Copper Fox Metals Inc. through its wholly owned subsidiary Desert Fox Copper Inc., are pleased to provide an update on its 100% owned Van Dyke in-situ copper recovery project located in the Globe-Miami Mining District, Arizona. Montgomery & Associates a water resource consulting firm headquartered in Tucson, AZ, completed an Order of Magnitude estimate of the timeline, costs and datasurveys required to complete the ...

Copper Fox Metals Inc. (TSXV: CUU) (OTCQX: CPFXF) ('Copper Fox' or the 'Company'), through its wholly owned subsidiary Desert Fox Copper Inc., are pleased to provide an update on its 100% owned Van Dyke in-situ copper recovery ("ISCR") project located in the Globe-Miami Mining District, Arizona. Montgomery & Associates ("Montgomery"), a water resource consulting firm headquartered in Tucson, AZ, completed an Order of Magnitude (+-30%) estimate of the timeline, costs and datasurveys required to complete the hydrogeological portion of the pre-application and formal permitting process for the Van Dyke project.

Highlights

  • The Underground Injection Control Permit and Aquifer Protection Permit are the primary permits to be obtained.
  • The pre-application phase is estimated to take between 2-3 years, this will be followed by a 1.5-2 year permitting process after the applications are submitted.
  • Engineering costs are estimated at $US3.9 million for the pre-application phase and $US1 million for the post-submittal phase.
  • Logging the drill core from the Azurite target indicates that sampling of the last 40m of core from DDH AZ-3 should be completed.

Elmer B. Stewart, President and CEO of Copper Fox stated, "Copper Fox, in conjunction with Montgomery, is currently working on scheduling meetings with the EPA and ADEQ to obtain preliminary comments to further define the scope of work and other concerns, all fundamental to establishing next steps for the project. The drill holes required for the hydrogeological investigation can also be used to obtain additional analytical results and samples to better inform the metallurgical and geotechnical variability within the deposit and to advance the project to the pre-feasibility stage. The 40m interval of secondary copper at the bottom of DDH AZ-3 is encouraging and supports the expansion potential of the Van Dyke deposit to the southwest."

Background to the Data Gap Study
The Preliminary Economic Assessment ("PEA"), announced in early 2021, demonstrated robust project economics and concluded that the Van Dyke deposit has the potential of becoming a mid-tier copper project. The PEA recommended advancing the project to the pre-feasibility stage with an estimated budget of $US15.5 million including permitting and wellfield pilot testing.

Permitting Considerations
Permitting of a resource project in the United States includes investigating the current and long-term effects of the proposed project on surface water, groundwater, cultural and biological resources and air.

In the pre-application phase, Hydrogeological/Water Quality/Air/Biological/Cultural data are collected to support the formal application and other requirements of the EPA/ADEQ. On submission of the formal permitting application, the EPA/ADEQ completes an in-depth review of the technical data presented in the permitting application followed by a public comment period. An overview of the two primary permits to be obtained is described below:

Underground Injection Control ("UIC") Permit issued by the United States Environmental Protection Agency ("EPA") addresses the design, construction, integrity, and closure of injection/recovery wells to protect underground sources of drinking water from injection fluid migration. The UIC permitting process requires details of aquifer characteristics, groundwater flow, geochemistry (including baseline) demonstration of fluid injection hydrodynamics control, operations, monitoring, closure, and post closure monitoring.

Aquifer Protection Permit ("APP") issued by the Arizona Department of Environmental Quality ("ADEQ") covers mining related discharge (or potential discharge) from mine facilities with potential to discharge to groundwater.

Montgomery OOM
Montgomery completed an Order of Magnitude (+/-30%) estimate of the timeline and engineering costs to complete hydrogeologic studies to support the UIC and APP permits for the Van Dyke project. The study outlined the status of the project and recommends a seven-stage approach as set out below;

Stage Description Tasks and Required Expertise OOM Cost (±30%)
1 Desktop Review Identify data gaps, outline regional hydrogeology of Miami area, conceptual model development $100K
2 Field Program1 Regional geology and hydrogeology, geophysical interpretation, , state-level drilling/well permitting, drilling contractors, ADEQ and EPA monitoring well design, construction, and sampling $2M
3/4 Hydrogeologic and Geochemical Studies/Models Advanced modeling in complex hydrogeologic settings, advanced geochemical interpretation and modeling and materials characterization, integration of groundwater and geochemical models $1M
5 Engineering Coordination2 Familiarity with surface and subsurface mining facilities and ISCR well design $150K
6 Prepare Application Experience compiling APP and UIC permit applications $300K
7 Post-Submittal Support3 Experience with addressing deficiencies and enquiries from ADEQ and EPA $350K

