii) statements that the risk of the risk of spreading or cross-contamination of COVID-19 at the Kamoa-Kakula Project is considered to be very low; (iv) statements regarding the expectation that Phase 2 of the project's development when the Kakula concentrator processing capacity doubles to 7.6 Mtpa is to be commissioned in Q3 2022; (v) statements regarding Kakula is projected to be the world's highest-grade major copper mine, with an initial mining rate of 3.8 Mtpa at an estimated average feed grade of more than 6.0% copper over the first five years of operation; (vi) statements regarding Phases 1 and 2 combined are forecast to produce approximately 400,000 tonnes of copper per year; (vii) statements regarding based on independent benchmarking, the project's phased expansion scenario to 19 Mtpa would position Kamoa-Kakula as the world's second largest copper mining complex, with peak annual copper production of more than 800,000 tonnes; (viii) statements regarding Kamoa-Kakula will be among the world's lowest greenhouse gas emitters per unit of copper produced; (ix) statements regarding Kamoa-Kakula should have more than sufficient stockpiles ahead of the Phase 2 concentrator commissioning; (x) statements regarding approximately one half of the mine's tailings will be sent back underground; (xi) statements regarding Kakula is expected to produce an extremely high grade and clean copper concentrate (containing over 55% copper and extremely low arsenic levels by world standards - approximately 0.01%) that will be highly coveted by copper smelters around the world; (xii) statements regarding the fully-refurbished Mwadingusha hydropower plant is expected to deliver approximately 78 megawatts of power to the national grid; and (xiii) statements regarding energizing of Kakula's main electrical substation and the concentrator plant by the end of March 2021

As well, all of the results of the Kakula definitive feasibility study, the Kakula-Kansoko pre-feasibility study and the Kamoa-Kakula preliminary economic assessment, constitute forward-looking statements or information, and include future estimates of internal rates of return, net present value, future production, estimates of cash cost, proposed mining plans and methods, mine life estimates, cash flow forecasts, metal recoveries, estimates of capital and operating costs and the size and timing of phased development of the projects. Furthermore, with respect to this specific forward-looking information concerning the development of the Kamoa-Kakula Project, the company has based its assumptions and analysis on certain factors that are inherently uncertain. Uncertainties include: (i) the adequacy of infrastructure; (ii) geological characteristics; (iii) metallurgical characteristics of the mineralization; (iv) the ability to develop adequate processing capacity; (v) the price of copper; (vi) the availability of equipment and facilities necessary to complete development; (vii) the cost of consumables and mining and processing equipment; (viii) unforeseen technological and engineering problems; (ix) accidents or acts of sabotage or terrorism; (x) currency fluctuations; (xi) changes in regulations; (xii) the compliance by joint venture partners with terms of agreements; (xiii) the availability and productivity of skilled labour; (xiv) the regulation of the mining industry by various governmental agencies; (xv) the ability to raise sufficient capital to develop such projects; (xvi) changes in project scope or design; and (xvii) political factors.

Forward-looking statements and information involve significant risks and uncertainties, should not be read as guarantees of future performance or results and will not necessarily be accurate indicators of whether or not such results will be achieved. A number of factors could cause actual results to differ materially from the results discussed in the forward-looking statements or information, including, but not limited to, the factors discussed below and under "Risk Factors", and elsewhere in this release, as well as unexpected changes in laws, rules or regulations, or their enforcement by applicable authorities; the failure of parties to contracts with the company to perform as agreed; social or labour unrest; changes in commodity prices; and the failure of exploration programs or studies to deliver anticipated results or results that would justify and support continued exploration, studies, development or operations.

Although the forward-looking statements contained in this release are based upon what management of the company believes are reasonable assumptions, the company cannot assure investors that actual results will be consistent with these forward-looking statements. These forward-looking statements are made as of the date of this release and are expressly qualified in their entirety by this cautionary statement. Subject to applicable securities laws, the company does not assume any obligation to update or revise the forward-looking statements contained herein to reflect events or circumstances occurring after the date of this release.

The company's actual results could differ materially from those anticipated in these forward-looking statements as a result of the factors set forth below in the "Risk Factors" section in the company's Q3 2020 MD&A and its current annual information form.

To view the source version of this press release, please visit https://www.newsfilecorp.com/release/73275

News Provided by Newsfile via QuoteMedia

The Conversation (0)
Lobo Tiggre, copper bars.

