- AustraliaNorth AmericaWorld
Investing News NetworkYour trusted source for investing success
- Lithium Outlook
- Oil and Gas Outlook
- Gold Outlook Report
- Uranium Outlook
- Rare Earths Outlook
- All Outlook Reports
- Top Generative AI Stocks
- Top EV Stocks
- Biggest AI Companies
- Biggest Blockchain Stocks
- Biggest Cryptocurrency-mining Stocks
- Biggest Cybersecurity Companies
- Biggest Robotics Companies
- Biggest Social Media Companies
- Biggest Technology ETFs
- Artificial Intellgience ETFs
- Robotics ETFs
- Canadian Cryptocurrency ETFs
- Artificial Intelligence Outlook
- EV Outlook
- Cleantech Outlook
- Crypto Outlook
- Tech Outlook
- All Market Outlook Reports
- Cannabis Weekly Round-Up
- Top Alzheimer's Treatment Stocks
- Top Biotech Stocks
- Top Plant-based Food Stocks
- Biggest Cannabis Stocks
- Biggest Pharma Stocks
- Longevity Stocks to Watch
- Psychedelics Stocks to Watch
- Top Cobalt Stocks
- Small Biotech ETFs to Watch
- Top Life Science ETFs
- Biggest Pharmaceutical ETFs
- Life Science Outlook
- Biotech Outlook
- Cannabis Outlook
- Pharma Outlook
- Psychedelics Outlook
- All Market Outlook Reports

Activities Report for the Quarter Ended 30 September 2023
GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) reports on its activities for the quarter ended 30 September 2023 (the “Quarter”), focused on the ongoing production ramp-up of both the underground mine and the processing plant to achieve steady-state production by the end of 2023, at its 60%-owned Abra Base Metals Mine (“Abra” or the “Project”) located in the Gascoyne region of Western Australia.
HIGHLIGHTS
- Quarterly record mining and processing levels achieved – ore mined of 293,919t at 5.5% lead and 19.0g/t silver, and processed 283,458t at 5.0% lead and 21.1g/t silver.
- Three lead concentrate shipments totalling 21,626t completed, more than doubling revenue from the previous quarter to ~A$45.4 million and generating positive operating cash flows.
- Underground development achieved a new quarterly record of 2,140m advance with the decline reaching 1,212mRL (333m vertically below the surface). New quarter underground ore drive development record of 1,202m and stope production record of 199,225t at 6.1% lead.
- Lead grade is expected to improve as new work areas are established and the ratio of stoping ore to development ore increases towards planned levels.
- Paste fill plant commissioned and paste filling of first stope completed in September 2023.
- Abra opening ceremony was held on 13 September 2023. The mine was officially opened by the President of Toho Zinc (Mr. Masahito Ito) and the Galena/Abra Chairman (Mr. Adrian Byass).
- Group cash balance at Quarter-end of A$14.4 million.
- December quarter mining plans set to achieve over 2,400m development and over 320,000t ore production (260,000t stope production) expecting to process over 320,000t of ore in the December quarter. Targeting ~25-30kt of lead concentrate shipments expected to generate increased operating cash flows and net growth in the group cash balance.
- CY2023 guidance updated, mainly due to the slower than expected ramp-up in lead grade during the June and September quarters (see page 10 for more details).
Managing Director, Tony James commented, “Continued improvement was achieved on a quarter-on-quarter basis with new record highs for mining and processing. This improvement is expected to continue in the December quarter as production edges closer to steady-state. The new MRE published in August strongly supports our knowledge of the Abra deposit, re- enforcing the global metal content. This underpins the long mine life and our improved understanding of this orebody and this new mineral province.
Importantly, we are forecasting the December quarter to be the one where our overall group cash levels start to build.
It has also been particularly satisfying seeing the improvement in safety with a reduction in key safety statistics on site. The Abra team continues to work very hard in unlocking the challenges we have faced in 2023, showing real determination and focus to get the mine up to the designed production levels.”
