LUCARA ANNOUNCES Q1 2023 RESULTS; UNDERGROUND EXPANSION CONTINUES

TSX: LUC) (BSE: LUC) (Nasdaq Stockholm: LUC)

Lucara Diamond Corp. ("Lucara" or the "Company") today reports its results for the quarter ended March 31, 2023 . View PDF version .

Q1 2023 HIGHLIGHTS:

  • Guidance maintained.
  • All key operational metrics were on plan, with 0.5 million tonnes of ore and 0.8 million tonnes of waste mined, 0.7 million tonnes of ore processed, and 89,640 carats recovered.
  • The Q1 2023 operating cash cost of $26.65 per tonne of ore processed (1) was well below the expected annual operating cash cost range of $32.50 to $35.50 per tonne of ore processed.
  • Revenue for the quarter ended March 31, 2023 totalled $42.8 million , including $5.3 million through Clara.
  • Cash flow generated from operating activities was $20.4 million .
  • $30.5 million invested in the Karowe underground expansion project ("UGP") in Q1 2023 focused on:
    • Main shaft sinking activities in both the ventilation shaft, currently at 213 metres below collar, and the production shaft, currently at 187 metres below collar.
    • The successful completion of the first grout programs in each shaft during the first quarter of 2023.
    • Completion and energization of the 11kV transmission line from the new Karowe substation to the UGP.
    • Stage two of the bulk power supply upgrade to connect all mine power requirements to the new Karowe Substation and 132kV power line. Both the existing operations and the UGP are now fully powered through the upgraded grid-supplied electricity.

(1) See "Non-IFRS Financial Performance Measures"


Eira Thomas, President & CEO commented: "As anticipated, Q1 delivered lower revenues than in the comparative period, owing to the change in ore mix processed and diamond pricing weakness resulting from continued geopolitical and economic uncertainty. Lucara's outlook for the year remains unchanged as the largest influence on our revenue in Q1, ore mix, returns to higher contributions of south lobe ore in subsequent quarters. Sinking continued in both the production and ventilation shafts with material improvement to planned sinking rates achieved for the production shaft and mitigations underway in the ventilation shaft to achieve the same. Water management remains a key focus area. An update to the schedule and budget for the underground project has been initiated in response to slower than planned ramp up to expected sinking rates, and, to account for time incurred and anticipated for future grouting programs. We remain on-track to complete the results of this analysis before the end of Q2, 2023."

REVIEW FOR THE QUARTER ENDED MARCH 31, 2023

  • Operational highlights from the Karowe Mine for Q1 2023 included:
    • Ore and waste mined of 0.5 million tonnes (Q1 2022: 0.8) and 0.8 million tonnes (Q1 2022: 0.5), respectively.
    • 0.7 million tonnes (Q1 2022: 0.7) of ore processed.
    • A total of 89,640 carats recovered (Q1 2022: 83,917) at a recovered grade of 12.8 carats per hundred tonnes of direct milled ore (Q1 2022: 12.6).
      • A total of 98 Specials were recovered, with two diamonds greater than 100 carats including one diamond greater than 300 carats in weight.
      • Recovered Specials equated to 4% of the weight percentage of total recovered carats from ore processed during Q1 2023 (Q1 2022 – 6.9%).
    • The twelve-month Total Recordable Injury Frequency Rate of 0.36 (Q1 2022: 0.23) trended downwards following a three-month period with no recordable injuries.
    • The Karowe Mine has operated for over two years without a lost time injury.
  • Financial highlights for the three months ended March 31, 2023 included:
    • Revenues of $42.8 million (Q1 2022: $68.2 million ) reflected a planned change in product mix beginning in early 2023 combined with the continuation of weaker diamond prices when compared to the strong diamond pricing observed in Q1 2022. During Q1 2023, 64% of the carats processed were recovered from the Centre and North Lobes and 36% were recovered from South Lobe material (Q1 2022: 100% South Lobe ore).
    • Karowe's +10.8 production, sold through HB, accounted for 57% (Q1 2022: 66%) of total revenues recognized in Q1 2023.
    • Sales of non-Karowe diamonds through Clara were $1.5 million in Q1 2023 (Q1 2022: $1.0 million ).
    • Adjusted EBITDA (1) was $15.3 million (Q1 2022: $36.0 million ), with the change directly attributed to a decrease in revenues.
    • Cash flow of $20.4 million (Q1 2022: $30.8 million ) from operating activities.
  • Cash position and liquidity at March 31, 2023 :
    • Cash and cash equivalents of $31.2 million .
    • Funded $18.0 million into a Cost Overrun Facility in the first quarter of 2023.
    • Drew $25.0 million from the $170.0 million project finance facility for the Karowe UGP resulting in $90.0 million drawn at quarter-end.
    • The outstanding balance on the working capital facility increased from $15.0 million to $23.0 million through Q1 2023, resulting in available liquidity of $27.0 million .

(1) See "Non-IFRS Financial Performance Measures"


DIAMOND MARKET

Despite a positive, longer-term outlook for natural diamonds, anchored on improving fundamentals around supply and demand, softer diamond prices observed in the latter half of 2022 have continued into 2023 as global economic concerns combined with geopolitical uncertainty, including the ongoing conflict in Ukraine continue to play out in the market, particularly in North America . Prices are beginning to show signs of stabilization as China begins to open-up post-Covid, a trend which is anticipated to continue towards the end of the year. Though sales of lab-grown diamonds increased during the period, intense competition combined with improvements in technology continue to drive prices of lab grown diamonds down. This further differentiates this market segment from the natural diamond market and highlights the unique nature and inherent rarity of natural diamonds. The longer-term market fundamentals remain unchanged and positive, pointing to strong price growth over the next few years as demand is expected to outstrip future supply.