20% Contingency
$780K

ADEQ APP Review4
Up to $200K

TOTAL OOM COST
$4.9M

 

  1. Estimated cost for a field program does not include lab costs, drilling contractor, equipping wells, etc.
  2. Engineering design cost estimates assumed to be included in pilot program and operational design cost estimates and not specific to permitting, costs include engineering coordination activities specific to APP and UIC permit applications
  3. Post-submittal support includes addressing minor reviewer inquiries and does not include substantial/additional studies or field work identified during regulatory review; estimated to be 10% of total costs for Stage 1-6
  4. ADEQ invoices applicant up to $200K for time to review APP application

Stage-1 has been completed and the key findings are summarized below:

  • Hydraulic conductivity values for the Gila Conglomerate and Pinal Schist (based on regional data) are variable and site-specific data will be required to support permitting. The historical data suggest a low hydraulic connectivity in the Pinal Schist.
  • Understanding the hydraulic characteristics of the faults will be important in modelling the movement of groundwater at the site to better-understand and simulate dewatering and ISCR wellfield operations.
  • Groundwater quality data from existing monitoring wells sampled in 2015 near the Van Dyke Shaft do not indicate any exceedances of regulatory standards.

Data gaps include lack of current water level measurements and background water quality data in the vicinity of the proposed ISCR wellfield and uncertainty regarding the extent and thickness of a clay layer at the base of the Gila Conglomerate. If laterally extensive, this clay layer could isolate the mineralized zone from the aquifer in the overlying Gila Conglomerate, which would be a positive feature for permitting the ISCR wellfield.

Montgomery recommendations based on Stage 1 key findings:

  • Installation of Vibrating Wire Piezometers in future drillholes to monitor groundwater levels and vertical gradients.
  • Installation of datalogging transducers in existing wells and in the Van Dyke Shaft to monitor groundwater levels.
  • Downhole video surveys of existing wells and the Van Dyke Shaft to verify historical records and assess downhole conditions.
  • Obtaining pumping records (or estimates) for groundwater withdrawals by adjacent mining operations and other users to refine the conceptual hydrogeologic model of the site.

Stage-2 of the Montgomery study recommends establishing a project wide system of monitoring wells as part of a comprehensive program to:

  • Monitor background groundwater quality and temporal changes in groundwater levels.
  • Conduct aquifer testing to establish site-specific hydraulic conductivity and storage values.
  • Conduct downhole geophysical logging to delineate the extent and thickness of the clay layer at the base of the Gila Conglomerate.

The data obtained from the above activities would be used to develop a numerical groundwater flow and transport model to support permitting of the ISCR wellfield.

Elmer B. Stewart, MSc. P. Geol., President and CEO of Copper Fox, is the Company's non-independent, nominated Qualified Person pursuant to National Instrument 43-101, Standards for Disclosure for Mineral Projects, and has reviewed and approves the scientific and technical information disclosed in this news release.

About Copper Fox:

Copper Fox is a Tier 1 Canadian resource company focused on copper exploration and development in Canada and the United States. The principal assets of Copper Fox and its wholly owned Canadian and United States subsidiaries, being Northern Fox Copper Inc. and Desert Fox Copper Inc., are the 25% interest in the Schaft Creek Joint Venture with Teck Resources Limited on the Schaft Creek copper-gold-molybdenum-silver project located in northwestern British Columbia and the 100% ownership of the Van Dyke oxide copper project located in Miami, Arizona. For more information on Copper Fox's other mineral properties and investments visit the Company's website at http://www.copperfoxmetals.com.

On behalf of the Board of Directors

Elmer B. Stewart
President and Chief Executive Officer

For additional information contact:
Lynn Ball: investor@copperfoxmetals.com
(844) 464-2820 or (403) 264-2820

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

Cautionary Note Regarding Forward-Looking Information

This news release contains forward-looking statements within the meaning of the Section 27A of the Securities Act of 1933 and Section 21E of the Securities Exchange Act of 1934, and forward-looking information within the meaning of the Canadian securities laws (collectively, "forward-looking information"). Forward-looking information is generally identifiable by use of the words "believes," "may," "plans," "will," "anticipates," "intends," "budgets", "could", "estimates", "expects", "forecasts", "projects" and similar expressions, and the negative of such expressions. Forward-looking information in this news release includes statements regarding recommendations of the PEA; a data gap analysis to determine requirements to enter a formal permitting process; preliminary meetings with the EPA and ADEQ; obtaining an UIC and APP permits; an ISCR wellfield pilot test program; and opportunities to advance the project to the pre-feasibility stage.

