
August 31, 2023
True North Copper Limited (ASX:TNC) (True North, TNC or the Company) is pleased to provide an operational update for the month of August 2023 regarding its copper sulphate production at its Cloncurry Project (Queensland, Australia).
TNC has consistently increased copper sulphate production throughout August 2023, in tandem with the rise in soluble metal concentrations within the SX Plant production circuit.
The Company anticipates metal concentrations to continue rising throughout September 2023 (as consistent with testwork), until the plant achieves its projected production capacity (projected to be by the end of September 2023).
TNC has an exclusive offtake agreement with Kanins International for its copper sulphate production in Queensland.1
SUMMARY
- Heap Leach operation is consistent with both metallurgical testwork and company projections.
- Daily production will increase throughout September until plant capacity is achieved. The targeted capacity is 25 bags per day (bag weight averages between 900kg and up to 1.25t).
- As of 29 August 2023, there was 70kt of crushed ore under leach, with an additional 50kt in Run-of-Mine stockpiles awaiting crushing.
- Full payment for 20-bag shipments (approximately 20t) typically occurs within 5 days of production. Prices are set at the LME rate plus a premium. Average attributable price received for the month of August 2023 was US$8445 per metal tonne plus surcharge.
- All-In Sustaining Costs (AISC) for this copper sulphate product are expected to be low and based on August 2023 production, AISC at steady-state is expected to be in the range of $0.8 - 1.40 per/lb AUD.
- Mining restart studies at the Cloncurry Project for copper sulphide production will be finalised and announced during Q4 2023.
COMMENT
True North Copper’s Managing Director Marty Costello said:
“Commissioning of our SX Plant commenced in late June following refurbishment works. Despite a delay of approximately three weeks to our initial commissioning schedule, our sulphate production levels are now progressing as anticipated.
Production of copper sulphate is low cost, and its market value ensures we receive timely revenue, typically within 5 days post-production. Our decision to initiate production with existing oxide ore stockpiles was strategic, allowing us to solidify our operational foundation as exploration progresses at our Mt Oxide and Cloncurry Projects and we finalise mining restart studies.
With the planned commencement of mining at our Cloncurry Project, copper sulphate production is projected to constitute 20-25% of our annual metal output.
We're nearing the final stages of studies supporting the pending decision to resume mining operations at Cloncurry, which will allow us to commence copper concentrate production, and we expect to update the market in the December quarter.”
About TNC’s copper sulphate product
- Contains greater than 24% copper content (generally between 24-26%), crystallised form and free flowing.
- Copper sulphate is a mineral salt widely used in various industries, including agriculture, mining, water treatment, and chemical manufacturing. Its applications range from agricultural fungicides, animal feed supplements, and soil sterilisation to electroplating and laboratory reagents.
- TNC is paid (100% LME price + premium) for the copper content of each bag. Each bag carries up to 1.25 tonnes of product (see Figures 1 & 2 below of bags of copper sulphate at the Cloncurry Project ready for shipment).
- TNC has an offtake agreement which requires all copper sulphate produced by the Company at its Queensland sites for the life of copper sulphate production from those sites to be purchased by Kanins International.


About TNC’s copper sulphate production
- Since commencement of copper sulphate production2, copper concentrations in solutions have continued to increase. The current PLS grade is 1.2g/L and flows from heap are 39.1m3/hr. TNC expects this to increase as per testwork and operational metallurgical balance, until process and plant capacity is reached. Refer to Figures 3 and 4 below with respect to current plant production for August 2023 and monthly production forecast for the next 3 months.
- TNC's operational team has delivered significant advancements in recent weeks as its operational knowledge and experience increases. Additionally, maintenance crews have transitioned from reactive measures, which were part of the initial plant commissioning, to now executing planned and scheduled programs.
- As of 29 August 2023, current Run-of-Mine uncrushed oxide ores stocks are circular 50kt of ore transported from TNC’s Mt Norma mine site. This oxide ore is uncrushed (sizing 100mm- 800mm) and unleached grading approximately 2% (refer to TNC’s Prospectus Annexure A - page 2043).
- All-In Sustaining Costs for this copper sulphate product are expected to be in the range of $0.8 - 1.40 per/lb AUD. August 2023 production is within this guidance.
Click here for the full ASX Release
This article includes content from True North Copper limited, licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.
TNC:AU
The Conversation (0)
11 October 2024
True North Copper
On the path to becoming Australia’s next responsible copper producer
On the path to becoming Australia’s next responsible copper producer Keep Reading...
20 November
Diamond Core Rig Arrived on Site
Critical Mineral Resources plc (“CMR”, “Company”) is delighted to announce the arrival of its diamond core drilling rig at Agadir Melloul, marking a major step forward that puts the project in an excellent position to accelerate drilling activity. The team is now focused on commissioning the rig... Keep Reading...
17 November
Drilling results confirm new copper discovery with district scale potential
Critical Mineral Resources plc (“CMR”, “Company”) is delighted to announce extremely encouraging results from its maiden core drilling programme at Agadir Melloul, confirming a significant new, shallow copper discovery and establishing the foundations for a potential district scale sediment... Keep Reading...
16 November
Nick Hodge: Copper is My Top 2026 Pick, but Gold, Silver Run Not Done
Nick Hodge, publisher at Digest Publishing, is most bullish on copper and uranium in 2026, but also believes gold and silver prices have further to go despite recent gains. "We are in the middle of a precious metals bull market," he said. "Silver hasn't had its day yet, so I think that's a... Keep Reading...
13 November
Cobre Advances Botswana Copper Project as Market Rerates Company
Cobre (ASX:CBE) CEO Adam Wooldridge says investor enthusiasm for the company has been driven by significant progress at its Ngami copper project in Botswana. “Investors are starting to see it as a real development opportunity,” he said, noting that Cobre has achieved in-situ copper recoveries of... Keep Reading...
13 November
Empire Metals Limited Announces Appointment of Joint Corporate Broker
Empire Metals Limited, the AIM-quoted and OTCQX-traded exploration and development company, is pleased to announce the appointment of Canaccord Genuity Limited ("Canaccord") as joint corporate broker with immediate effect. Canaccord will work alongside S. P. Angel Corporate Finance LLP and Shard... Keep Reading...
Latest News
Latest Press Releases
Related News
TOP STOCKS
American Battery4.030.24
Aion Therapeutic0.10-0.01
Cybin Corp2.140.00