2023 OUTLOOK

This section of the press release provides management's production and cost estimates for 2023. These are "forward-looking statements" and subject to the cautionary note regarding the risks associated with forward-looking statements. Diamond revenue guidance does not include revenue related to the sale of exceptional stones (an individual rough diamond which sells for more than $10 million ), or the Sethunya.

No changes were made to the Company's 2023 Guidance (released in December 2022).

Karowe Diamond Mine

Full Year – 2023

In millions of U.S. dollars unless otherwise noted


Diamond revenue (millions)

$200 to $230

Diamond sales (thousands of carats)

385 to 415

Diamonds recovered (thousands of carats)

395 to 425

Ore tonnes mined (millions)

1.9 to 2.3

Waste tonnes mined (millions)

2.2 to 2.8

Ore tonnes processed (millions)

2.6 to 2.9

Total operating cash costs (1) including waste mined (2) (per tonne processed)

$32.50 to $35.50

Botswana general & administrative expenses including marketing costs (per tonne processed)

$3.50 to $4.50

Tax rate (3)

0 %

Average exchange rate – USD/Pula

12.0

(1)

Operating cash costs are a non-IFRS measure. See "Non-IFRS Financial Performance Measures".

(2)

Includes ore and waste mined cash costs of $7.00 to $8.00 (per tonne mined) and processing cash costs of $12.00 to $13.00 (per tonne processed).

(3)

The Company is subject to a variable tax rate in Botswana based on a profit and revenue ratio which increases as profit as a percentage of revenue increases. The lowest variable tax rate is 22% while the highest variable tax rate is 55% (only if taxable income were equal to revenue). Capital expenditures are deductible when incurred. With planned capital expenditures of up to $105 million for the UGP, a tax rate of 0% is forecast for 2023. Should capital expenditures vary from plan, the Company could be subject to current tax.


DIAMOND SALES

Karowe diamonds are sold through three separate and distinct sales channels: through the HB sales agreement, on the Clara digital sales platform and through quarterly tenders.

HB SALES AGREEMENT FOR +10.8 CARAT DIAMOND PRODUCTION FROM KAROWE

For the three months ended March 31, 2023 , the Company recorded revenue of $24.5 million from the HB agreement (inclusive of top-up payments of $6.6 million ), as compared to revenue of $45.2 million (inclusive of top-up payments of $11.7 million ). The revenue achieved in Q1 2023 is comparable to the $24.1 million earned from the HB agreement (inclusive of top-up payments of $3.6 million ) in Q4 2022.

The decrease in revenue in Q1 2023 versus the comparative quarter can be attributed primarily to the number of high value diamonds delivered to HB in 2022 and the value of diamonds delivered earlier in 2021 for which top-up revenue was received in the period. Top-up values will typically increase as the more valuable stones move through production and become available for sale. Adjusting for the sale of Sewelô, a lower number of carats from production were delivered to HB in Q1 2023 compared to Q1 2022. The lower initial value of the shipments was reflective of the value in the stones delivered consistent with the change in product mix. This result is consistent with the resource model and expected.

At March 31, 2023 , a number of higher value and more technically complex stones that take longer to manufacture had not fully completed the manufacturing and sales process. As these stones finish the manufacturing process, the Company may record additional revenue in the form of "top-up" payments when these diamonds are sold.

Despite the overall decrease in revenue recognized in Q1 2023, diamond market fundamentals continued to support healthy prices as the number of polished stones sold by HB has improved from Q4 2022. Natural variability in the quality profile of the +10.8ct production in any production period or fiscal quarter results in fluctuations in recorded revenue and associated top-ups. During Q1 2023, 4% weight percentage of Specials of total carats recovered was consistent with the Karowe resource model.

CLARA SALES PLATFORM

As Clara grows, to complement goods from the Karowe mine, additional supply is being made available through diamonds purchased by the Company and re-sold through Clara and secondary market suppliers. Total volume transacted on the platform was $5.3 million in Q1 2023, with Karowe goods representing 63% of the total sales volume transacted. Sales of third-party diamonds increased to $1.5 million in Q1 2023 (Q1 2022: $1.0 million ). The Company is focused on growing Clara through building additional supply in 2023, both from third-party producers and the secondary market. The number of buyers on the platform continues to grow with 99 buyers on the platform at March 31, 2023 .

During Q1 2023, the sales volume transacted was $5.3 million (Q1 2022: $7.0 million ), as lower volumes were placed for sale (due to a shift in product mix from the Karowe Mine). A softening in market prices was observed between Q1 2023 and Q1 2022.

QUARTERLY TENDER

The Q1 2023 tender of $12.9 million (Q1 2022: $16.1 million ) reflected a good performance in rough diamond pricing with strength in the small stones. Rough diamond prices had reached a multi-year high point at the time of the Q1 2022 tender. Pricing achieved through the tender remained at or above price levels in 2019. A total of 77,750 carats were sold in the March 2023 tender, generating revenues of $12.9 million (Q1 2023 tender: $16.1 million from the sale of 74,638 carats).

