Atico Produces 3.75 Million Pounds of Cu and 2,724 Ounces of Au in Q3 2022

Atico Produces 3.75 Million Pounds of Cu and 2,724 Ounces of Au in Q3 2022

Atico Mining Corporation (the "Company" or "Atico") (TSX.V: ATY | OTCQX: ATCMF) announces its operating results for the three months ended September 30, 2022 from its El Roble mine. Production for the quarter totaled 3.75 million pounds of copper and 2,724 ounces of gold in concentrates, a decrease of 15% for copper and an increase of 8% for gold over the same period in 2021.

"Production for the period was slightly below budget due to extended maintenance of the SAG mill system. This was mostly driven by unusually long shipping delays of spare parts that were required to perform the maintenance. Production rate improved towards the end of the quarter as steady state-run rate was again achieved." said Fernando E. Ganoza, CEO. "For the fourth quarter, we continue looking for opportunities to improve metal production as we stay on track to deliver our 2022 production guidance. At the same time, we are aggressively drill testing in proximity to our mine and on the large regional land package."

Third Quarter Operational Highlights

  • Production of 3.75 million pounds of copper contained in concentrates; a decrease of 15% over Q3 2021.
  • Production of 2,724 ounces of gold contained in concentrates; a decrease of 9% over Q3 2021.
  • Average processed tonnes per day of 786, a decrease of 15% over Q3 2021.
  • Copper head grade of 3.12%, an increase of 11% over Q3 2021.
  • Gold head grade of 2.28 grams per tonne; an increase of 13% over Q3 2021.
  • Copper and gold recovery of 91.5% and 62%; no significant change for copper and an increase of 4% for gold, respectively over Q3 2021.

Third Quarter Operational Review

Overall production was slightly below the Company budget for the third quarter. The decrease in both copper and gold production is mainly explained by the decrease in processed tonnes, partially offset by improved head grades for the period. Copper recovery was in line with the Company budget while the gold recovery showed a slight improvement over the same period last year. During the quarter the Company delivered two concentrate shipments as the operation remains on track to deliver on set guidance throughout the remainder of the year.

Third Quarter Operational Details

Q3 2022 Q3 2021 % Change
Production (Contained in Concentrates)
Copper (000s pounds) 3,753 4,442 -15 %
Gold (ounces) 2,724 2,978 -9 %
Mine
Tonnes of ore mined 66,245 76,276 -13 %
Mill
Tonnes processed 59,689 77,816 -23 %
Tonnes processed per day 786 919 -15 %
Copper grade (%) 3.12 2.80 11 %
Gold grade (g/t) 2.28 2.02 13 %
Recoveries
Copper (%) 91.5 92.6 Nil %
Gold (%) 62.0 58.8 5 %
Concentrates
Copper and Gold Concentrates (dmt) 9,048 10,704 -15 %
Payable copper produced (000s lbs) 3,565 4,220 -15 %

Note: Metal production figures are subject to adjustments based on final settlement.


Concentrate Inventory

The number of shipments the Company can export in any given quarter depends on several variables some of which the Company does not control, hence there may be an inherent variability in tonnes shipped quarter to quarter.

Q3 2022
Amounts in dry metric tonnes
Opening inventory 13,458
Production 9,048
Sales -14,219
Number of shipments 2
Adjustments -267
Closing inventory 8,020
Note: Concentrate figures are subject to adjustments based on final surveys and final settlement of sales.


El Roble Mine

The El Roble mine is a high grade, underground copper and gold mine with nominal processing plant capacity of 1,000 tonnes per day, located in the Department of Choco in Colombia. Its commercial product is a copper-gold concentrate.

Since obtaining control of the mine on November 22, 2013, Atico has upgraded the operation from a historical nominal capacity of 400 tonnes per day.

