South Star Battery Metals Announces Santa Cruz Graphite Mine Phase 1 Construction and Licensing Update

South Star Battery Metals Announces Santa Cruz Graphite Mine Phase 1 Construction and Licensing Update

Highlights:

  • Santa Cruz Phase 1 construction has zero lost time accidents through end of July.
  • Santa Cruz Phase 1 construction is on budget and on schedule with commercial production planned for the EOY 2023.
  • All main construction contracts have been executed.
  • Overall construction advance at 68% complete.
  • Manufacturing of equipment at 80% complete.
  • Foundations & concrete work on schedule to be substantially completed in September.
  • Initial comments from Brazil's National Mining Agency for the definitive mining concessions for Santa Cruz's Phases 1, 2 & 3 have been received & responses returned.
  • The biannual environmental condition precedent report associated with Santa Cruz's environmental license has been submitted.

South Star Battery Metals Corp. ("South Star" or the "Company") (TSXV:STS)(OTCQB:STSBF), is pleased to announce a Phase 1 construction update through the end of July for the Company's flagship Santa Cruz Graphite Mine in Bahia Brazil, as well as providing a permitting and licensing update for Phases 2 and 3 operations

Richard Pearce, CEO of South Star commented, "We are extremely pleased with the construction progress through the end July on the Santa Cruz Phase 1 plant and mine installations. The build continues on budget and on schedule, and we are very proud of our ongoing safety record. The team will continue to work hard and focus on our ongoing commitment to safe, responsible operations. Significant progress has been made on the concrete and foundation work, which should be substantially completed in next couple weeks. Equipment manufacturing is on schedule and should be largely wrapped up in next 6 weeks, with all major equipment delivered to the mine. The electrical and mechanical contractor is in the process of mobilizing. We are firmly on track to be commissioning Santa Cruz in November and starting commercial production by EOY 2023. Notably, the start of commercial production at Santa Cruz will be a significant milestone achievement marking the first new graphite producer in the Americas since 1996. Additionally, our BamaStar projected is expected to commence vertically integrated production in 2027."

Santa Cruz Construction and Licensing Update

Construction through the end of July 2023 is on schedule and on budget for Phase 1 commercial production planned for the EOY 2023. South Star's Q3 2023 primary work programs include:

  • Civil construction, foundations, and retention walls for the plant area;
  • Structural, electrical and mechanical assemblies;
  • Electrical substation and internal electrical distribution network;
  • Laboratory, cafeteria, changing rooms, warehouse, shops and other appurtenant support structures; and
  • Delivery of 100% of the major equipment.

Initial comments from Brazil's National Mining Agency have been received and responded to for the majority of the final mining concessions incorporating a phased approach to Phases 1, 2 and 3 and up to 50,000 tonnes per year of concentrate production. The biannual condition precedents report associated with Santa Cruz's environmental license has also been submitted to the environmental regulatory agency. The Company expects to receive the definitive mining licenses and environmental permits for Phases 1, 2 and 3 in early Q1 2024.

About South Star Battery Metals Corp

South Star Battery Metals Corp. is a Canadian battery metals project developer focused on the selective acquisition and development of near-term production projects in the Americas. South Star's Santa Cruz Graphite Project, located in Southern Bahia, Brazil is the first of a series of industrial and battery metals projects that will be put into production. Brazil is the second-largest graphite-producing region in the world with more than 80 years of continuous mining. Santa Cruz has at-surface mineralization in friable materials, and successful large-scale pilot-plant testing (> 30 tonnes) has been completed. The results of the testing show that approximately 65% of Cg concentrate is +80 mesh with good recoveries and 95%-99% Cg. With excellent infrastructure and logistics, South Star is fully funded for Phase 1, and the 12-month construction and commissioning are underway. Santa Cruz will be the first new graphite production in the Americas since 1996 with Phase 1 commercial production projected in Q4 2023. Phase 2 production (25,000 tpa) is partially funded and planned for 2026, while Phase 3 (50,000 tpa) is scheduled for 2028.

South Star's second project in the development pipeline is strategically located in Alabama in the center of a developing electric vehicle, aerospace, and defense hub in the southeastern United States. The BamaStar Project is a historic mine active during World Wars I & II. A NI43-101 technical report with the maiden resource estimate has been filed on SEDAR. Trenching, phase 1 drilling, sampling, analysis, and preliminary metallurgical testing have been completed. The testing indicates a traditional crush/grind/flotation concentration circuit that achieved grades of approximately 94-97% Cg with approximately 86% recoveries. South Star is executing on its plan to create a multi-asset, diversified battery metals company with near-term operations in strategic jurisdictions. South Star trades on the TSX Venture Exchange under the symbol STS, and on the OTCQB under the symbol STSBF.