KAROWE UNDERGROUND EXPANSION UPDATE

The Karowe UGP is expected to extend the mine life to at least 2040, with initial underground carat production predominantly from the highest value EM/PK(S) unit and is forecast to contribute approximately $4 billion in additional revenues, using conservative diamond prices.

During 2022, the Company updated the estimated capital cost for the Karowe UGP to $547 million (including contingency). As a result of sinking delays and grouting events beginning in mid-2022 and which are ongoing, the Company is evaluating the impact of the incurred delays against the overall project schedule and budget. Several operational adjustments were implemented beginning in Q4 2022 to address the challenges encountered. An update to the project schedule and budget to take into account these developments is expected to be completed before the end of Q2, 2023.

During the three months ended March 31, 2023 , a total of $30.5 million was spent on the Karowe UGP development, primarily in relation to ongoing construction activities, including:

  • Main sinking in the production and ventilation shafts:
    • In response to water inflows from the sandstones, one cover grouting event in the ventilation shaft and two events in the production shaft were successfully completed during February and March 2023 . Experiences gained from these first grouting events will inform future anticipated cover grouting events as the shafts progress to depth.
    • Planned sinking rates achieved in the production shaft in Q1 following active interventions and mitigations implemented in Q4 2022. Further investments made in Q4 2022 are expected to similarly improve sinking cycle times to planned rates in the ventilation shaft and progress is being closely monitored. Cycle time is the period it takes to complete a series of activities within the sinking process to achieve the next planned vertical advance.
    • The ventilation shaft is currently at 213 metres below collar, with a planned final depth of 731 metres. The production shaft is currently at 187 metres below collar, with a planned final depth of 765 metres.
  • The 11kV transmission line to the project site was commissioned in mid-January 2023 . This represents a significant milestone for the Karowe UGP as it is now fully powered through grid-supplied electricity.
  • Transition of the temporary power supply to a back-up power configuration. Back-up power will continue to be provided by diesel generators.
  • Stage two of the bulk power supply upgrade to connect all mine power requirements to the new Karowe Substation and 132kV power line. This upgrade is expected to deliver stable and dedicated power to the Karowe Mine operations.
  • The roll out of a behavioural-based safety training program in Q4 2022 has continued in the first quarter of 2023. The UGP achieved a three-month period with no reportable incidents delivering a three-month rolling Total Recordable Injury Frequency Rate of zero.

Activities for the Karowe UGP in Q2 2023 are expected to include the following:

  • Sinking and grouting within both the ventilation and production shafts.
  • Procurement of underground equipment, including dewatering pumps, underground crush and convey systems and the permanent stage winder.
  • Initiation of construction on the bulk air cooler system.
  • Development of a request for proposal for the underground lateral development work; and,
  • Continuation of detailed design and engineering of the underground mine infrastructure and layout.

The capital cost estimate for the underground expansion in 2023 is $105 million – see "2023 Outlook". The program will focus predominantly on shaft sinking and grouting activities in both shafts, along with construction of the bulk air cooler, tendering of the underground development contract and underground equipment purchases. Ramp-up to planned sinking rates for the ventilation shaft continues and additional cover grouting events are expected for both shafts in 2023 and 2024.

FINANCIAL HIGHLIGHTS – Q1 2023












Three months ended
March 31,

In millions of U.S. dollars, except carats or otherwise noted





2023

2022








Revenues




$

42.8

68.2

Operating expenses





(18.3)

(18.0)

Net income for the period





1.0

19.0

Earnings per share (basic and diluted)





0.00

0.04

Operating cash flow per share (1)





0.03

0.08

Cash on hand





31.2

39.1

Amounts drawn on working capital facility (2)





23.0

12.0

Amounts drawn on project finance facility





90.0

45.0

Karowe Revenue





41.2

67.2

Carats sold





83,374

80,295

(1)

Operating cash flow per share before working capital adjustments is a non-IFRS measure. See "Use of Non-IFRS Performance Measures" below.

(2)

Excludes amounts drawn from the Clara revolving credit facility.


QUARTERLY RESULTS OF OPERATIONS – KAROWE MINE, BOTSWANA


UNIT

Q1-23

Q4-22

Q3-22

Q2-22

Q1-22

Sales







Revenues from the sale of Karowe diamonds

US$M

41.3

40.1

46.5

50.0

67.2

Karowe carats sold

Carats

83,374

81,264

99,301

66,167

80,295

Production







Tonnes mined (ore)

Tonnes

541,400

484,705

920,410

1,091,192

811,947

Tonnes mined (waste)

Tonnes

761,295

199,385

453,860

357,764

482,104

Tonnes processed

Tonnes

700,678

690,946

693,398

719,207

666,488

Average grade processed (1)

cpht (*)

12.8

12.5

11.4

12.0

12.6

Carats recovered

Carats

89,640

86,655

78,879

86,317

83,917

Costs







Operating cost per tonne of ore processed (2)

US$

26.65

26.20

29.33

28.78

27.80








Capital Expenditures







Sustaining capital expenditures

US$M

0.8

9.9

4.0

4.1

0.8

Underground expansion project (3)

US$M

30.5

22.3

23.9

29.1

31.1

(*) carats per hundred tonnes

(1)

Average grade processed is from direct milling carats and excludes carats recovered from re-processing historic recovery tailings from previous milling.