El Roble has Proven and Probable reserves of 1.00 million tonnes grading 3.02% copper and 1.76 g/t gold, at a cut-off grade of 1.3% copper equivalent with an effective date of September 30, 2020. Mineralization is open at depth and along strike and the Company plans to further test the limits of the deposit. On the larger land package, the Company has identified a prospective stratigraphic contact between volcanic rocks and black and grey pelagic sediments and cherts that has been traced by Atico geologists for ten kilometers. This contact has been determined to be an important control on VMS mineralization on which Atico has identified numerous target areas prospective for VMS type mineralization occurrence, which is the focus of the current surface drill program at El Roble.

Qualified Person

Mr. Thomas Kelly (SME Registered Member 1696580), advisor to the Company and a qualified person under National Instrument 43-101 standards, is responsible for ensuring that the technical information contained in this news release is an accurate summary of the original reports and data provided to or developed by Atico.

About Atico Mining Corporation

Atico is a growth-oriented Company, focused on exploring, developing and mining copper and gold projects in Latin America. The Company generates significant cash flow through the operation of the El Roble mine and is developing it's high-grade La Plata VMS project in Ecuador. The Company is also pursuing additional acquisition of advanced stage opportunities. For more information, please visit www.aticomining.com .

ON BEHALF OF THE BOARD

Fernando E. Ganoza
CEO
Atico Mining Corporation

Trading symbols: TSX.V: ATY | OTCQX: ATCMF

Investor Relations
Igor Dutina
Tel: +1.604.633.9022

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

No securities regulatory authority has either approved or disapproved of the contents of this news release. The securities being offered have not been, and will not be, registered under the United States Securities Act of 1933, as amended (the ‘‘U.S. Securities Act''), or any state securities laws, and may not be offered or sold in the United States, or to, or for the account or benefit of, a "U.S. person" (as defined in Regulation S of the U.S. Securities Act) unless pursuant to an exemption therefrom. This press release is for information purposes only and does not constitute an offer to sell or a solicitation of an offer to buy any securities of the Company in any jurisdiction.

Cautionary Note Regarding Forward Looking Statements

This announcement includes certain "forward-looking statements" within the meaning of Canadian securities legislation. All statements, other than statements of historical fact, included herein, without limitation the use of net proceeds, are forward-looking statements. Forward- looking statements involve various risks and uncertainties and are based on certain factors and assumptions. There can be no assurance that such statements will prove to be accurate, and actual results and future events could differ materially from those anticipated in such statements. Important factors that could cause actual results to differ materially from the Company's expectations include uncertainties relating to interpretation of drill results and the geology, continuity and grade of mineral deposits; uncertainty of estimates of capital and operating costs; the need to obtain additional financing to maintain its interest in and/or explore and develop the Company's mineral projects; uncertainty of meeting anticipated program milestones for the Company's mineral projects; the world-wide economic and social impact of COVID-19 is managed and the duration and extent of the coronavirus pandemic is minimized or not long-term; disruptions related to the COVID-19 pandemic or other health and safety issues, or the responses of governments, communities, the Company and others to such pandemic or other issues; and other risks and uncertainties disclosed under the heading "Risk Factors" in the prospectus of the Company dated March 2, 2012 filed with the Canadian securities regulatory authorities on the SEDAR website at www.sedar.com



Primary Logo

News Provided by GlobeNewswire via QuoteMedia

ATY:CA
The Conversation (0)
Atico Mining Announces Completion NI 43-101 Feasibility Study for the La Plata Project in Ecuador

Atico Mining Announces Completion NI 43-101 Feasibility Study for the La Plata Project in Ecuador

Atico Mining Corporation (the "Company" or "Atico") (TSX.V: ATY | OTC: ATCMF) is pleased to announce the results of the Definitive Feasibility Study (the "DFS" or the "Study") for its 100% owned La Plata Project ("La Plata") located in Ecuador. The DFS was prepared in accordance with the National Instrument 43-101 Standards of Disclosure for Mineral Projects ("NI 43-101"). Please note that all financial figures in this press release are in United States dollars, unless otherwise noted.

