Predictive Discovery Limited (ASX:PDI, TSX:PDI) ("PDI" or "Company") is pleased to announce a production update for the three-month period ended 30 June 2026.1

  • Kiniero Gold Mine in Guinea delivered outstanding operational performance during the quarter. Average plant throughput of 1,113tph (~9.0Mtpa) – well above the 6.0Mtpa nameplate capacity – with gold recovery improving to 90.5%, demonstrating continued process optimisation and strong plant performance.
  • Mining operations at Kiniero continued to perform strongly during the quarter, supporting sustained mill throughput above nameplate capacity and consistent processing performance.
  • Kiniero milled 2.2Mt of ore at an average grade of 0.86g/t Au to pour 54,252oz Au.
  • Nampala milled 0.45Mt of ore at an average grade of 0.71g/t Au to pour 9,774oz Au.
  • Combined gold poured from Kiniero and Nampala of 64,026oz Au during the June 2026 quarter.
  • Cash and bullion as at 30 June 2026 of A$530M (US$365M).2

PDI will provide a comprehensive update of activities in its June 2026 quarterly report, to be released later this month.

This announcement is authorised for release by the PDI Board of Directors.

Neither the Toronto Stock Exchange nor its Regulation Services Provider (as that term is defined in the policies of the Toronto Stock Exchange) accepts responsibility for the adequacy or accuracy of this release.

For further information visit our website at www.predictivediscovery.com or contact:

Investor Enquiries
Matthew Wilcox
CEO & Managing Director
E: info@predictivediscovery.com
P: +61 8 9216 1000
Media Enquiries
Nathan Ryan
NWR Communications
E: nathan.ryan@nwrcommunications.com.au
P: +61 420 582 887
   

ABOUT PREDICTIVE DISCOVERY

PDI is a leading West African gold production and development company, combining a portfolio of high quality assets with a proven execution capability and strong financial platform.

PDI asset portfolio is anchored by the Kiniero Gold Mine in Guinea, which commenced production in late 2025, and the Nampala Gold Mine in Mali, which has been operating since 2017. These production assets provide momentum and strong cash flows as the Company advances its growth plans.

PDI's long-life growth asset is the Tier-1 Bankan Gold Project in Guinea, one of the largest undeveloped gold projects in Africa. Bankan is approaching construction-ready status with expected production of ~250,000oz per annum over more than 12 years.

Once Bankan is in production, PDI is targeting annual production exceeding 400,000oz by 2029 from its low-cost mining hub in Guinea, leveraging the proximity and synergies of the Kiniero and Bankan assets.

PDI is at a pivotal stage in its evolution, growing into a mid-tier, multi-mine West African gold producer, with a clear focus on sustainably developing its portfolio to create long-term value for shareholders and stakeholders.

COMPLIANCE STATEMENTS

Not an Offer

This announcement does not constitute an offer to sell or the solicitation of an offer to buy any securities. No securities regulatory authority has approved or disapproved the contents of this announcement. The securities referred to in this announcement have not been, and will not be, registered under the U.S. Securities Act of 1933, as amended, and may not be offered or sold in the United States, or to, or for the account or benefit of, U.S. persons, except pursuant to an exemption from, or in a transaction not subject to, U.S. registration requirements.

Forward-Looking Statements

This announcement contains forward-looking statements and forward-looking information within the meaning of applicable securities laws. Forward-looking statements include, but are not limited to, statements regarding gold production and guidance, expectations regarding exploration and development activities and potential, expectations regarding permitting and development funding for the Bankan Project. Forward-looking statements are based on assumptions and expectations as at the date of this announcement and are subject to known and unknown risks and uncertainties that may cause actual results to differ materially. Forward-looking statements are generally identified by words such as "will", "expect", "anticipate", "may", "could", "should", "plan", "estimate" and similar expressions.

Although PDI believes that the expectations reflected in the forward-looking statements are reasonable, undue reliance should not be placed on forward-looking statements since no assurance can be provided that such expectations will prove to be correct. Forward-looking statements are based on information available at the time those statements are made and/or good faith belief of the officers and directors of PDI as of that time with respect to future events and are subject to risks and uncertainties that could cause actual results to differ materially from those expressed in or suggested by the forward-looking statements. Forward-looking statements involve numerous risks and uncertainties. Factors that could cause actual results to differ materially include, but are not limited to, commodity price fluctuations, foreign exchange movements and general economic conditions, geopolitical, social and regulatory risks, operating and cost risks, the speculative nature of exploration and project development including the risks of obtaining necessary approvals, licenses, permits and funding, diminishing quantities or grades of reserves, changes to the legal and regulatory framework within which PDI operates or may in the future operate, environmental conditions including extreme weather conditions, recruitment and retention of personnel, industrial relations issues and litigation and other risks described in PDI's public disclosure documents filed on ASX and on SEDAR+.