(2)

Operating cost per tonne of ore processed is a non-IFRS measure. See "Use of Non-IFRS Performance Measures" below.

(3)

Excludes qualifying borrowing cost capitalized in each quarter.


CONFERENCE CALL

The Company will host a conference call and webcast to discuss the results on Friday, May 12, 2023 at 5:00am Pacific, 8:00am Eastern, 1:00pm UK, 2:00pm CET .

To join the conference call please use the following link https://emportal.ink/3MK80nT or the phone numbers listed below.

Conference ID:
33643944 / Lucara Diamond

Dial-In Numbers:

Toll-Free Participant Dial-In North America (+1) 888 390 0605
UK Toll free 0800 652 2435
Local Vancouver (+1) 416 764 8609

Webcast:
To view the live webcast presentation, please log on using this direct link: https://app.webinar.net/8rMY2nz2Z7p
The presentation slideshow will also be available in PDF format for download from the Lucara website ( Link to presentation ).

Conference Replay:
A replay will be available until May 19, 2023 . The pass code for the replay is: 643944#.

Replay number (Toll Free North America) (+1) 888 390 0541
Replay number (Local) (+1) 416 764 8677

On behalf of the Board,
Eira Thomas
President and Chief Executive Officer

Follow Lucara Diamond on Facebook , Twitter , Instagram , and LinkedIn

ABOUT LUCARA

Lucara is a leading independent producer of large exceptional quality Type IIa diamonds from its 100% owned Karowe Diamond Mine in Botswana . The Karowe Mine has been in production since 2012 and is the focus of the Company's operations and development activities. Clara Diamond Solutions Limited Partnership ("Clara"), a wholly-owned subsidiary of Lucara, has developed a secure, digital sales platform that uses proprietary analytics together with cloud and blockchain technologies to modernize the existing diamond supply chain, driving efficiencies, unlocking value and ensuring diamond provenance from mine to finger. Lucara has an experienced board and management team with extensive diamond development and operations expertise. Lucara and its subsidiaries operate transparently and in accordance with international best practices in the areas of sustainability, health and safety, environment, and community relations. Lucara has adopted the IFC Performance Standards and the World Bank Group's Environmental, Health and Safety Guidelines for Mining (2007). Accordingly, the development of the Karowe underground expansion project ("UGP") adheres to the Equator Principles. Lucara is committed to upholding high standards while striving to deliver long-term economic benefits to Botswana and the communities in which the Company operates.

The information is information that Lucara is obliged to make public pursuant to the EU Market Abuse Regulation and the Swedish Securities Markets Act. This information was submitted for publication, through the agency of the contact person set out above, on May 11, 2023 at 5:00pm Pacific Time .

NON-IFRS FINANCIAL PERFORMANCE MEASURES

This news release refers to certain financial measures, such as adjusted EBITDA, adjusted operating earnings, operating cash flow per share, operating margin per carat sold and operating cost per tonne of ore processed, which are not measures recognized under IFRS and do not have a standardized meaning prescribed by IFRS. These measures may differ from those made by other corporations and accordingly may not be comparable to such measures as reported by other corporations. These measures have been derived from the Company's financial statements, and applied on a consistent basis, because the Company believes they are of assistance in the understanding of the results of operations and financial position. Please refer to the Company's MD&A for the quarter ended March 31, 2023 for an explanation of non-IFRS measures used.

CAUTIONARY NOTE REGARDING FORWARD LOOKING STATEMENTS

Certain of the statements made and contained herein and elsewhere constitute forward-looking statements as defined in applicable securities laws. Generally, these forward-looking statements can be identified by the use of forward-looking terminology such as "expects", "anticipates", "believes", "intends", "estimates", "potential", "possible" and similar expressions, or statements that events, conditions or results "will", "may", "could" or "should" occur or be achieved.

Forward-looking statements are based on the opinions and estimates of management as of the date such statements are made, and they are subject to a number of known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of the Company to be materially different from any future results, performance or achievement expressed or implied by such forward-looking statements. The Company believes that expectations reflected in this forward-looking information are reasonable, but no assurance can be given that these expectations will prove to be accurate and such forward-looking information included herein should not be unduly relied upon.

In particular, forward-looking information and forward-looking statements in this news release may include, but are not limited to, information or statements of projected capital costs associated with the Karowe UGP,, the Company's ability to comply with the terms of the facilities which are required to construct the Karowe UGP, that expected cash flow from operations, combined with external financing will be sufficient to complete construction of the Karowe UGP, the potential impacts of COVID-19, economic and geopolitical risks, including potential impacts from the Russian military invasion of Ukraine , expectations regarding longer-term market fundamentals and price growth, the disclosure under "2023 Outlook", expectations regarding top-up payments, processing expectations, expectations that the Karowe UGP will extend mine life, forecasts of additional revenues, estimated capital costs, production and cost estimates, tax rates, expectations regarding the scheduling of activities for the Karowe UGP in 2023 and in future, that the estimated timelines to achieve mine ramp up and full production from the Karowe UGP can be achieved, the economic potential of a mineralized area, the size and tonnage of a mineralized area, anticipated sample grades or bulk sample diamond content, future production activity, the future price and demand for, and supply of, diamonds, future forecasts of revenue and variable consideration in determining revenue, estimation of mineral resources, exploration and development plans, cost and timing of the development of deposits and estimated future production, currency exchange rates, success of exploration, requirements for and availability of additional capital, capital expenditures, operating costs, the completion of transactions the profitability of Clara and the Clara Platform, and the scaling of the digital platform for the sale of rough diamonds owned by Clara, the Company's intent to continue to seek additional supply, both from third-party producers and the secondary market, the benefits to the Company of diamond supply agreements with HB and the ability to generate better prices from the sale of the Company's +10.8 carat production as a polished stone.

