Galena Mining

Activities Report for the Quarter Ended 30 September 2023

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) reports on its activities for the quarter ended 30 September 2023 (the “Quarter”), focused on the ongoing production ramp-up of both the underground mine and the processing plant to achieve steady-state production by the end of 2023, at its 60%-owned Abra Base Metals Mine (“Abra” or the “Project”) located in the Gascoyne region of Western Australia.


HIGHLIGHTS

  • Quarterly record mining and processing levels achieved – ore mined of 293,919t at 5.5% lead and 19.0g/t silver, and processed 283,458t at 5.0% lead and 21.1g/t silver.
  • Three lead concentrate shipments totalling 21,626t completed, more than doubling revenue from the previous quarter to ~A$45.4 million and generating positive operating cash flows.
  • Underground development achieved a new quarterly record of 2,140m advance with the decline reaching 1,212mRL (333m vertically below the surface). New quarter underground ore drive development record of 1,202m and stope production record of 199,225t at 6.1% lead.
  • Lead grade is expected to improve as new work areas are established and the ratio of stoping ore to development ore increases towards planned levels.
  • Paste fill plant commissioned and paste filling of first stope completed in September 2023.
  • Abra opening ceremony was held on 13 September 2023. The mine was officially opened by the President of Toho Zinc (Mr. Masahito Ito) and the Galena/Abra Chairman (Mr. Adrian Byass).
  • Group cash balance at Quarter-end of A$14.4 million.
  • December quarter mining plans set to achieve over 2,400m development and over 320,000t ore production (260,000t stope production) expecting to process over 320,000t of ore in the December quarter. Targeting ~25-30kt of lead concentrate shipments expected to generate increased operating cash flows and net growth in the group cash balance.
  • CY2023 guidance updated, mainly due to the slower than expected ramp-up in lead grade during the June and September quarters (see page 10 for more details).

Managing Director, Tony James commented, “Continued improvement was achieved on a quarter-on-quarter basis with new record highs for mining and processing. This improvement is expected to continue in the December quarter as production edges closer to steady-state. The new MRE published in August strongly supports our knowledge of the Abra deposit, re- enforcing the global metal content. This underpins the long mine life and our improved understanding of this orebody and this new mineral province.

Importantly, we are forecasting the December quarter to be the one where our overall group cash levels start to build.

It has also been particularly satisfying seeing the improvement in safety with a reduction in key safety statistics on site. The Abra team continues to work very hard in unlocking the challenges we have faced in 2023, showing real determination and focus to get the mine up to the designed production levels.”

ABRA BASE METALS MINE (60%-OWNED)

Abra comprises a granted Mining Lease, M52/0776 and surrounding Exploration Licence E52/1455, together with several co-located General Purpose and Miscellaneous Leases. The Project is 100% owned by Abra Mining Pty Limited (“AMPL” the Abra Project joint-venture entity), which in turn is 60% owned by Galena and 40% owned by Toho Zinc Co., Ltd. (“Toho”) of Japan.

Abra is fully permitted, and construction of the processing plant and surface infrastructure was completed in December 2022. First production of its lead-silver concentrate occurred in January 2023 with first product shipment achieved in March 2023.

Review of operations

During the Quarter, new quarterly record mining and processing levels were achieved despite mining stope production delays caused by access timing, paste plant commissioning and processing plant downtime associated with unplanned (conveyor belt tears and crusher blockage) and planned maintenance work (first full mill re-line).

In September, a mine development record was set with 807m of lateral and vertical development achieved during the month. To achieve the mine’s production rate and gain access to the required stoping areas, the mine needs to consistently achieve its monthly development target of over 800m well into 2024. This level of development is required for the mine to open as many work areas as possible (particularly higher-grade stopes) to consistently achieve steady-state production levels. Equipment and personnel levels are now well established to achieve the target levels.


Click here for the full ASX Release

This article includes content from Galena Mining, licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.


G1A:AU
Galena Mining

Galena Mining Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

The Conversation (0)
Galena Mining (ASX:G1A)

Galena Mining


Keep reading...Show less
Galena Mining

Abra Construction At 97% Complete – First Ore Stockpiled For January Processing

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 97% complete as of 30 November 2022. Processing plant commissioning is progressing quickly with practical completion now expected in December 2022. Ore currently being mined from underground is being stockpiled in readiness for processing to begin in January 2023. Concentrate production will commence January 2023.

