Galena Mining

Abra Production and Operations Update

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that production numbers achieved in October (subject to final reconciliation) show continual improvement and ramp-up progress at its Abra Base Metals Mine (“Abra”). In October, Abra achieved new record highs for overall mining and processing rates, and successful despatch of the mine’s seventh high-grade lead-silver concentrate shipment.


HIGHLIGHTS

  • October concentrate shipment was largest high-grade lead-silver concentrate shipment to date of ~10kt generating ~A$19.0 million revenue (loaded and despatched 5-7 November).
  • The following has been achieved in October (subject to final reconciliation):
    • New monthly record total ore milled of over 117kt (i.e., >1.4Mtpa implied annualised production rate compared to previous steady-state guidance of 1.3Mtpa).
    • New monthly record total material movement with ore and waste mined of over 150kt (high grade ore 105kt including 71kt from stope production).
    • During October the mine set multiple daily production records, including 4,593t of ore processed (~1.7Mtpa rate compared to previous steady-state guidance of 1.3Mtpa), 383t of concentrate produced (~140ktpa rate), 36m of development (~1,080m per month rate), 3,844t stoping production (~115kt per month rate) and 4,650t of total ore mined (~1.7Mtpa rate compared to previous steady-state guidance of 1.3Mtpa).
    • Underground development of ~750m (compared to September 2023 quarter monthly average of 713m) showing continued progress to our near-term 800-850m per month target.
  • December quarter mining and processing plans reaffirmed following October’s mining and production performance:
    • Processing over 320,000t of ore.
    • Lead concentrate shipments of approximately 25-30kt.
    • Mining over 2,400m of development and over 260,000t of stope ore.
    • Forecast group cash balance as at 31 December 2023 of A$15-25 million (after first Taurus debt repayment of ~A$7.0 million in December and finance costs), i.e., forecast positive all- in cash flow of A$8-18 million before taking into account the ~A$7.0 million debt repayment.
  • Detailed technical work is currently underway to look at 2024 production targets, with strong confidence based on ongoing ramp-up that Abra can comfortably exceed the previous mature steady-state target of 1.3Mtpa without material incremental capital expenditure. Planning underway to continue ramp-up towards 1.5Mtpa steady-state level.
Managing Director, Tony James commented, “Abra continues to set new monthly production records as ramp-up continues. Following October’s mining and processing performance we are well on track to meet our guidance for the December quarter. This will allow us to achieve our 31 December 2023 forecast group cash balance of A$15-25 million after accounting for the first Taurus debt repayment.

More importantly, we continue to see scope for continued ramp-up beyond the original 1.3Mtpa target without material capital expenditure and planning is underway to continue ramping-up towards a production running rate in the order of 1.5Mtpa, which we expect to be achieved during 2024.

Figure 1 – Vessel “CORETALENT OL” containing Abra’s seventh lead-silver concentrate shipment at Geraldton Port bound for Qinzhou, China

Figure 2 – Qube Logistics Services transferring the RotaboxTM containers to the ship for unloading. Once inside the ship’s hold, the lifting mechanism rotates the container to place the concentrate in the hold(photo 7 November 2023).


Click here for the full ASX Release

This article includes content from Galena Mining, licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.


G1A:AU
Galena Mining

Galena Mining Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

The Conversation (0)
Galena Mining (ASX:G1A)

Galena Mining


Keep reading...Show less
Galena Mining

Abra Construction At 97% Complete – First Ore Stockpiled For January Processing

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 97% complete as of 30 November 2022. Processing plant commissioning is progressing quickly with practical completion now expected in December 2022. Ore currently being mined from underground is being stockpiled in readiness for processing to begin in January 2023. Concentrate production will commence January 2023.

