Golden Independence Provides Independence Project Update

Golden Independence Provides Independence Project Update

Golden Independence Mining Corp. (CSE: IGLD) (OTCQB: GIDMF) (FSE: 6NN) (the "Company" or "Golden Independence") is pleased to provide an update on ongoing permitting and project-related activities at it's Independence heap-leach development project in Nevada.

  • NDEP approval for geochemical sampling & analysis plan
  • Commencement of NV Energy engineering study
  • NOI for additional resource and geotechnical drilling
  • Re-sampling and assaying of 725 feet of historical core drilling

"We continue to advance the Independence project along the development path, in addition to derisking the project." commented Jeremy Poirier, Chief Executive Officer. "We have engaged the leading power provider, NV Energy, to complete a scoping study along a new services corridor for stand-alone development. With the water rights we have already secured, the power corridor represents the last outstanding piece of critical project infrastructure required. In addition, we continue to refine the resource model with the resampling of over 725 feet of historical core and through the permitting for additional oxide resource expansion and geotechnical drilling. The expedited permitting and development timeline represents a significant strength of the project, relative to other projects in the State of Nevada."

NDEP Approval of Geochemical Sampling and Analysis Plan

The State of Nevada Division of Environmental Protection (NDEP) has approved the Company's geochemical sampling and analysis plan for the proposed open-pit heap-leach operation as outlined in the January 2022 Preliminary Economic Assessment. This represents the culmination of over one year's worth of humidity cell testing and analysis of 150 selected representative samples.

Commencement of Scoping Study with NV Energy

The Company has engaged NV Energy, the leading power and utility company servicing northern and southern Nevada, to provide an engineering study on providing independent power services for the development and operation of the Independence project. The commencement of this study comes as a result of a successful wildlife and fauna study across the proposed new corridor for independent power and services to support the proposed project.

NOI for Additional Resource and Geotechnical Drilling

The Company has filed two (2) amended Notice of Intent permits with the Nevada Bureau of Land Management (Nevada BLM) for additional oxide resource expansion and geotechnical drilling totalling 41 proposed drill holes totaling an estimated 27,500 feet.

Resampling and Assaying of Historical Core Drilling

The Company has also undertaken a program of relogging and resampling of historical drilling, as the deeper drilling on the project targeting the skarn mineralization left the upper portions of mineralization uninvestigated. Specifically, 725 feet of samples from IND#1 (from 144.5 - 136.5 ft and 325 - 607 ft) and IND#7 (8 - 97 ft, 197.5 - 213 ft, 236 - 312 ft, and 2,604 - 2,703 ft) have been sent to the lab for assays.

The technical content of this news release has been reviewed and approved by R. Tim Henneberry, P.Geo. (BC), a Director and President of Golden Independence Mining Corp. and a Qualified Person under National Instrument 43-101.

About Golden Independence Mining Corp.

Golden Independence Mining Corp. is a development company currently focused on the advanced-stage Independence project located adjacent to Nevada Gold Mine's Phoenix-Fortitude mine in the Battle Mountain-Cortez Trend of Nevada. The Independence project hosts an M&I resource of 334,300 ounces of gold and an Inferred resource of 847,000 ounces of gold with a substantial silver credit. A 2021 Preliminary Economic Assessment (PEA) outlined a low-cost heap leach operation focusing on the near-surface resource with total production of 195,443 ounces of gold at an all-in sustaining cost of US$1,078 per ounce of gold.

FOR FURTHER INFORMATION PLEASE CONTACT:

Jeremy Poirier, Interim Chief Executive Officer
Telephone: 604-722-9842

This press release contains forward-looking information (within the meaning of applicable Canadian securities legislation) that involves various risks and uncertainties regarding future events. Such forward-looking information includes statements based on current expectations involving a number of risks and uncertainties and such forward-looking statements are not guarantees of future performance of the Company. There are numerous risks and uncertainties that could cause actual results and the Company's plans and objectives to differ materially from those expressed in the forward-looking information in this news release, including without limitation, risks related to uncertainties inherent in the preparation of PEAs, drill results and the estimation of mineral resources, including changes in the economic parameters, risks relating to not securing agreements with third parties or not receiving required permits, risks associated with executing the Company's objectives and strategies, including costs and expenses, as well as those risk factors discussed in the Company's most recently filed management's discussion & analysis. Actual results and future events could differ materially from those anticipated in such information. This forward-looking information is based on estimates and opinions of management on the date hereof and is expressly qualified by this notice. Risks and uncertainties about the Company's business are more fully discussed in the Company's disclosure materials filed with the securities regulatory authorities in Canada at www.sedar.com. The Company assumes no obligation to update any forward-looking information or to update the reasons why actual results could differ from such information unless required by applicable law.