Key Highlights:

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
Atico Reports Consolidated Financial Results for First Quarter of 2024

Atico Reports Consolidated Financial Results for First Quarter of 2024

Atico Mining Corporation (the "Company" or "Atico") (TSX.V: ATY | OTC: ATCMF) today announced its financial results for the three months ended March 31, 2024, posting income from mining operations of $2.8 million and a net loss of $0.4 million. Production for the period at Atico's El Roble mine totaled 3.3 million pounds ("lbs") of copper and 2,185 ounces ("oz") of gold in concentrate at a cash cost (1) of $2.57 per payable pound of copper (2) .

Fernando E. Ganoza, CEO and Director, commented, "the operational and financial results for this quarter were in line with Company expectations. We are already into development of the newly discovered reserves and have been making additional investments in preparation for ore extraction from these areas." Mr. Ganoza continued, "for the remainder of the year, we should start to see an improvement in our operating costs as we progressively gain access to mining the upper areas of the mine, while at the same time the recent increase in metals prices, particularly in copper should be positively reflected in our revenue and margin."

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
Atico Produces 3.34 Million Pounds of Cu and 2,156 Ounces of Au in First Quarter 2024

Atico Produces 3.34 Million Pounds of Cu and 2,156 Ounces of Au in First Quarter 2024

Atico Mining Corporation (the "Company" or "Atico") (TSX.V: ATY | OTCQX: ATCMF) announces its operating results for the three months ended March 31, 2024 from its El Roble mine. Production for the quarter totaled 3.34 million pounds of copper and 2,156 ounces of gold in concentrates, an increase of 44% for copper and a decrease of 16% for gold, respectively, over the same period in 2023.

"The El Roble mine operated in line with set expectations for this quarter as we improved on almost all metrics over the same period last year," said Fernando E. Ganoza, CEO. "For the remainder of the year, the team will be focused on optimizing production to take advantage of the higher metal price environment and to deliver on this year's set guidance. In parallel, we continue to drill new high-grade resources in the mine vicinity target areas. These new areas will be incorporated into our mine plan as well as the new resource update which is planned to be published imminently."

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
Atico Reports Consolidated Financial Results for 2023

Atico Reports Consolidated Financial Results for 2023

(All amounts expressed in US dollars, unless otherwise stated)

Atico Mining Corporation (the "Company" or "Atico") (TSX.V: ATY | OTC: ATCMF) today announced its financial results for the year ended December 31, 2023, posting income from mining operations of $7.4 million and a net loss of $5.8 million. Production for the year at Atico's El Roble mine totaled 13.2 million pounds ("lbs") of copper and 10,149 ounces ("oz") of gold in concentrate at a cash cost ( 1) of $2.04 per payable pound of copper (2) .

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
Atico Reports Multiple High Grade Intercepts up to 20.70m of 5.76% Cu, 4.46 g/t Au and 11.50m of 8.16% Cu, 8.09 g/t Au and Continues to Extend the Ore Body at El Roble Mine in Colombia

Atico Reports Multiple High Grade Intercepts up to 20.70m of 5.76% Cu, 4.46 g/t Au and 11.50m of 8.16% Cu, 8.09 g/t Au and Continues to Extend the Ore Body at El Roble Mine in Colombia

Atico Mining Corporation (TSX.V: ATY | OTCQX: ATCMF) ("Atico" or the "Company") is pleased to announce positive results for the latest 49 drill holes being carried out in an area of historical mining to expand tonnage at the El Roble mine. In addition, the Company reports the results for sixteen diamond drill core holes (see first table below), which included 20.70m of 5.76% Cu, 4.46 gt Au and 11.50m of 8.16% Cu, 8.09 gt Au. Ore grade intercepts in another fourteen drill holes are also reported over narrower widths of approximately 1 to 2 meters in areas with limited drilling which highlights the possibility of further extending the ore body with additional drill programs.