Keep reading...Show less
Galena Mining

Abra Construction At 92% Complete – Reaches First Ore Underground

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 92% complete as of 31 October 2022. Underground mine has reached the first ore (see ASX announcement 14 November 2022) and plant commissioning continues in several key areas with the project focussed on achieving first concentrate production in Q1 2023.
Keep reading...Show less
Galena Mining

Abra Mine Reaches Ore

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the underground development at its Abra Base Metals Mine (“Abra” or the “Project”) has reached the Abra orebody. Commissioning has commenced in several key areas of the processing facility and the Power Station (Pacific Energy) completed full integration of the hybrid gas/solar/battery energy storage system (BESS) power station on 10 November. The project remains on track for first concentrate production in Q1 2023.
Keep reading...Show less
Galena Mining

Galena Mining Activities Report For Quarter Ended 30 September 2022

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) reports on its activities for the quarter ended 30 September 2022 (the “Quarter”), primarily focused on construction of its 60%- owned Abra Base Metals Mine (“Abra” or the “Project”) located in the Gascoyne region of Western Australia.

Keep reading...Show less
Miners filing out paperwork.

Northern Territory Finalises Mine Legacy Remediation Program

The Northern Territory's government has finalised a AU$5.5 million six month mine legacy remediation program for sites located in the Tennant Creek area, a January 9 press release states.

The next phase will involve Alice Springs, where further works are scheduled for later this year.

“Mining has been an integral part of the Northern Territory’s history for more than 150 years, but historical mining activities have left behind a range of legacy features such as open shafts, degraded infrastructure, tailings dams, and waste rock dumps,” said Gerard Maley, deputy chief minister and minister for mining and energy.

Keep reading...Show less
Asian Battery Metals PLC

High grade Massive Sulphide Intercepts Confirmed at Oval

Asian Battery Metals PLC (ABM or the Company, ASX: AZ9) is pleased to announce the remaining laboratory assay results of the 2024 Phase 2 drilling program for samples from drillholes OVD026, OVD027, OVD028, and OVD029. The details of the assays are provided in Table 1.
Keep reading...Show less
Stock chart over globe.

Canadian Markets Steady Amid Trump Tariff Speculation and Renewed Greenland Interest

Canada's main stock index gained on Wednesday (January 8), driven by strength in tech and mining stocks.

Investors continue to weigh the impact of potential US trade policy changes under President-elect Donald Trump, as well as his renewed interest in taking ownership of Greenland, an idea he first raised in 2019.

The S&P/TSX Composite Index (INDEXTSI:OSPTX) closed at 25,049.66, recovering from two consecutive sessions of losses following Justin Trudeau's resignation as Canadian prime minister on Monday (January 6).

Keep reading...Show less
Stock chart with Canadian flag.

Trudeau Resigns, Canadian and US Markets React

Canadian markets showed mixed reactions following Prime Minister Justin Trudeau’s resignation.

The S&P/TSX Composite Index (INDEXTSI:OSPTX) closed lower on Monday (January 6), while the Canadian dollar gained strength against the US dollar, reflecting diverging investor sentiment.

The index dropped by 142.14 points to settle at 24,995.93, marking a 0.57 percent decline from its starting point for the day. Meanwhile, the Canadian dollar rose to 69.7 cents US, reaching a near three week high.

Keep reading...Show less
Australian dollars Australian flag in the background.

5 Australian Mining Grants Open for Applications in 2025

As 2025 begins, companies in the mining sector are gearing up for another year of work.

In Australia, there are many chances for explorers and developers to access government funding at both the state and federal level. The list below includes five programs that are open for applications, or will be soon.

Read on to learn more about what companies can apply and how much money is up for grabs.

Keep reading...Show less
Jay Martin, city skyline and gold bars.

VRIC 2025 Preview — Jay Martin Talks Resource Wars, Geopolitics and How to Invest

The next Vancouver Resource Investment Conference (VRIC) is set to run from January 19 to 20, 2025, and Jay Martin, president of Cambridge House, joined the Investing News Network ahead of time to discuss the event.

Looking at the resource sector, Martin, who also hosts the Jay Martin Show on YouTube, said the current decade has been defined by chaos and uncertainty, with no signs of a slowdown any time soon.

With that in mind, his macro thesis on commodities remains steadfast, and he's watching three key drivers.

Keep reading...Show less
Galena Mining

Galena Mining Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

Latest Press Releases

Related News

×