Forward-looking statements speak only as of the date they are made. Except as required by applicable law, PDI undertakes no obligation to update or revise any forward-looking statements contained in this announcement. All forward-looking statements contained in this announcement are expressly qualified in its entirety by the above cautionary statement.

Production Targets

This announcement refers to PDI having expected production of 400,000oz per annum by 2029. The production targets in respect of the Bankan Project were released to ASX on 25 June 2025 in an announcement by PDI titled "Bankan DFS Confirms Outstanding Project Economics". The production targets in respect of Robex's Kiniero Project were released to ASX on 22 August 2025 in an announcement by Robex titled "Amendment to Kiniero Gold Project Technical Report". PDI confirms that all the material assumptions underpinning the production targets in the previous announcements continue to apply and have not materially changed.

1 All figures in this announcement are unaudited.
2 Based on an AUD:USD exchange rate of 0.689 as at 30 June 2026. Bullion valued at a spot price of US$4,026/oz. PDI's cash balance includes US$80M in restricted cash. One-off costs incurred during the quarter included merger related costs of US$36M and a royalty buy back of US$9M.


Primary Logo

News Provided by GlobeNewswire via QuoteMedia

RBX:CC
The Conversation (0)
Canadian Maple Leaf gold coin floating over stacked gold bars with glowing red lights.

Top 5 Junior Gold Mining Stocks on the TSXV in 2026

Junior gold stocks are seeing heightened interest in 2026 despite volatility in the gold price, which reached a new record high of nearly US$5,600 per ounce during the first quarter.The gold price may have fallen to the US$4,000 level in the second quarter, but plenty of upside potential remains... Keep Reading...
Peruvian Metals Production Update for the First Half of 2026 at Aguila Norte Processing Plant

Peruvian Metals Production Update for the First Half of 2026 at Aguila Norte Processing Plant

Peruvian Metals Corp. (TSXV: PER,OTC:DUVNF) (OTC Pink: DUVNF) ("Peruvian Metals" or the "Company") is pleased to provide an update regarding the mineral processing at its 80-per-cent-owned fully permitted Aguila Norte processing plant ("Aguila Norte" or the "Plant") located in Northern... Keep Reading...
Pile of gold bars over black background.

5 Best-performing Gold Stocks on the TSX in 2026

The gold price hit record highs in January 2026, and still up more than 25 percent from this time last year.Gold's growth may have been stalled by a variety of factors, including widespread economic and geopolitical uncertainty as the US and Israel clash with Iran and the US Federal Reserve... Keep Reading...
La Dama de Oro Discovery Vein Assays 7.5 grams over .45 metre

La Dama de Oro Discovery Vein Assays 7.5 grams over .45 metre

Providence Gold Mines Inc. (“Providence” or the “Company”) further to the June 29th, 2026, news release the Company is very pleased to provide gold assays from the channel sampling of the vein discovery. As reported, the discovery was made by the Company’s registered California geologist Mark... Keep Reading...
Wooden blocks with "M & A" stand vertically on white papers with charts, against a gray background.

Genesis Minerals Launches US$3.9 Billion Bid for Vault Minerals

Australian gold miner Genesis Minerals (ASX:GMD,OTCPL:GSISF) has submitted a US$3.9 billion cash-and-stock proposal to acquire Vault Minerals (ASX:VAU,OTCPL:REDLF), presenting a premium over Vault's existing merger agreement with Regis Resources (ASX:RRL,OTCPL:RGRNF).Under the proposed scheme of... Keep Reading...
Map of the Philippines with a red pushpin over Manila, text reads: South China Sea, Celebes Sea.

OceanaGold Commits US$1.9 Billion to Extend Philippine Gold Mine to 2037

Canadian miner OceanaGold (TSX:OGC) has committed US$1.9 billion to expand and extend the operational lifespan of its flagship Didipio gold and copper mine in the Philippines.The investment will push the operational life of the high-grade Didipio project, located across the provinces of Nueva... Keep Reading...

Interactive Chart

Latest Press Releases

Related News