ABRA BASE METALS MINE (60%-OWNED)
Abra comprises a granted Mining Lease, M52/0776 and surrounding Exploration Licence E52/1455, together with several co-located General Purpose and Miscellaneous Leases. The Project is 100% owned by Abra Mining Pty Limited (“AMPL” the Abra Project joint-venture entity), which in turn is 60% owned by Galena and 40% owned by Toho Zinc Co., Ltd. (“Toho”) of Japan.
Abra is fully permitted, and construction of the processing plant and surface infrastructure was completed in December 2022. First production of its lead-silver concentrate occurred in January 2023 with first product shipment achieved in March 2023.
Review of operations
During the Quarter, new quarterly record mining and processing levels were achieved despite mining stope production delays caused by access timing, paste plant commissioning and processing plant downtime associated with unplanned (conveyor belt tears and crusher blockage) and planned maintenance work (first full mill re-line).
In September, a mine development record was set with 807m of lateral and vertical development achieved during the month. To achieve the mine’s production rate and gain access to the required stoping areas, the mine needs to consistently achieve its monthly development target of over 800m well into 2024. This level of development is required for the mine to open as many work areas as possible (particularly higher-grade stopes) to consistently achieve steady-state production levels. Equipment and personnel levels are now well established to achieve the target levels.
Click here for the full ASX Release
This article includes content from Galena Mining, licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.
Abra Construction At 97% Complete – First Ore Stockpiled For January Processing
GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 97% complete as of 30 November 2022. Processing plant commissioning is progressing quickly with practical completion now expected in December 2022. Ore currently being mined from underground is being stockpiled in readiness for processing to begin in January 2023. Concentrate production will commence January 2023.
Managing Director, Tony James commented, “Record underground development in November with delivery of the first 9,000t of ore to the ROM pad along with successful plant commissioning to date puts Abra on the verge of a quick transition into production. Recruitment and other operational readiness activities are well advanced in preparation for January production”.
Figure 1 – First material being tipped into the crusher during commissioning (Photo 26 November).
Figure 2 – Crushing and screening plant commissioning (Photo 26 November).
The following link will show a short video of the Abra crusher commissioning. https://youtube.com/shorts/iSG58MiW_3o
Update on Abra Project progress
Overall progress continues as planned, with first concentrate production expected in Q1 CY2023, following ore commissioning in January 2023. Practical completion of the processing plant is now expected ahead of schedule in December 2022. The processing plant engineering, procurement and construction has reached 99% complete. Piping and electrical works have made significant progress and at the end of November were 96% and 92% complete, respectively. Mechanical items installation is almost complete at 99%.
In November, the first material was crushed and screened as part of the staged commissioning process. The crushing plant ran at design capacity and all commissioning milestones were successfully achieved. Dry commissioning also progressed in most areas of the plant including water and air services, tailings and concentrate thickening, grinding and reagents. Dry commissioning of the remaining areas will be completed in December. Water commissioning commenced in the tailings and concentrate thickening areas of the plant and the remaining areas are expected to be wet commissioned by the end of December. The remaining commissioning schedule is unchanged from the last update and is shown below in Table 1.
Click here for the full ASX Release
This article includes content from Galena Mining, licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.
Abra Construction At 92% Complete – Reaches First Ore Underground
Managing Director, Tony James commented, “Reaching first ore underground is extremely rewarding for everyone involved in the project. To see for the first time what we have predicted and interpreted as the Abra orebody delivers a significant step forward for the project. Record development metres in October has taken the mine to the ore and we continue to establish key underground infrastructure with the completion of the 6m diameter surface rise that will be the primary return airway.”
Update on Abra Project progress
Overall progress continues to remain in line for Project completion, with first commercial production expected in Q1 CY2023. The processing plant engineering, procurement and construction has reached 97% complete. Structural steel has been completed in October and mechanical installations are at 96% complete. Piping at 80% and electrical at 71% complete continue to progress quickly.
Pacific Energy’s Hybrid 10MW LNG/solar power station completed full integration with the solar power supply, dry commissioning of the crushing and screening areas was completed in early November and first rock crushing is scheduled for late November. Grinding section dry and wet commissioning will commence in the second half of November and is planned for completion by mid-December. The remaining commissioning schedule is unchanged from the last update and is shown below in Table 1.
