Cameco Announces McArthur River/Key Lake Operation Resumes Production

Cameco Announces McArthur River/Key Lake Operation Resumes Production

All amounts in Canadian dollars unless specified otherwise

Cameco (TSX: CCO; NYSE: CCJ) today announced that the Key Lake mill and McArthur River mine have returned to full production activities following a disruption caused by flooding in northern Saskatchewan. Our 2026 consolidated production outlook remains unchanged.

On May 10, 2026, Cameco announced that Key Lake had temporarily halted production activities and McArthur River had reduced activities due to the impact of flooding in northern Saskatchewan. While our northern Saskatchewan sites were not directly impacted by flood waters, the Smoothstone River Bridge, which is on the primary route we use to transport supplies to the McArthur River and Key Lake sites, partially collapsed due to flood waters. There were also weight and traffic restrictions on the alternative roadway, which interrupted the delivery of critical operating materials.

We are in regular contact with the Saskatchewan Ministry of Highways, and while the timing to restore access to our primary supply route is still being confirmed, we have now been able to consistently deliver the volume of critical materials required to resume full operations at Key Lake and McArthur River using the secondary route. However, as is the case every spring season, there remains a risk that continued thawing and precipitation events could result in further road restrictions, which could cause delays in future deliveries of critical operating materials to our sites.

Our 2026 production plan for the McArthur River/Key Lake operation has not been impacted by this disruption. Cigar Lake mine was not impacted and continues to operate. Our consolidated 2026 production outlook remains unchanged at 19.5 million to 21.5 million pounds of U 3 O 8 (our share).

Caution about forward-looking information

This news release includes statements and information about expectations for the future, which are referred to as forward-looking information. This forward-looking information is based on current views, which can change significantly, and actual results and events may be significantly different from what is currently expected. Examples of forward-looking information in this news release include: statements regarding our 2026 consolidated production outlook and production plan; the uncertainty of the timing to restore access to our primary supply route; and the possibility of further road restrictions resulting in delays in future deliveries of operating materials. Material risks that could lead to different results in our 2026 production plan and outlook include: the risk of delays in restoring access to our primary supply route; delays in future delivery of operating materials due to spring thawing and precipitation events, or for other reasons; or other factors that prevent us from achieving the expected production plan and outlook. In presenting the forward-looking information, we have made material assumptions which may prove incorrect about our supply routes and our ability to deliver operating materials, and otherwise about our ability to meet our production plan and outlook. Other material risks and assumptions which may impact our 2026 production plan and outlook are described in greater detail in Cameco's current annual information form and its most recent annual and subsequent quarterly management's discussion and analysis. Forward-looking information is designed to help you understand management's current views of our near-term and longer-term prospects, and it may not be appropriate for other purposes. Cameco will not necessarily update this information unless required by securities laws.

Profile

Cameco is one of the largest global providers of the uranium fuel needed to power a secure energy future. Our competitive position is based on our controlling ownership of the world's largest high-grade reserves and low-cost operations, as well as significant investments across the nuclear fuel cycle, including ownership interests in Westinghouse Electric Company and Global Laser Enrichment. Utilities around the world rely on Cameco to provide global nuclear fuel solutions for the generation of safe, reliable, carbon-free nuclear power. Our shares trade on the Toronto and New York stock exchanges. Our head office is in Saskatoon, Saskatchewan, Canada.

As used in this news release, the terms we, us, our, the Company and Cameco mean Cameco Corporation and its subsidiaries unless otherwise indicated.

Investor inquiries
Cory Kos
306-716-6782
cory_kos@cameco.com

Media inquiries
Veronica Baker
306-385-5541
veronica_baker@cameco.com

News Provided by Business Wire via QuoteMedia

CCO:CC
The Conversation (0)
Standard Uranium Confirms Uranium Enrichment in All Winter 2026 Drill Holes at the Corvo Uranium Project

Standard Uranium Confirms Uranium Enrichment in All Winter 2026 Drill Holes at the Corvo Uranium Project

Standard Uranium Ltd. (TSXV: STND,OTC:STTDF) (OTCQB: STTDF) (FSE: 9SU0) ("Standard Uranium" or the "Company") is pleased to report a summary of geochemical assay results from its winter 2026 drill program at the Corvo Uranium Project ("Corvo", or the "Project") located near Wollaston Lake in... Keep Reading...
American Uranium Reports Completed Drilling Strengthens Lo Herma Uranium Resource Upgrade for Upcoming Scoping Study

American Uranium Reports Completed Drilling Strengthens Lo Herma Uranium Resource Upgrade for Upcoming Scoping Study

American Uranium Limited (ASX: AMU,OTC:AMUIF, OTCQB: AMUIF) announced that resource drilling at its Lo Herma ISR uranium project in Wyoming, is now completed with the final 32 mud rotary drill holes for approximately 12,757 meters (41,855 feet) across a total of 50 drill holes. The program was... Keep Reading...
Premier American Uranium Successfully Completes Drilling Program at Cebolleta Project, New Mexico and Delivers Samples for Advanced Metallurgical Testing

Premier American Uranium Successfully Completes Drilling Program at Cebolleta Project, New Mexico and Delivers Samples for Advanced Metallurgical Testing

Premier American Uranium Inc. ("PUR", the "Company" or "Premier American Uranium") (TSXV: PUR,OTC:PAUIF) (OTCQB: PAUIF) is pleased to announce the successful completion of its drilling program at the Company's wholly owned Cebolleta Uranium Project ("Cebolleta" or the "Project") in New Mexico.... Keep Reading...
Completed Drilling Strengthens Lo Herma Resource Upgrade

Completed Drilling Strengthens Lo Herma Resource Upgrade

American Uranium (AMU:AU) has announced Completed Drilling Strengthens Lo Herma Resource UpgradeDownload the PDF here. Keep Reading...
Generation to Present on the Emerging Growth Conference on July 15, 2026

Generation to Present on the Emerging Growth Conference on July 15, 2026

(TheNewswire) Generation Uranium invites individual and institutional investors as well as advisors and analysts, to attend its real-time, interactive presentation on the Emerging Growth Conference. Vancouver, British Columbia TheNewswire - July 9, 2026 - Generation Uranium Inc. (TSXV:... Keep Reading...
Generation Announces $350,000 Non-Brokered Flow Through Private Placement

Generation Announces $350,000 Non-Brokered Flow Through Private Placement

(TheNewswire) Vancouver, British Columbia July 3, 2026 TheNewswire Generation Uranium Inc. (TSX.V: GEN, OTCQB: GENRF, FRA: W85) ("Generation" or the "Company") is pleased to announce a non-brokered flow through private placement (the "Offering") for gross proceeds of up to $350,000. The Company... Keep Reading...

Interactive Chart

Latest Press Releases

Related News