There can be no assurance that such forward looking statements will prove to be accurate, as the Company's results and future events could differ materially from those anticipated in this forward-looking information as a result of those factors discussed in or referred to under the heading "COVID-19 Global Pandemic, Economic and Geopolitical Risks" in the Company's most recent MD&A and under the heading "Risks and Uncertainties" in the Company's most recent Annual Information Form, both available at https://www.sedar.com , as well as changes in general business and economic conditions, the ability to continue as a going concern, changes in interest and foreign currency rates, changes in inflation, the supply and demand for, deliveries of and the level and volatility of prices of rough diamonds, costs of power and diesel, impacts of potential disruptions to supply chains, acts of foreign governments and the outcome of legal proceedings, inaccurate geological and recoverability assumptions (including with respect to the size, grade and recoverability of mineral reserves and resources), and unanticipated operational difficulties (including failure of plant, equipment or processes to operate in accordance with specifications or expectations, cost escalations, unavailability of materials and equipment, government action or delays in the receipt of government approvals, industrial disturbances or other job actions, adverse weather conditions, and unanticipated events relating to health safety and environmental matters).

Accordingly, readers are cautioned not to place undue reliance on these forward-looking statements which speak only as of the date the statements were made, and the Company does not assume any obligations to update or revise them to reflect new events or circumstances, except as required by law.

LUCARA ANNOUNCES Q1 2023 RESULTS; UNDERGROUND EXPANSION CONTINUES (CNW Group/Lucara Diamond Corp.)

SOURCE Lucara Diamond Corp.

Cision View original content to download multimedia: https://www.newswire.ca/en/releases/archive/May2023/11/c2572.html

News Provided by Canada Newswire via QuoteMedia

LUC:CC
The Conversation (0)

LUCARA FIRST QUARTER 2023 RESULTS TO BE RELEASED THURSDAY, MAY 11, 2023

TSX: LUC) (BSE: LUC) (Nasdaq Stockholm: LUC)

LUCARA FIRST QUARTER 2023 RESULTS TO BE RELEASED THURSDAY, MAY 11, 2023 (CNW Group/Lucara Diamond Corp.)

Lucara Diamond Corp. ("Lucara" or the "Company") announces that it will be publishing its 2023 First Quarter Results on Thursday, May 11, 2023 after market close in North America . PDF Version

The Company will host a conference call and webcast to discuss the results on Friday, May 12, 2023 at 5:00am Pacific, 8:00am Eastern, 1:00pm UK, 2:00pm CET .

CONFERENCE CALL:
To join the conference call please use the following link https://emportal.ink/3MK80nT or the phone numbers listed below.

Conference ID:
33643944 / Lucara Diamond

Dial-In Numbers:

Toll-Free Participant Dial-In North America

(+1) 888 390 0605

UK Toll free

0800 652 2435

Local Toronto

(+1) 416 764 8609

Webcast:
To view the live webcast presentation, please log on using this direct link: https://app.webinar.net/8rMY2nz2Z7p

The presentation slideshow will also be available in PDF format for download from the Lucara website ( Link to presentation ).

Conference Replay:
A replay of the telephone conference will be available two hours after the completion of the call until May 19, 2023 .

Replay number (Toll Free North America)

(+1) 888 390 0541

Replay number (Local)

(+1) 416 764 8677

The pass code for the replay is: 643944 #.

On behalf of the Board,

Eira Thomas
President and Chief Executive Officer

Follow Lucara Diamond on Facebook , Twitter , Instagram and LinkedIn

ABOUT LUCARA

Lucara is a leading independent producer of large exceptional quality Type IIa diamonds from its 100% owned Karowe Mine in Botswana and owns a 100% interest in Clara Diamond Solutions, a secure, digital sales platform positioned to modernize the existing diamond supply chain and ensure diamond provenance from mine to finger. The Company has an experienced board and management team with extensive diamond development and operations expertise. The Company operates transparently and in accordance with international best practices in the areas of sustainability, health and safety, environment and community relations.

The information in this release is accurate at the time of distribution but may be superseded or qualified by subsequent news releases.

The information was submitted for publication, through the agency of the contact person set out above, at 2:00pm Pacific Time on April 27, 2023 .

SOURCE Lucara Diamond Corp.

Cision View original content to download multimedia: https://www.newswire.ca/en/releases/archive/April2023/27/c2230.html

News Provided by Canada Newswire via QuoteMedia

Keep reading...Show less

Mountain Province Diamonds Announces First Quarter 2024 Production and Sales Results, Details of First Quarter 2024 Earnings Release and Conference Call

TSX and OTC: MPVD

Mountain Province Diamonds Inc. ("Mountain Province", the "Company") (TSX: MPVD) & (OTC: MPVD) today announces production and sales results for the first quarter ended March 31, 2024 ("the Quarter" or "Q1 2024") from the Gahcho Kué Diamond Mine ("GK Mine"). All figures are expressed in Canadian dollars unless otherwise noted.