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
Cygnus Metals Ltd.  Opens the Market

Cygnus Metals Ltd. Opens the Market

Ernest Mast, President and Managing Director, Cygnus Metals Ltd. (TSXV: CYG) ("Cygnus Metals" or the "Company"), and his team, joined Robert Peterman, Chief Commercial Officer, Toronto Stock Exchange (TSX), to open the market to celebrate the Company's new listing on TSX Venture Exchange.

Cygnus Metals Limited (TSXV: CYG) (ASX: CY5) is a diversified critical minerals exploration and development company with projects in Quebec, Canada and Western Australia. The Company is dedicated to advancing its Chibougamau Copper-Gold Project in Quebec with an aggressive exploration program to drive resource growth and develop a hub-and-spoke operation model with its centralised processing facility. In addition, Cygnus has quality lithium assets with significant exploration upside in the world-class James Bay district in Quebec, and REE and base metal projects in Western Australia. The Cygnus team has a proven track record of turning exploration success into production enterprises and creating shareholder value.

MEDIA CONTACT:
Laurie Gaborit
Advisor, Investor Relations
lgaborit@cygnusmetals.com
416.219.2049

Paul Armstrong
Read Corporate
+61 8 9388 1474

To view the source version of this press release, please visit https://www.newsfilecorp.com/release/236970

News Provided by Newsfile via QuoteMedia

Keep reading...Show less
Osisko Metals Welcomes the Participation of the Quebec Government in Its Gaspé Copper Project

Osisko Metals Welcomes the Participation of the Quebec Government in Its Gaspé Copper Project

Osisko Metals Incorporated (the " Company or " Osisko Metals ") ( TSX-V: OM ; OTCQX: OMZNF ; FRANKFURT: 0B51 ) is pleased to welcome the participation of the Government of Quebec in its Gaspé Copper Project, located next to the Town of Murdochville in the Gaspé Peninsula, on the traditional territory of the Mi'gmaq First Nation of Gespe'gewa'gi.

The Government of Quebec will lead a pilot project to create a committee that seeks to maximize the economic benefits of the Gaspé Copper Project. The committee will be overseen by the Ministère des Ressources naturelles et des Forêts (Quebec Ministry of Natural Resources and Forests) and aims to optimize socio-economic benefits in the Gaspé Peninsula by ensuring strong collaboration with the business community throughout the project development process.

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
FPX Nickel Announces Results of Baptiste Nickel Project Economic Impact Study

FPX Nickel Announces Results of Baptiste Nickel Project Economic Impact Study

FPX Nickel Corp. (TSXV: FPX) (OTCQB: FPOCF) (" FPX Nickel " or the " Company ") is pleased to announce the results of an Economic Impact Study (the "Study" ) completed for the Company's Baptiste Nickel Project (" Baptiste " or " the Project "). The Company engaged Mansfield Consulting Inc. to assess the potential regional, provincial, and national economic impact of the Baptiste Nickel Project, based on the findings of the Company's Pre-Feasibility Study ("PFS" ) published in September 2023 .

The Economic Impact Study focuses on quantification of the economic impacts that would be created by the development and ongoing operations of the Project, and assesses the regional employment impacts created by the Project; the Study does not replace or alter the findings of the PFS. Amounts herein are in Canadian Dollars unless otherwise noted.

News Provided by Canada Newswire via QuoteMedia

Keep reading...Show less
Awalé's Transformative 2024 Sets the Stage for an Ambitious 2025

Awalé's Transformative 2024 Sets the Stage for an Ambitious 2025

HIGHLIGHTS

  • Charger Zone: A significant gold target in Awalé's portfolio, marking a transformative achievement in 2024 with some of the highest-grade intercepts in Africa in the last 12 months.

News Provided by Newsfile via QuoteMedia

Keep reading...Show less
RMI: granted option to acquire JV interests in Saudi Arabia

RMI: granted option to acquire JV interests in Saudi Arabia

AuKing Mining (AKN:AU) has announced RMI: granted option to acquire JV interests in Saudi Arabia

Download the PDF here.

Latest Press Releases

Related News

×