In connection with the forward-looking information contained in this news release, Copper Fox and its subsidiaries have made numerous assumptions regarding, among other things: the geological advice that Copper Fox has received is reliable and is based upon practices and methodologies which are consistent with industry standards and the reliability of historical reports. While Copper Fox considers these assumptions to be reasonable, these assumptions are inherently subject to significant uncertainties and contingencies.

Additionally, there are known and unknown risk factors which could cause Copper Fox's actual results, performance, or achievements to be materially different from any future results, performance or achievements expressed or implied by the forward-looking information contained herein. Known risk factors include, among others: the data gap analysis may not be completed as planned or at all; the recommendation of the PEA may not be completed as planned or at all; the UIC and APP permits may not be obtained; the ISCR wellfield pilot test program may not be undertaken as planned or at all; discussions with the EPA and ADEQ may be delayed or not scheduled; potential to enhance project value may not be achieved; the financial markets and the overall economy may deteriorate; the need to obtain additional financing and uncertainty of meeting anticipated program milestones; uncertainty as to timely availability of permits and other governmental approvals.

A more complete discussion of the risks and uncertainties facing Copper Fox is disclosed in Copper Fox's continuous disclosure filings with Canadian securities regulatory authorities at www.sedar.com. All forward-looking information herein is qualified in its entirety by this cautionary statement, and Copper Fox disclaims any obligation to revise or update any such forward-looking information or to publicly announce the result of any revisions to any of the forward-looking information contained herein to reflect future results, events, or developments, except as required by law.

To view the source version of this press release, please visit https://www.newsfilecorp.com/release/105301

News Provided by Newsfile via QuoteMedia

Copper Fox Metals

Copper Fox Metals

Overview

Keep reading... Show less

Teck Announces New Collective Agreement at Highland Valley Copper Operations

Teck Resources Limited (TSX: TECK.A and TECK.B, NYSE: TECK) ("Teck") announced today that members of United Steelworkers (USW) Local 7619, representing 1,048 workers at Teck's Highland Valley Copper (HVC) Operations in B.C., have ratified a new five-year collective agreement, replacing one that expired on September 30, 2021.

"We are pleased to have reached a collective agreement that is fair to employees and supports the long-term success of Highland Valley Copper Operations," said Matt Parrilla, General Manager, Highland Valley Copper Operations.

Keep reading... Show less
Benton and Sokoman Initiate Drill Program at the Kraken Lithium Prospect on the Golden Hope JV; Spodumene-bearing Pegmatite Encountered in First Hole

Benton and Sokoman Initiate Drill Program at the Kraken Lithium Prospect on the Golden Hope JV; Spodumene-bearing Pegmatite Encountered in First Hole

Benton Resources Inc. (TSXV: BEX) ("Benton") and Sokoman Minerals Corp. (TSXV: SIC) (OTCQB: SICNF) ("Sokoman") together, (the "Alliance") are pleased to announce that the Alliance has commenced the Phase 1 diamond drilling program at the Kraken Lithium prospect on the Golden Hope JV project located in southwest Newfoundland near the village of Burgeo. The diamond drilling program is expected to consist of 1,000 to 2,000 metres of diamond drill core in 4-6 holes designed to test an extensive system of spodumene- bearing dykes which have been sampled over a strike length of two kilometres within a corridor measuring 1,000 metres in apparent width and open in all directions. The Alliance is also pleased to announce that the first hole, with planned drill depth of 350 m-400 m across stratigraphy, has intercepted several spodumene-bearing (an important source of lithium) dykes near surface and the hole continues. Pictures of the core will be posted on both Benton's and Sokoman's websites in order to keep shareholders engaged in its progress at the Kraken dyke swarm. The Alliance is very pleased with the progress thus far and is in the process of logging, cutting and sampling the core to be submitted for assay as soon as possible. Kraken is the first-ever high-grade lithium discovery in Newfoundland and Labrador, with surface grab samples returning grades from trace to 2.37% Li2O (see Alliance joint press release dated August 16, 2021). This is also the first Newfoundland drilling program designed to target lithium.