News Provided by Canada Newswire via QuoteMedia

Keep reading...Show less

Mountain Province Diamonds Announces Full Year and Fourth Quarter 2023 Results

TSX and OTC: MPVD

Mountain Province Diamonds Inc. (" Mountain Province Diamonds", or the " Company ") (TSX: MPVD) (OTC: MPVD) today announces its financial and operating results for the fourth quarter (" the Quarter " or " Q4 2023 ") and the full year ended December 31, 2023 (" FY 2023 ").

News Provided by Canada Newswire via QuoteMedia

Keep reading...Show less

STAR DIAMOND CORPORATION COMPLETES ACQUISITION OF RIO TINTO'S 75% INTEREST IN FORT À LA CORNE JOINT VENTURE

TSX: DIAM

Star Diamond Corporation (" Star Diamond ") today announced the completion of its previously announced transaction (the " Transaction ") with Rio Tinto  Exploration Canada Inc. (" RTEC ") whereby RTEC has transferred to Star Diamond all of RTEC's 75% interest in the Fort à la Corne diamond project located in central Saskatchewan (the " Project "). Star Diamond now owns 100% of the Project.

News Provided by Canada Newswire via QuoteMedia

Keep reading...Show less

STAR DIAMOND CORPORATION ANNOUNCES 2023 YEAR END RESULTS

TSX: DIAM

Star Diamond Corporation ("Star Diamond" or the "Company") reports that the audited financial results for the year ended December 31, 2023 will be filed today on SEDAR+ and may be viewed at www.sedarplus.ca once posted.

Star Diamond Logo (CNW Group/Star Diamond Corporation)

Overview
Star Diamond Corporation is a Canadian natural resource company focused on exploring and developing Saskatchewan's diamond resources. Star Diamond currently holds, through a joint venture arrangement with Rio Tinto Exploration Canada Inc. ("RTEC"), a wholly-owned subsidiary of Rio Tinto plc, a 25% interest in certain mineral properties (which include the Star – Orion South Diamond Project, or the "Project") within the Fort à la Corne diamond district of central Saskatchewan, Canada . These properties are in close proximity to established infrastructure, including paved highways and the electrical power grid, which provide significant advantages for future mine development.

The Company also holds a 50% interest in the exploration and evaluation properties and assets of the Buffalo Hills JV located in north-central Alberta, Canada . Canterra Minerals Corporation ("Canterra") holds the remaining 50% interest. Canterra is the operator of the Buffalo Hills JV.

Fort à la Corne mineral properties
On November 28, 2023 , the Company entered into a binding agreement (the "Agreement") with RTEC, providing for the transfer by RTEC to Star Diamond all of RTEC's 75% interest in the Project.

The Agreement provides that, upon closing:

  • RTEC will transfer to Star Diamond all of RTEC's 75% interest in the Project, such that the Project will be 100% owned by Star Diamond ;
  • RTEC will transfer to Star Diamond ownership of the trench cutter drill rig used by RTEC to complete its prior bulk sampling program at the Project;
  • RTEC will transfer to Star Diamond the Bulk Sample Plant located at the Project, including the TOMRA XRT diamond sorting machine that is on-site;
  • Star Diamond will issue to RTEC and/or an affiliate that number of common shares of Star Diamond that results in RTEC and its affiliates owning 19.9% of the then outstanding common shares of Star Diamond (RTEC and its affiliates currently own approximately 2.3% of Star Diamond's outstanding common shares); and
  • RTEC and Star Diamond will enter into an Investor Rights Agreement whereby, among other things, RTEC will be granted certain pre-emptive rights to maintain its 19.9% ownership interest in Star Diamond in connection with future financings undertaken by Star Diamond , and RTEC will agree to certain standstill protections provided that RTEC will have the right to increase its 19.9% ownership position in the event that Star Diamond receives an acquisition proposal.

Upon completion of the transactions that are the subject of the Agreement, Star Diamond will have full control and responsibility for the Project, the existing joint venture agreement between RTEC and Star Diamond will terminate, and Star Diamond will release and indemnify RTEC for liabilities arising from or relating to the Project, all in exchange for a $4 million payment from RTEC to Star Diamond . RTEC has agreed that it will provide on Star Diamond's behalf, for up to five years following closing, letters of credit in the aggregate amount of no more than $9.9 million to secure certain environmental remediation and reclamation obligations related to the Project. Star Diamond will be obliged to repay any amounts drawn on these letters of credit and such repayment obligations will be secured against the Project and its assets.

As of the date of this News Release, the Agreement is expected to close in the near future.

Recent activities relating to the Star - Orion South Diamond Project and Fort à la Corne mineral properties
During the first quarter of 2024, Star Diamond continued to work with RTEC and Saskatchewan Ministry of Environment representatives to ensure an orderly close to the Agreement between Star Diamond and RTEC.

Year End Results
For the year ended December 31, 2023 , the Company recorded a net loss of $2.8 million or $0.01 per share (basic and fully diluted) compared to a net loss of $68.8 million or $0.15 per share in 2022. The decrease in net loss year over year was due primarily to the prior year's impairment charge of $66.3 million combined with the mark-to-market loss on the Wescan investment offset by the elimination of the $0.9 million contingent consideration.