South Star is committed to a corporate culture, project execution plan and safe operations that embrace the highest standards of ESG principles based on transparency, stakeholder engagement, ongoing education, and stewardship. To learn more, please visit the Company website at https://www.southstarbatterymetals.com.

This news release has been reviewed and approved by Richard Pearce, P.E., a "Qualified Person" under National Instrument 43-101 and President and CEO of South Star Battery Metals Corp.

On behalf of the Board,

MR. RICHARD PEARCE
Chief Executive Officer

For additional information, please contact:

South Star Investor Relations
Email:invest@southstarbatterymetals.com
+1 (604) 706-0212
Twitter:https://twitter.com/southstarbm
Facebook: https://www.facebook.com/southstarbatterymetals
LinkedIn: https://www.linkedin.com/company/southstarbatterymetals/
YouTube:South Star Battery Metals - YouTube

CAUTIONARY STATEMENT

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this press release.

Forward-Looking Information

This press release contains "forward-looking statements" within the meaning of applicable securities legislation. Forward-looking statements relate to information that is based on assumptions of management, forecasts of future results, and estimates of amounts not yet determinable. Any statements that express predictions, expectations, beliefs, plans, projections, objectives, assumptions or future events or performance are not statements of historical fact and may be "forward-looking statements". Forward-looking statements in this press release include, but are not limited to, statements regarding, moving Santa Cruz into production and scaling operations as well as advancing the Alabama project; and the Company's plans and expectations.

Forward-looking statements are subject to a variety of risks and uncertainties which could cause actual events or results to differ from those reflected in the forward-looking statements, including, without limitation: risks related to failure to obtain adequate financing on a timely basis and on acceptable terms; risks related to the outcome of legal proceedings; political and regulatory risks associated with mining and exploration; risks related to the maintenance of stock exchange listings; risks related to environmental regulation and liability; the potential for delays in exploration or development activities or the completion of feasibility studies; the uncertainty of profitability; risks and uncertainties relating to the interpretation of drill results, the geology, grade and continuity of mineral deposits; risks related to the inherent uncertainty of production and cost estimates and the potential for unexpected costs and expenses; results of prefeasibility and feasibility studies, and the possibility that future exploration, development or mining results will not be consistent with the Company's expectations; risks related to commodity price fluctuations; and other risks and uncertainties related to the Company's prospects, properties and business detailed elsewhere in the Company's disclosure record. Should one or more of these risks and uncertainties materialize, or should underlying assumptions prove incorrect, actual results may vary materially from those described in forward-looking statements. Investors are cautioned against attributing undue certainty to forward-looking statements. These forward-looking statements are made as of the date hereof and the Company does not assume any obligation to update or revise them to reflect new events or circumstances. Actual events or results could differ materially from the Company's expectations or projections.

SOURCE: South Star Battery Metals Corp.



View source version on accesswire.com:
https://www.accesswire.com/773068/South-Star-Battery-Metals-Announces-Santa-Cruz-Graphite-Mine-Phase-1-Construction-and-Licensing-Update

News Provided by ACCESSWIRE via QuoteMedia

STS:CA
The Conversation (0)
South Star Announces Additional Sales of Natural Flake Graphite Concentrate to U.S. Customer

South Star Announces Additional Sales of Natural Flake Graphite Concentrate to U.S. Customer

Advancing the First New Natural-Flake Graphite Mine in the Americas this Century

South Star Battery Metals CORP. ("South Star" or the "Company") (TSXV:STS)(OTCQB:STSBF) is pleased to announce that, further to the Company's May 6, 2024 announcement ("South Star Battery Metals Announces the First Sale of Natural Flake Graphite Concentrate from its Santa Cruz Graphite Mine in Brazil") and its August 1, 2024 announcement ("South Star Announces Successful Product Qualification and 100-Tonne Sale of Natural Flake Graphite Concentrate to U.S. Customer"), South Star has executed another binding commercial sales agreement (the "Agreement") for an initial 40 tonnes (more than 88,000 pounds) of natural-flake graphite concentrate from the Company's flagship Santa Cruz Graphite Mine("Santa Cruz"), located in northeastern Brazil's Bahia state. This most recent sales Agreement was formally executed with a prominent American industrial graphite customer (the "U.S. Client

News Provided by ACCESSWIRE via QuoteMedia

Keep reading...Show less
South Star Announces Successful Product Qualification and 100-Tonne Sale of Natural Flake Graphite Concentrate to U.S. Customer

South Star Announces Successful Product Qualification and 100-Tonne Sale of Natural Flake Graphite Concentrate to U.S. Customer

South Star advancing the first new natural-flake graphite mine in the Americas this century.