The Kraken Pegmatites are highly evolved, pegmatite swarms similar to the geological environment and setting of other large systems in the Appalachian belt, including the important deposits held by Piedmont Lithium Inc. in the Carolinas, eastern US, as well as in the geologically equivalent Avalonia Project being advanced by Ganfeng Lithium in the Caledonides of Ireland. All samples will be submitted to Actlabs in Ancaster, Ontario for analysis by Sodium Peroxide Fusion ICPOES + ICPMS.

Keep reading... Show less
Sienna Receives Drill Permit for the Blue Clay Lithium Project in the Clayton Valley of Nevada

Sienna Receives Drill Permit for the Blue Clay Lithium Project in the Clayton Valley of Nevada

Sienna Resources Inc. (TSXV: SIE) (OTC Pink: SNNAF) (FSE: A1XCQ0) ("Sienna" or the "Company") is pleased to announce that it has received the drill permit for the planned upcoming drill program on the Blue Clay Lithium Project in Clayton Valley, Nevada. This project consists of 94 contiguous claims totaling approximately 1950 acres prospective for lithium.

Jason Gigliotti, President of Sienna Resources, states, "This was the final step needed to start our much anticipated maiden drill program on the Blue Clay Lithium Project right in the heart of the Clayton Valley, the preeminent address for lithium in North America. We anticipate the commencement of drilling shortly, coming at a time when lithium demand and prices are at all-time highs. Nevada has become one of the most sought after lithium addresses in the world, and Sienna is located in multiple locations in this prolific region. Management is very optimistic about the prospects for this project and expects to have a steady flow of news moving forward."

Keep reading... Show less
Falcon Receives Final TSX.V Approval on Viernes Adjacent to Yamana's El-Peñón Gold/Silver Deposit, Antofagasta City, Chile

Falcon Receives Final TSX.V Approval on Viernes Adjacent to Yamana's El-Peñón Gold/Silver Deposit, Antofagasta City, Chile

Falcon Gold Corp. (TSXV:FG)(GR:3FA)(OTCQB:FGLDF); ("Falcon" or the "Company") is pleased to report it has received final TSX Venture approval to move ahead on the option to purchase the Viernes project located 122km SE of Antofagasta City in Northern Chile. The claims encompass 13 claim blocks covering 3,300 Ha. The western portion of the project offers prospectivity for epithermal gold veins as evidenced by outcrops of the Chile-Alemania Paleocene volcano-stratigraphic sequence, which is the same host rock at the El-Peñón Gold Deposit owned by Yamana Gold. Additionally, Barrick Gold in 2015 sold a 50% stake in Zaldívar Mine for a $1.005 Billion in cash forming a partnership with Antofagasta PLC one of the worlds leading copper companies. Antofagasta has an outstanding track record of building and operating mines in Chile, the Zaldívar project is approximately 35kms NE of our claims

The Viernes project is located at moderate elevation of approximately 2000 meters above sea-level and is 5km east of Yamana Gold's highly profitable El-Peñón low sulfidation gold and silver mine, and 35kms southeast of the world class Escondida-Zaldívar copper hub. The project has year-round access via paved and gravel roads from the mining capital of Chile, known as Region II, Antofagasta.

Keep reading... Show less

Teck and DLT Partner to Pilot Traceability for Critical Minerals with Blockchain

Teck Resources Limited (TSX: TECK.A and TECK.B, NYSE: TECK) ("Teck") and DLT Labs™ ("DLT") today announced a pilot to use blockchain technology to trace responsibly-produced germanium from the mine to the customer, the first such use of blockchain to trace this critical mineral.

Teck is North America's largest producer of germanium, a critical mineral and one of the integral elements required for digital devices and communications. It is an essential component in fiber optic cables and high-speed computer chips and circuitry. Beyond its use in communications technology, germanium is also important for low-carbon technologies such as solar cells and light-emitting diodes (LEDs). Germanium is considered essential for communications technology and the transition to a low-carbon economy.

Keep reading... Show less

Trilogy Metals Announces Updated Resource Estimate for the Bornite Project

Trilogy Metals Inc. (TSX: TMQ) (NYSE American: TMQ) ("Trilogy" or the "Company") is pleased to announce the release of an updated mineral resource estimate for the Bornite Project located in the highly prospective Ambler Mining District of Northwest Alaska . The Bornite Project forms part of the Upper Kobuk Mineral Projects ("UKMP"), owned by Ambler Metals LLC ("Ambler Metals"), the joint venture operating company equally owned by Trilogy and a wholly owned subsidiary of South32 Limited (ASX, LSE, JSE: S32; ADR: SOUHY) ("South32").

Highlights of the Updated Bornite Resource Estimate

Keep reading... Show less

Latest Press Releases

Related News

×