At December 31, 2023 , the Company had $0.6 million (2022 – $2.6 million ) in cash and cash equivalents and a working capital deficit of $(0.3) million (2022 - $2.0 million ). The decrease in working capital was a result of administrative and exploration and evaluation expenditures offset by proceeds received from the December 2023 private placement. Subsequent to December 31, 2023 , the Company closed the second and final tranche of a non-brokered private placement. However, the ability of the Company to continue as a going concern and fund its expenses in an orderly manner will require additional forms of financings.

Selected financial highlights include:

Condensed Consolidated Statements of Financial Position

As at

December 31,

2023

As at

December 31,

2022

Current assets

$    0.6 M

$    2.7 M

Exploration and evaluation, investments and other assets

0.6 M

0.4 M

Current liabilities

0.9 M

0.7 M

Non-current liabilities

0.1 M

0.0 M

Shareholders' equity

0.2 M

2.4 M




Consolidated Statements of Loss

Year Ended
December 31,

2023

Year Ended
December 31,

2022

Expenses

$ 3.0 M

$ 3.0 M

Loss before undernoted items

(3.0)M

(3.0)M

Investment in Wescan Goldfields Inc.

(0.0)M

(0.4)M

Contingent consideration

0.0 M

0.9 M

Impairment charge

0.0 M

(66.3)M

Net loss for the year

(3.0)M

(68.8)M

Net loss per share for the year (basic and diluted)

(0.01)

(0.15)




Condensed Consolidated Statements of Cash Flows

Year Ended
December 31,

2023

Year Ended
December 31,

2022

Cash flows used in operating activities

$  (2.3)M

$  (4.9)M

Cash flows from investing activities

0.0 M

0.6 M

Cash flows from financing activities

0.2 M

5.7 M

Net increase (decrease) in cash

(2.1)M

1.3 M

Cash – beginning of year

2.6 M

1.3 M

Cash – end of year

0.6 M

2.6 M

Outlook
Fort à la Corne mineral properties
Subsequent to the successful close of the Agreement with RTEC, Star Diamond's technical team will focus on the technical investigation and evaluation of the Star – Orion South Diamond Project, with the goal of a future development decision. The initial work aims to prepare a revised Mineral Resource estimate for the Star – Orion South Diamond Project, which will form the foundation of an updated Prefeasibility study(" PFS"). The PFS will enable a Feasibility Study, on which a production decision can be based.

Buffalo Hills mineral properties
Management continues to review the recent results from the diamond valuation and typing analysis. A more detailed update on activities at the Buffalo Hills JV will be provided as it becomes available.

About Star Diamond Corporation
Star Diamond Corporation is a Canadian based corporation engaged in the acquisition, exploration and development of mineral properties. Shares of Star Diamond trade on the Toronto Stock Exchange under the trading symbol "DIAM". Star Diamond currently holds, through a joint venture arrangement with RTEC, a 25% interest in the Project. The Project is located in central Saskatchewan , in close proximity to established infrastructure, including paved highways and the electrical power grid, which provide significant advantages for future mine development. The Company also holds a 50% interest in the exploration and evaluation properties and assets of the Buffalo Hills JV located in north-central Alberta, Canada . Canterra holds the remaining 50% interest and is the operator of the Buffalo Hills JV.

Technical Information
All technical information in this press release has been prepared under the supervision of George Read , Senior Vice President Corporate Development, Professional Geoscientist in the Provinces of Saskatchewan and British Columbia and Mark Shimell , Vice President Exploration, Professional Geoscientist in the Provinces of Saskatchewan and Alberta , who are the Company's "Qualified Persons" under the definition of NI 43-101.

Stay Connected with Us:
Twitter: https://twitter.com/StarDiamondCorp
LinkedIn: https://www.linkedin.com/company/star-diamond-corp
Facebook: https://www.facebook.com/people/Star-Diamond-Corp/100058096376664/
Instagram: https://www.instagram.com/stardiamondcorp/

Caution Regarding Forward-looking Statements

This press release contains "forward-looking statements" and/or "forward-looking information" (collectively, "forward-looking statements") within the meaning of applicable securities legislation. Generally, these forward-looking statements can be identified by the use of forward-looking terminology such as "plans", "expects" or "does not expect", "is expected", "budget", "scheduled", "estimates", "forecasts", "intends", "anticipates" or "does not anticipate" or "believes", or the negative connotation thereof or variations of such words and phrases or state that certain actions, events or results, "may", "could", "would", "will", "might" or "will be taken", "occur" or "be achieved" or the negative connotation thereof. All statements, other than statements of historical fact, are forward-looking statements.

These forward-looking statements are based on Star Diamond's current beliefs as well as assumptions made by and information currently available to Star Diamond and involve inherent risks and uncertainties, both general and specific. Risks exist that forward-looking statements will not be achieved due to a number of factors including, but not limited to, statements regarding Rio Tinto Canada, the Company's ability to obtain financing to further the exploration, evaluation and/or development of exploration and evaluation properties in which the Company holds interest, the economic feasibility of any future development projects, developments in world diamond markets, changes in diamond prices, risks relating to fluctuations in the Canadian dollar and other currencies relative to the US dollar, the impact of changes in the laws and regulations regulating mining exploration, development, closure, judicial or regulatory judgments and legal proceedings, operational and infrastructure risks and the additional risks described in Star Diamond's most recently filed Annual Information Form, and annual and interim MDA.