South Star Battery Metals CORP. ("South Star" or the "Company") (TSXV:STS)(OTCQB:STSBF) is pleased to announce that further to the Company's May 6, 2024 announcement ("South Star Battery Metals Announces the First Sale of Natural Flake Graphite Concentrate from its Santa Cruz Graphite Mine in Brazil"), South Star has executed another binding commercial sales agreement (the "Agreement") for the initial purchase of 100 tonnes (more than 220,000 pounds) of graphite concentrate from the Company's flagship Santa Cruz Graphite Mine ("Santa Cruz"), located in northeastern Brazil's Bahia state

News Provided by ACCESSWIRE via QuoteMedia

Keep reading...Show less
South Star Announces Substantial Completion and Commissioning of the Santa Cruz Phase 1 Graphite Mine in Brazil

South Star Announces Substantial Completion and Commissioning of the Santa Cruz Phase 1 Graphite Mine in Brazil

Highlights

  • Mine prestrip, preliminary dump foundations and ramps are complete, and approximately 50,000 tonnes of ore is being placed on the ore pad by end of August for commissioning and initial operations.

News Provided by ACCESSWIRE via QuoteMedia

Keep reading...Show less
South Star Battery Metals Announces Successful Metallurgical Results for its BamaStar Graphite Project in Alabama, USA

South Star Battery Metals Announces Successful Metallurgical Results for its BamaStar Graphite Project in Alabama, USA

Highlights:

  • Metallurgical work completed on representative oxide, transition and fresh rock composite samples ranging in grade from 2.36% Cg for fresh rock to 3.04% Cg for oxide samples.
  • Bond abrasion and work index testing show low to medium abrasion and low energy requirements.
  • Open circuit flotation tests resulted in excellent concentrates grade ranging from 94.4% Cg for fresh rock materials to 99.5% Cg for oxide samples with a simple flowsheet that maximizes graphite recovery and minimizes flake degradation.
  • The open circuit graphite recoveries were high, ranging between 87.5% and 91.5%.
  • Given the superior response of the oxide and transitional material, the next phase of work will investigate mining pit design to maximize processing of oxide and transitional material early in the project life and postpone mining of the fresh ore in order to decrease initial CAPEX, lower OPEX and target improved project economics.
  • The NI43-101 Preliminary Economic Assessment results for BamaStar are scheduled for release in August 2024.

South Star Battery Metals Corp. ("South Star" or the "Company") (TSXV:STS)(OTCQB:STSBF) is pleased to announce successful results from the ongoing metallurgical process development program for the Bama Star graphite project in Alabama, USA

News Provided by ACCESSWIRE via QuoteMedia

Keep reading...Show less
South Star Battery Metals Announces Land Purchase, Construction Update, and the Approval of the Definitive Mining Licenses For Phases 1, 2 & 3 for its Santa Cruz Graphite Mine in Brazil

South Star Battery Metals Announces Land Purchase, Construction Update, and the Approval of the Definitive Mining Licenses For Phases 1, 2 & 3 for its Santa Cruz Graphite Mine in Brazil

Santa Cruz Graphite Mine Highlights:

  • Final payment of land purchase for Phase 1 Plant and Operations.
  • Approval of the Definitive Mining Licenses For Phases 1, 2 & 3. All mining and environmental licenses/permits are approved and in-hand for the future phased, modular expansion of Santa Cruz graphite production up to 50,000 tonnes/year.
  • Phase 1 construction is on schedule for substantial completion by the end of June 2024 followed by a 6-week plant commissioning and ramp-up period. Commercial sales are planned to start in September 2024. Name plate production capacity is expected to be reached in Q4 2024.

South Star Battery Metals Corp. ("South Star" or the "Company") (TSXV:STS)(OTCQB:STSBF) is pleased to announce the final payment of the previously announced (Aug. 02, 2022) land purchase required for construction of the Phase 1 mine and plant facilities. The farm totals approximately 325 hectares and is where all the plant facilities, mine and infrastructure installations are required for the first three years of operations at its Santa Cruz Graphite Project in Bahia, Brazil

News Provided by ACCESSWIRE via QuoteMedia

Keep reading...Show less
Altech Batteries Ltd  CERENERGY Battery Project Funding Update

Altech Batteries Ltd CERENERGY Battery Project Funding Update

Perth, Australia (ABN Newswire) - Altech Batteries Limited (ASX:ATC) (FRA:A3Y) (OTCMKTS:ALTHF) is pleased to announce an update on funding of the CERENERGY(R) sodium-chloride solid-state battery project in Saxony, Germany.