Lobo Tiggre: Copper is My Highest-Confidence Trade for 2025 — Here's Why

Lobo Tiggre, CEO of IndependentSpeculator.com, gave the Investing News Network his updated thoughts on the US economy, as well as his outlook for gold, silver and uranium in 2025.

However, he said his highest-confidence trade for next year is copper.

"I think that it's easier to see — and highly likely to see — copper moving higher next year," Tiggre explained.

Keep reading...Show less
Large chunk of copper.

29Metals Shares Feasibility Study and Final Investment Decision for Gossan Valley Project

29Metals (ASX:29M) has announced a feasibility study and final investment decision for the Gossan Valley project at its Golden Grove volcanic-hosted massive sulphide mine in Western Australia.

The feasibility study is an update to the 2022 version of the document. It outlines production of 4,000 tonnes of copper and 20,000 tonnes of zinc annually at Gossan Valley over an initial mine life of seven years.

CEO James Palmer said the development of Gossan Valley is the "next logical development option" when it comes to moving forward at Golden Grove, which was first discovered in 1971.

Keep reading...Show less
Somerset Minerals Logo

Acquisition of High-Grade Copper Project Adjacent to White Cliff Minerals

Somerset Minerals Ltd (“Somerset” or the “Company”) (ASX:SMM) is pleased to advise that it has entered into a conditional agreement to acquire 100% of the issued capital of Sentinel Resources Pty Ltd (“Sentinel”), which, through its local subsidiary, holds the Coppermine Project (the “Project”) in Nunavut, Canada.

Importantly, the Coppermine Project hosts 1,055 km2 of the prospective Copper Creek Formation basalts, and is interpreted to include the strike extensions to White Cliff’s high priory targets of Vision, Stark, Thor and Rocket (Figure 2 & 3), with the prospectivity of the wider project area also supported by extensive surface sampling and historic exploration (Table 1). Importantly, Somerset holds the ground entirely around and along strike from White Cliff’s recently acquired Danvers prospect which contains a non-JORC or NI 43-101 resource of 4.16Mt @ 2.96% Cu.

Keep reading...Show less
US$100 bills.

Lundin Mining to Divest Neves-Corvo and Zinkgruvan Operations for US$1.52 Billion

Lundin Mining (TSX:LUN,OTC Pink:LUNMF) has entered a definitive agreement to sell its Neves-Corvo operation in Portugal and Zinkgruvan operation in Sweden to Boliden (STO:BOL) for up to US$1.52 billion.

The sale, announced by the company on Monday (December 9), will see Boliden acquire full ownership of Somincor, the company operating Neves-Corvo, as well as Zinkgruvan Mining Aktiebolag and its associated entities.

Lundin expects to receive upfront cash consideration of US$1.37 billion at closing, based on financial conditions as of August 31, 2024. Interest will accrue at 5 percent annually until the closing date.

Keep reading...Show less

Lundin Mining Announces Sale of Neves-Corvo and Zinkgruvan for Total Consideration of up to $1.52 Billion

Lundin Mining logo (CNW Group/Lundin Mining Corporation)

TSX: LUN) (Nasdaq Stockholm: LUMI) Lundin Mining Corporation ("Lundin Mining" or the "Company") announces today it has signed a definitive agreement to sell its Neves-Corvo operation in Portugal and Zinkgruvan operation in Sweden to Boliden AB (OM: BOL) ("Boliden") for up to $1.52 billion in total consideration (the "Transaction"). Unless otherwise stated, all numbers are presented in United States dollars.

News Provided by Canada Newswire via QuoteMedia

Keep reading...Show less
Business handshake.

Rio Tinto and Sumitomo Partner to Advance Winu Copper-Gold Project

Rio Tinto (ASX:RIO,NYSE:RIO,LSE:RIO) has signed a term sheet with Sumitomo Metal Mining (TSE:5713) for a joint venture to advance the Winu copper-gold project in Western Australia.

The partnership, announced on Wednesday (December 4), seeks to develop both companies’ exploration initiatives.

Sumitomo will acquire a 30 percent equity stake in the Winu project for US$399 million, including an initial payment of US$195 million and US$204 million in deferred considerations tied to project milestones and other conditions.

Keep reading...Show less

Latest Press Releases

Related News

×