To view the source version of this press release, please visit https://www.newsfilecorp.com/release/126866

News Provided by Newsfile via QuoteMedia

IGLD:CNX
The Conversation (0)
Golden Independence Announces Appointment to Board of Directors

Golden Independence Announces Appointment to Board of Directors

Golden Independence Mining Corp. (CSE: IGLD) (OTCQB: GIDMF) (FSE: 6NN) (the "Company" or "Golden Independence") is pleased to announce that Jordan Carroll has been appointed to the Board of Directors of the Company.

Mr. Carroll is a certified electrician and has extensive experience in mining operations and mineral extraction. Mr. Carroll led a team involved in the commissioning of the Rio Tinto Alcan aluminum smelter located in Kitimat, B.C. and has prospected and owned placer mine claims. Mr. Carroll was formerly a director of American Battery Minerals Corp as well as Pike Mountain Minerals Inc., and is currently a director of J4 Ventures Inc. He has completed courses in public company governance through Simon Fraser University.

News Provided by Newsfile via QuoteMedia

Keep reading...Show less
Golden Independence Announces Change to Board of Directors

Golden Independence Announces Change to Board of Directors

Golden Independence Mining Corp. (CSE: IGLD) (OTCQB: GIDMF) (FSE: 6NN) (the "Company" or "Golden Independence") is pleased to announce that Ben Hinkle has been appointed to the Board of Directors of the Company.

"We are excited to welcome Ben to the Board," commented Jeremy Poirier, Interim Chief Executive Officer. "Ben brings a wealth of knowledge and experience in resource modelling that will not only advance our knowledge and understanding of the Independence Project but will also aid us in identifying other opportunities."

News Provided by Newsfile via QuoteMedia

Keep reading...Show less
Golden Independence Acquires Fraser Lake Copper Porphyry Project

Golden Independence Acquires Fraser Lake Copper Porphyry Project

Golden Independence Mining Corp. (CSE: IGLD) (OTCQB: GIDMF) (FSE: 6NN) (the "Company" or "Golden Independence") announces the acquisition by staking of the Fraser Lake copper project located in the Quesnel Trough of Central British Columbia. The project is comprised of three claim blocks totalling approximately 9,900 hectares and are located between 40 to 55 kilometres northwest of Fraser Lake, BC.

"The addition of the Fraser Lake copper project provides the Company with portfolio diversification, at a very low cost due to staking and without the typical encumbrances of royalties or work commitments," commented Jeremy Poirier, Chief Executive Officer. "This large land position within the prolific Quesnel Trough is prospective for copper porphyries of which gold and molybdenum are typically associated. We are currently reviewing the historical data on the project, including geophysical surveys completed in the late 2000's, and will provide an update on exploration plans once completed."

News Provided by Newsfile via QuoteMedia

Keep reading...Show less
Golden Independence Announces Results from Ongoing Exploration at the Independence Project, Nevada

Golden Independence Announces Results from Ongoing Exploration at the Independence Project, Nevada

Golden Independence Mining Corp. (CSE: IGLD) (OTCQB: GIDMF) (FSE: 6NN) (the "Company") is pleased to provide an update from ongoing exploration activities at the Company's Independence Oxide Heap Leach project (the "Project") which adjoins Nevada Gold Mines' Phoenix-Fortitude mining operations in the Battle Mountain-Cortez trend of Nevada.

Since tabling a PEA for near-surface heap-leach operation at the Project, the Company has been focused on improving the metrics of the project which yielded an after-tax NPV5% of US$45M and IRR of 22%. Specifically, exploration has been focused on delineating additional near-surface oxide resources to expand the open pit and reclassify waste with mineralized material. Both of the aforementioned would have the possibility to increase the production profile, extend the mine life, and improve project economics from a cost and valuation perspective (i.e., NPV and IRR).

News Provided by Newsfile via QuoteMedia

Keep reading...Show less
Golden Independence Announces Update on Permitting for the Independence Oxide Heap Leach Project, Nevada

Golden Independence Announces Update on Permitting for the Independence Oxide Heap Leach Project, Nevada

Golden Independence Mining Corp. (CSE: IGLD) (OTCQB: GIDMF) (FRA:6NN) (the "Company") is pleased to announce an update on the ongoing permitting activities for the Company's Independence Oxide Heap Leach project (the "Project") which adjoins Nevada Gold Mines' Phoenix-Fortitude mining operations in the Battle Mountain-Cortez trend of Nevada.

The Company has engaged EM Strategies, a WestLand Resources Inc. Company, to conduct baseline biological and cultural studies to facilitate an engineering study for the powerline (and production water pipeline) route to develop and operate the Project. The results of the 2022 field surveys will be presented in a Baseline Biology Report (BBR), which will include data from field surveys performed in 2021 and incorporate relevant botanical and wildlife data from previous surveys performed at the adjacent Phoenix Mine, and will be submitted to the Nevada Bureau of Land Management (BLM) for review. These studies will support the engagement with the numerous state and federal agencies to permit the utility corridor for the proposed power and water lines as outlined in the Preliminary Economic Assessment( PEA), and is inclusive of a 300-foot buffer.