Although the Company has attempted to identify important factors that could cause actual results to differ materially from those contained in forward-looking statements, there may be other factors that cause results not to be as anticipated, estimated or intended. There can be no assurance that such statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. In addition, forward-looking statements are provided solely for the purpose of providing information about management's current expectations and plans and allowing investors and others to get a better understanding of our operating environment. Accordingly, readers should not place undue reliance on forward-looking statements.

Forward-looking statements in this news release are made as of the date hereof and Star Diamond assumes no obligation to update any forward-looking statements, except as required by applicable laws.

SOURCE Star Diamond Corporation

Cision View original content to download multimedia: http://www.newswire.ca/en/releases/archive/March2024/25/c1142.html

News Provided by Canada Newswire via QuoteMedia

Keep reading...Show less

Mountain Province Diamonds Announces Revised Details for Q4 and Full-Year 2023 Earnings Release and Conference Call

TSX and OTC: MPVD

Mountain Province Diamonds Inc. ("Mountain Province", the "Company") (TSX: MPVD) (OTC: MPVD) today announces revised details for its fourth quarter and full-year 2023 earnings release and conference call. The delay in the issuance of fourth quarter and year-end 2023 results is due to the financial audit process not being completed by the planned date.

News Provided by Canada Newswire via QuoteMedia

Keep reading...Show less

STAR DIAMOND APPOINTS EWAN MASON AS ITS PRESIDENT AND CEO

Star Diamond Corp (TSX: DIAM) ("Star Diamond" or the "Company") is pleased to announce that its Board of Directors has appointed Ewan Mason to the position of President and Chief Executive Officer, effective immediately. Mr. Mason has served as Interim President and Chief Executive Officer since January 1, 2023. Mr. Mason will continue to serve as Chair of the Company's Board.

add logo (CNW Group/Star Diamond Corporation)

"We are pleased to name Ewan Mason as the President and CEO of Star Diamond," said Lisa Riley , Lead director of the Board. "Since he was appointed interim CEO in January 2023, Ewan's leadership has been integral in the successful negotiation process and the coming acquisition of Rio Tinto Exploration Canada Inc.'s 75% interest in the Fort à la Corne ("FALC") diamond district. He also continues to build strong relationships with our employees, shareholders and stakeholders, all while maintaining a focus on shareholder value."

"I am honored to accept the CEO position at Star Diamond," said Ewan Mason, President and CEO of Star Diamond. "I am excited about the prospect of an ongoing collaboration with an exceptional team and the future development of the world class diamond project that is FALC".

About Star Diamond Corporation
Star Diamond is a Canadian-based corporation engaged in the acquisition, exploration and development of mineral properties. Shares of Star Diamond trade on the Toronto Stock Exchange under the trading symbol "DIAM". Star Diamond's most significant asset is its interest in the Fort à la Corne property in central Saskatchewan. These kimberlites are located in close proximity to established infrastructure, including paved highways and the electrical power grid, which provide significant advantages for future mine development.

Stay Connected with Us:
Twitter: https://twitter.com/StarDiamondCorp
LinkedIn: https://www.linkedin.com/company/star-diamond-corp
Facebook: https://www.facebook.com/people/Star-Diamond-Corp/100058096376664/
Instagram: https://www.instagram.com/stardiamondcorp/

Caution Regarding Forward-looking Statements

This press release contains "forward-looking statements" and/or "forward-looking information" (collectively, "forward-looking statements") within the meaning of applicable securities legislation. All statements, other than statements of historical fact, are forward-looking statements. The use of any of the words "anticipate", "plan", "aim", "target", "contemplate", "continue", "estimate", "expect", "intend", "propose", "might", "may", "will", "shall", "project", "should", "could", "would", "believe", "predict", "forecast", "pursue", "potential", "possible", "capable" and similar expressions are intended to identify "forward-looking statements. Forward-looking statements in this press release include, but are not limited to, expectations regarding the timing for transfer of the Permit to Operate and completion of the transactions that are the subject of the Agreement.

These forward-looking statements are based on Star Diamond's current beliefs as well as assumptions made by and information currently available to it and involve inherent risks and uncertainties, both general and specific. Risks exist that forward-looking statements will not be achieved due to a number of factors including, but not limited to, the MoE's approval processes and the impact of changes in the laws and regulations regulating mining exploration, development, closure, judicial or regulatory judgments and legal proceedings and the additional risks described in Star Diamond's most recently filed Annual Information Form, annual and interim MD&A.

Although management of Star Diamond considers the assumptions contained in forward-looking statements to be reasonable based on information currently available to Star Diamond, those assumptions may prove to be incorrect. When making decisions with respect to Star Diamond, investors and others should not place undue reliance on these statements and should carefully consider the foregoing factors and other uncertainties and potential events.

Star Diamond does not undertake any obligation to release publicly revisions to any forward-looking statement to reflect events or circumstances after the date of this release, or to reflect the occurrence of unanticipated events, except as may be required under applicable securities laws. Investors should not assume that any lack of update to a previously issued forward-looking statement constitutes a reaffirmation of that statement. Continued reliance on forward-looking statements is at investors' own risk.

SOURCE Star Diamond Corporation

Cision View original content to download multimedia: http://www.newswire.ca/en/releases/archive/March2024/01/c3453.html

News Provided by Canada Newswire via QuoteMedia

Keep reading...Show less

Latest Press Releases

Related News

×