Mine decline development continued during October. A total of 311m was developed with the decline reaching 1,284mRL. October represents the highest individual development month since the first cut was fired in the portal in October 2021. The decline location is 266m vertically below the surface and is 29m vertically below the original top of the orebody (1313mRL). Underground drilling has now identified mineralisation as high as 1330mRL which is currently being reviewed for potential extraction. The 1300mRL ore access drive reached first ore in early November (See ASX announcement 14 November 2022).
The 1290mRL horizon is a significant work area for development as underground infrastructure for pumping, ventilation, second means of egress and power are all distributed from this level outwards into the development network. All this infrastructure is currently being established and will result in an increased focus on lateral development and lower decline development in the short term.
Click here for the full ASX Release
This article includes content from Galena Mining, licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.
Abra Mine Reaches Ore
Managing Director, Tony James commented, “Reaching first ore underground delivers another significant step in bringing the Abra project on-line. The first cut in the portal was taken in October 2021, and now 2,949m later and 250m below surface we have reached the orebody. Special acknowledgement needs to be given to Byrnecut and the Abra mining team for achieving this milestone, and everyone involved should be very proud of what they have achieved. It’s also important to acknowledge Pacific Energy and the Abra project team for the faultless commissioning of the power station and completing the full integration of the solar system”.
First ore heading underground has been reached on the 1300mRL access drive. Project to date (PTD) underground development to this point in time was 2,949m and first ore is 250m below the surface. Figure 2 below shows the mine development completed to the end of October 2022. The second underground development Jumbo has commenced at Abra in line with multiple headings being established and underground development is expected to increase accordingly. Underground grade control drilling continues and the 6m diameter return airway shaft drilling has been completed in November through to the surface.
On 20 October, the site changed over to mains power station with the commissioning of the Pacific Energy hybrid 10MW gas/solar/BESS power station. On the 10 November the system was fully integrated with the successful integration of the 6MW solar panels. The mine and general site infrastructure is running on mains power and plant commissioning to date includes the energisation of the crushing/screening sections.
Click here for the full ASX Release
This article includes content from Galena Mining, licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.
Galena Mining Activities Report For Quarter Ended 30 September 2022
GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) reports on its activities for the quarter ended 30 September 2022 (the “Quarter”), primarily focused on construction of its 60%- owned Abra Base Metals Mine (“Abra” or the “Project”) located in the Gascoyne region of Western Australia.
Highlights
- Abra Project 87% complete at end of the Quarter (14% of construction works completed during the Quarter). Project focus remains on underground access to the orebody and completion of the processing plant and remaining surface infrastructure.
- Underground development achieved 771m advance during the Quarter remaining on schedule with the decline reaching 1,300mRL. The decline is 13m below the top of the orebody and 250m below the surface.
- Overall processing plant construction has reached 93% complete. Plant engineering and drafting work is 100% complete and site construction work is 90% complete.
- All key overseas supplied equipment has arrived on site.
- Completed oversubscribed placement to raise A$17.2M.
- US$25M final debt drawdown was completed under the Taurus Debt Facilities.
- Cash balance at Quarter-end A$60.5M.
ABRA BASE METALS MINE (60%-OWNED)
Abra comprises a granted Mining Lease, M52/0776 and surrounding Exploration Licence E52/1455, together with several co-located General Purpose and Miscellaneous Leases. The Project is 100% owned by Abra Mining Pty Limited (“AMPL” the Abra Project joint-venture entity), which in turn is 60% owned by Galena, with the remainder owned by Toho Zinc Co., Ltd. (“Toho”) of Japan.
Abra is fully permitted and under construction. First production of its high-value, high-grade lead- silver concentrate is currently scheduled for the first quarter of 2023 calendar-year.
Click here for the full ASX Release
This article includes content from Galena Mining, licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.
Latest News
Latest Press Releases
Related News
TOP STOCKS
Investing News Network websites or approved third-party tools use cookies. Please refer to the cookie policy for collected data, privacy and GDPR compliance. By continuing to browse the site, you agree to our use of cookies.