News Provided by Newsfile via QuoteMedia

Keep reading...Show less
Horizon Minerals Limited  First Gold Pour - Boorara Gold Project

Horizon Minerals Limited First Gold Pour - Boorara Gold Project

Perth, Australia (ABN Newswire) - Horizon Minerals Limited (ASX:HRZ) is pleased to provide an update on operations and gold production from the Boorara gold project ("Boorara"). The first stockpile of 56,654 wmt @ 0.8g/t Au was accepted by Paddington early in December 2024, and ongoing haulage has continued throughout December and into January 2025.

HIGHLIGHTS

- On Tuesday 14 January 2025, Horizon poured its first gold bar from Boorara under the Ore Sale Agreement with Paddington Mill.

- Horizon entered into an Ore Sale Agreement with Norton Gold Fields' Paddington Mill for 1.24Mt of Boorara ore for processing over 18 months.

- Horizon approved the development of Boorara in late July 2024 to mine a series of four open pits containing 1.24Mt of ore at 1.24g/t Au for 49.5koz of gold.

- The first stockpile of approximately 56k wmt of Boorara ore has been hauled to Paddington over December 2024 and January 2025 for processing.

- Open pit mining is progressing safely however is running behind schedule, mainly due to lack of dust suppression via water trucks which were down for repairs and since then have been repaired and are operational.

As of 14 January 2025, the entire stockpile No.1 had been hauled to the Paddington Mill ROM. Prior to this date, and early in January 2025 Horizon achieved 50% of the delivery schedule and agreed the first invoice estimate with Paddington which is now payable on or about 21 January 2025.

At the same time mining continues at Boorara pits 2 and 4 building the next stockpile for haulage. Commenting on the mining progress, Managing Director and CEO Mr Grant Haywood said:

"We are delighted to become Australia's newest gold producing company in 2025. We have a Mineral Resource of 1.8Moz across our projects and developing a sustainable gold production pipeline which includes numerous projects that are ready for a Final Investment Decision, such as Penny's Find and the Cannon projects. With the cashflow we expect to generate from Boorara and our other advanced projects, we will seek to use this production pipeline to feed a refurbished Black Swan mill after completion of our proposed merger with Poseidon Nickel Limited."

*To view photographs, please visit:
https://abnnewswire.net/lnk/056J6Y2B



About Horizon Minerals Limited:  

Horizon Minerals Limited (ASX:HRZ) is a gold exploration and mining company focussed on the Kalgoorlie and Menzies areas of Western Australia which are host to some of Australia's richest gold deposits. The Company is developing a mining pipeline of projects to generate cash and self-fund aggressive exploration, mine developments and further acquisitions. The Teal gold mine has been recently completed.

Horizon is aiming to significantly grow its JORC-Compliant Mineral Resources, complete definitive feasibility studies on core high grade open cut and underground projects and build a sustainable development pipeline.

Horizon has a number of joint ventures in place across multiple commodities and regions of Australia providing exposure to Vanadium, Copper, PGE's, Gold and Nickel/Cobalt. Our quality joint venture partners are earning in to our project areas by spending over $20 million over 5 years enabling focus on the gold business while maintaining upside leverage.

News Provided by ABN Newswire via QuoteMedia

Keep reading...Show less
Freegold Extends Mineralization to the West and SouthWest Intersecting 1.88 g/t Au over 54.2 metres and 1.58 g/t Au over 60 metres at Golden Summit

Freegold Extends Mineralization to the West and SouthWest Intersecting 1.88 g/t Au over 54.2 metres and 1.58 g/t Au over 60 metres at Golden Summit

GS2422 Higher grade at depth and to the west

  • 157 g/t Au over 3 metres from 299 metres
  • 1.88 g/t Au over 54.2 metres starting at 499.8 metres
  • 1.58 g/t Au over 60 metres from 743 metres

GS2417 – Higher grade within the south-southwest trend

News Provided by Canada Newswire via QuoteMedia

Keep reading...Show less
Element79 Announces Proposed Spin Out and Merger

Element79 Announces Proposed Spin Out and Merger

(TheNewswire)

Element79 Gold Corp.

VANCOUVER, BC T heNewswire January 13, 2025 Element79 Gold Corp. (CSE: ELEM) (OTC: ELMGF) (FSE: 7YS) ("Element79", or the "Company") is excited to announce that, in connection with its proposed spin out transaction, it has entered an arrangement agreement dated January 10, 2025 (the " Arrangement Agreement "), with its majority owned subsidiary, Synergy Metals Corp. (" Synergy "), and that it has also entered into a merger agreement dated January 10, 2025 (the " Merger Agreement "), with Synergy, Synergy's wholly owned subsidiary, 1515041 B.C. Ltd. (" Synergy SubCo "), and 1425957 B.C. Ltd. (" 142 "), as further described below.

News Provided by TheNewsWire via QuoteMedia

Keep reading...Show less

Latest Press Releases

Related News

×