Highlights

- Financing plan and target structure in place

- Funding investment teaser documents and data room established

- Reach out to 10 commercial banks and 2 venture debt funds - all positive interests

- Shortlisting potential lead bank

- Equity Funding - potential sale of minority interest of the project to realise capital and strategic value

- Discussions and draft term sheets shared with investors

- Offtake agreement LOI signed with ZISP

On 14 June 2024, the Company, through its Germany subsidiary Altech Batteries GmbH ("ABG"), announced the appointment of global big four professional services firm ("funding adviser") to assist in securing finance for the construction of Altech's 120MWh CERENERGY(R) battery manufacturing plant in Germany. The project's financing strategy is structured across three key areas: debt, equity, and grants.

These sources will cover not only the capital expenditures but also financing costs, working capital, debt service coverage, and an additional contingency for potential business interruptions, See Figure 1*.

DEBT PROCESS

A funding invitation document (investment teaser) has been finalised and distributed to various financial institutions for debt funding in the project. The Group has engaged ten commercial banks and two venture debt funds in a first market round, receiving predominantly positive initial feedback. Several of these institutions have expressed strong interest in participating in the financing. The Group is now in the process of shortlisting potential lenders to identify the most suitable financial partners for the project. To support a thorough due diligence process, a secure data room has been set up, providing detailed project information to interested financiers and ensuring full transparency. The DFS financial model has been adjusted to stress-test various funding scenarios tailored to the lending institutions ABG has engaged with. Further steps involve determining the most suitable banks to form a syndicate and appointing a lead bank to guide the lending process. This syndicate will play a crucial role in structuring the financing arrangement to meet the project's requirements.

EQUITY FUNDING

In addition to ongoing debt financing efforts, the Group has engaged several equity advisers to support the equity component of the project's funding package. As part of this strategy, the Altech Group plans to divest a minority interest in the project to one or two strategic investors. This partial divestment aims to attract investors who can bring not only capital, but also strategic value to the project, aligning with the CERENERGY(R) project's long-term growth and sustainability objectives.

The Group is specifically targeting large utility groups, data centre operators, investment funds and corporations that are heavily involved in the green energy transition. These entities are seen as ideal partners due to their strong alignment with the project's focus on sustainable energy solutions, as well as their capacity to provide substantial financial backing.

To date, significant progress has been made in these equity discussions. Several Non-Disclosure Agreements (NDAs) have been signed, allowing for deeper engagement with prospective investors. Altech has also circulated draft term sheets to a number of interested parties, outlining the proposed terms and conditions for investment. These documents serve as a starting point for negotiations, paving the way for more detailed discussions regarding the potential equity stake and partnership structure.

The strategic decision to divest a portion of the project is aimed at reducing the overall financial burden on the Company while bringing in experienced partners who can contribute to the project's success. By securing both the equity and debt components, the Company aims to finalise the full financing package, ensuring the timely construction and commissioning of the CERENERGY(R) battery plant. The next steps will focus on advancing these discussions and converting interest into formal commitments, which are crucial for moving forward with the project.

OFFTAKE ARRANGEMENTS

On 13 September 24, Altech announced the execution of an Offtake Letter of Intent between Zweckverband Industriepark Schwarze Pumpe (ZISP) and Altech Batteries GmbH. Under this Offtake Letter of Intent (LOI), ZISP will purchase 30 MWh of energy storage capacity annually, consisting of 1MWh GridPacks, for the first five years of production. The price of these batteries has been agreed and aligns with the sales price contained within Altech's Definitive Feasibility Study. The purchase of these batteries is subject to performance tests, battery specifications and the batteries meeting customer requirements. This offtake LOI constitutes an important aspect of the financing process. This lays the foundation for additional offtake arrangements, which are currently in progress. These agreements are vital for advancing our financing and construction timelines for the CERENERGY(R) project.

CEO and MD Mr Iggy Tan stated "The funding stage of any project is the most complex and challenging process of any project. Securing a big four funding adviser with expertise and a global network is a major step in our financing efforts. Altech is advancing both debt and equity discussions, along with offtake agreements, to fully fund the CERENERGY(R) project. We are seeing strong interest, especially from European banks and potential equity partners".