Keep reading...Show less
Galena Mining

Abra Construction At 92% Complete – Reaches First Ore Underground

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 92% complete as of 31 October 2022. Underground mine has reached the first ore (see ASX announcement 14 November 2022) and plant commissioning continues in several key areas with the project focussed on achieving first concentrate production in Q1 2023.
Keep reading...Show less
Galena Mining

Abra Mine Reaches Ore

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the underground development at its Abra Base Metals Mine (“Abra” or the “Project”) has reached the Abra orebody. Commissioning has commenced in several key areas of the processing facility and the Power Station (Pacific Energy) completed full integration of the hybrid gas/solar/battery energy storage system (BESS) power station on 10 November. The project remains on track for first concentrate production in Q1 2023.
Keep reading...Show less
Galena Mining

Galena Mining Activities Report For Quarter Ended 30 September 2022

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) reports on its activities for the quarter ended 30 September 2022 (the “Quarter”), primarily focused on construction of its 60%- owned Abra Base Metals Mine (“Abra” or the “Project”) located in the Gascoyne region of Western Australia.

Keep reading...Show less
Miners filing out paperwork.

Northern Territory Finalises Mine Legacy Remediation Program

The Northern Territory's government has finalised a AU$5.5 million six month mine legacy remediation program for sites located in the Tennant Creek area, a January 9 press release states.

The next phase will involve Alice Springs, where further works are scheduled for later this year.

“Mining has been an integral part of the Northern Territory’s history for more than 150 years, but historical mining activities have left behind a range of legacy features such as open shafts, degraded infrastructure, tailings dams, and waste rock dumps,” said Gerard Maley, deputy chief minister and minister for mining and energy.

Keep reading...Show less
Asian Battery Metals PLC

High grade Massive Sulphide Intercepts Confirmed at Oval

Asian Battery Metals PLC (ABM or the Company, ASX: AZ9) is pleased to announce the remaining laboratory assay results of the 2024 Phase 2 drilling program for samples from drillholes OVD026, OVD027, OVD028, and OVD029. The details of the assays are provided in Table 1.
Keep reading...Show less
Stock chart over globe.

Canadian Markets Steady Amid Trump Tariff Speculation and Renewed Greenland Interest

Canada's main stock index gained on Wednesday (January 8), driven by strength in tech and mining stocks.

Investors continue to weigh the impact of potential US trade policy changes under President-elect Donald Trump, as well as his renewed interest in taking ownership of Greenland, an idea he first raised in 2019.

The S&P/TSX Composite Index (INDEXTSI:OSPTX) closed at 25,049.66, recovering from two consecutive sessions of losses following Justin Trudeau's resignation as Canadian prime minister on Monday (January 6).

Keep reading...Show less
Stock chart with Canadian flag.

Trudeau Resigns, Canadian and US Markets React

Canadian markets showed mixed reactions following Prime Minister Justin Trudeau’s resignation.

The S&P/TSX Composite Index (INDEXTSI:OSPTX) closed lower on Monday (January 6), while the Canadian dollar gained strength against the US dollar, reflecting diverging investor sentiment.

The index dropped by 142.14 points to settle at 24,995.93, marking a 0.57 percent decline from its starting point for the day. Meanwhile, the Canadian dollar rose to 69.7 cents US, reaching a near three week high.

Keep reading...Show less
Australian dollars Australian flag in the background.

5 Australian Mining Grants Open for Applications in 2025

As 2025 begins, companies in the mining sector are gearing up for another year of work.

In Australia, there are many chances for explorers and developers to access government funding at both the state and federal level. The list below includes five programs that are open for applications, or will be soon.

Read on to learn more about what companies can apply and how much money is up for grabs.

Keep reading...Show less
Jay Martin, city skyline and gold bars.

VRIC 2025 Preview — Jay Martin Talks Resource Wars, Geopolitics and How to Invest

The next Vancouver Resource Investment Conference (VRIC) is set to run from January 19 to 20, 2025, and Jay Martin, president of Cambridge House, joined the Investing News Network ahead of time to discuss the event.

Looking at the resource sector, Martin, who also hosts the Jay Martin Show on YouTube, said the current decade has been defined by chaos and uncertainty, with no signs of a slowdown any time soon.

With that in mind, his macro thesis on commodities remains steadfast, and he's watching three key drivers.

Keep reading...Show less
Galena Mining

Galena Mining Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

Latest Press Releases

Related News

×