*To view tables and figures, please visit:
https://abnnewswire.net/lnk/PO741A78

To view MD Iggy Tan explain the Funding, please visit:
https://www.abnnewswire.net/lnk/23705649



About Altech Batteries Ltd:  

Altech Batteries Limited (ASX:ATC) (FRA:A3Y) is a specialty battery technology company that has a joint venture agreement with world leading German battery institute Fraunhofer IKTS ("Fraunhofer") to commercialise the revolutionary CERENERGY(R) Sodium Alumina Solid State (SAS) Battery. CERENERGY(R) batteries are the game-changing alternative to lithium-ion batteries. CERENERGY(R) batteries are fire and explosion-proof; have a life span of more than 15 years and operate in extreme cold and desert climates. The battery technology uses table salt and is lithium-free; cobalt-free; graphite-free; and copper-free, eliminating exposure to critical metal price rises and supply chain concerns.

The joint venture is commercialising its CERENERGY(R) battery, with plans to construct a 100MWh production facility on Altech's land in Saxony, Germany. The facility intends to produce CERENERGY(R) battery modules to provide grid storage solutions to the market.

News Provided by ABN Newswire via QuoteMedia

Keep reading...Show less
E-Power Resources Inc. Announces Closing of a Third and Final Tranche of Oversubscribed Private Placement

E-Power Resources Inc. Announces Closing of a Third and Final Tranche of Oversubscribed Private Placement

E-Power Resources Inc. (CSE: EPR) ("E-Power" or the "Company") announces that it has closed a third and final tranche of the private placement previously announced on September 24, 2024 (the "Private Placement"). The oversubscribed private placement was originally announced for $420,000, but a total of $526,264 was raised in all three tranches.

An aggregate of 3,150,000 units (the " Units") of the Company were issued in the third and final tranche at a price of $0.05 per Unit for gross proceeds of $157,500, each Unit being comprised of one common share in the capital of the Company (each a "Common Share") and one-half common share purchase warrant (each a "Warrant"), each Warrant entitling its holder thereof to acquire one additional common share (each a "Warrant Share") at a price of $0.10 per Warrant Share for a period of 60 months from the closing date. (the "Offering").

News Provided by Newsfile via QuoteMedia

Keep reading...Show less
Mawson Finland Limited Presents Downhole EM  Geophysics: Multiple Deep Conductors Newly Identified at Rajapalot

Mawson Finland Limited Presents Downhole EM Geophysics: Multiple Deep Conductors Newly Identified at Rajapalot

Mawson Finland Limited ("Mawson" or the "Company") (TSXV:MFL) is pleased to announce results from downhole electro-magnetic "DHEM" geophysical surveys conducted at the Rajapalot gold-cobalt project in Finland

Highlights:

News Provided by ACCESSWIRE via QuoteMedia

Keep reading...Show less
Canadian Investment Regulatory Organization Trade Resumption - EDDY

Canadian Investment Regulatory Organization Trade Resumption - EDDY

Trading resumes in:

Company: Edison Lithium Corp.

News Provided by Canada Newswire via QuoteMedia

Keep reading...Show less
Edison Lithium Arranges Sale of Interest in Argentinian Lithium Properties for US$3.5 Million

Edison Lithium Arranges Sale of Interest in Argentinian Lithium Properties for US$3.5 Million

Edison Lithium Corp. (TSXV: EDDY) (OTC Pink: EDDYF) (FSE: VV0) ("Edison" or the "Company") is pleased to announce that, effective November 12, 2024, it has accepted a non-binding purchase offer letter from Mava Gasoil LLC ("Mava"), a corporation based in Houston Texas, for the sale of 100% of the interest in the Company's Argentina subsidiary, Resource Ventures S.A. ("ReVe"), in consideration for USD$3,500,000. One of the LEXI claims owned by ReVe and the royalties on that mining property, and the PINAC mining properties owned by ReVe are excluded from the sale and will be retained by Edison.

ReVe controls the rights to prospective lithium brine claims in the province of Catamarca, Argentina. The claims are principally located in the two geologic basins known as the Antofalla Salar and the Pipanaco Salar. ReVe's assets on closing of the disposition to Mava will include 30 mining concessions covering approximately 104,538 hectares area in Catamarca Province, Argentina. The Company will retain and focus its Argentinian efforts on 8 mining concessions covering approximately 35,000 hectares area in Catamarca Province, Argentina, which are not subject to the sale and amount to approximately 25% of the claims currently held by ReVe.

News Provided by Newsfile via QuoteMedia

Keep reading...Show less