Atico Produces 2.32 Million Pounds of Cu and 2,566 Ounces of Au in First Quarter 2023 and Resumes Full Operations at El Roble

Atico Produces 2.32 Million Pounds of Cu and 2,566 Ounces of Au in First Quarter 2023 and Resumes Full Operations at El Roble

Atico Mining Corporation (the "Company" or "Atico") (TSX.V: ATY | OTCQX: ATCMF) announces its operating results for the three months ended March 31, 2022 from its El Roble mine. Production for the quarter totaled 2.32 million pounds of copper and 2,566 ounces of gold in concentrates, a decrease of 51% and 3% for copper and gold, respectively, over the same period in 2022.

"At the El Roble mine we had a lower than usual copper head grade and output for the quarter as the mine plan called for transitioning through the lower grade areas of the deposit. The team anticipates that the operation will be moving back into higher copper grades during the second quarter and remain in these areas moving forward," said Fernando E. Ganoza, CEO. "For the remainder of the year, the operation is projected to make up for lower first quarter production and deliver on this year's set guidance. In parallel, we continue to make progress on the mine vicinity drilling with the goal to find additional reserves and resources."

First Quarter Operational Highlights

  • Production of 2.32 million pounds of copper contained in concentrates; a decrease of 51% over Q1 2022.
  • Production of 2,566 ounces of gold contained in concentrates; a decrease of 3% over Q1 2022.
  • Average processed tonnes per day of 747, a decrease of 10% over Q1 2022.
  • Copper head grade of 1.88%, a decrease of 47% over Q1 2022.
  • Gold head grade of 2.20 grams per tonne; an increase of 6% over Q1 2022.
  • Copper and gold recovery of 89.2% and 57.9%; a decrease of 3% for copper and gold over Q1 2022.

First Quarter Operational Details

Q1 2023 Total Q1 2022 Total % Change
Production (Contained in Concentrates)
Copper (000s pounds) 2,319 4,731 -51%
Gold (ounces) 2,566 2,636 -3%
Mine
Tonnes of ore mined 60,568 66,594 -9%
Mill
Tonnes processed 62,793 65,844 -5%
Tonnes processed per day 747 826 -10%
Copper grade (%) 1.88 3.55 -47%
Gold grade (g/t) 2.20 2.08 6%
Recoveries
Copper (%) 89.2 91.8 -3%
Gold (%) 57.9 59.7 -3%
Concentrates
Copper and Gold Concentrates (dmt) 5,813 10,719 -46%
Payable copper produced (000s lbs) 2,180 4,576 -52%

Note: Metal production figures are subject to adjustments based on final settlement. The reported results are preliminary in nature and are awaiting independent lab verification.

Concentrate Inventory

The number of shipments the Company can export in any given quarter depends on several variables some of which the Company does not control, hence there may be an inherent variability in tonnes shipped quarter to quarter.

Q1 2023 Total
Amounts in dry metric tonnes
Opening inventory 7,326
Production 5,813
Sales -6,475
Number of shipments 1
Closing inventory 6,647

Note: Concentrate figures are subject to adjustments based on final settlement.

El Roble Mine

The El Roble mine is a high grade, underground copper and gold mine with nominal processing plant capacity of 1,000 tonnes per day, located in the Department of Choco in Colombia. Its commercial product is a copper-gold concentrate.

Since obtaining control of the mine on November 22, 2013, Atico has upgraded the operation from a historical nominal capacity of 400 tonnes per day.

El Roble has Proven and Probable reserves of 1.00 million tonnes grading 3.02% copper and 1.76 g/t gold, at a cut-off grade of 1.3% copper equivalent as of September 30 th , 2020. Mineralization is open at depth and along strike and the Company plans to further test the limits of the deposit.

On the larger land package, the Company has identified a prospective stratigraphic contact between volcanic rocks and black and grey pelagic sediments and cherts that has been traced by Atico geologists for ten kilometers. This contact has been determined to be an important control on VMS mineralization on which Atico has identified numerous target areas prospective for VMS type mineralization occurrence, which is the focus of the current surface drill program at El Roble.

Qualified Person

Mr. Thomas Kelly (SME Registered Member 1696580), advisor to the Company and a qualified person under National Instrument 43-101 standards, is responsible for ensuring that the technical information contained in this news release is an accurate summary of the original reports and data provided to or developed by Atico.

About Atico Mining Corporation
Atico is a growth-oriented Company, focused on exploring, developing and mining copper and gold projects in Latin America. The Company generates significant cash flow through the operation of the El Roble mine and is developing its high-grade La Plata VMS project in Ecuador. The Company is also pursuing additional acquisition of advanced stage opportunities. For more information, please visit www.aticomining.com .

ON BEHALF OF THE BOARD

Fernando E. Ganoza
CEO
Atico Mining Corporation

Trading symbols: TSX.V: ATY | OTCQX: ATCMF

Investor Relations
Igor Dutina
Tel: +1.604.633.9022

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

No securities regulatory authority has either approved or disapproved of the contents of this news release. The securities being offered have not been, and will not be, registered under the United States Securities Act of 1933, as amended (the ‘‘U.S. Securities Act''), or any state securities laws, and may not be offered or sold in the United States, or to, or for the account or benefit of, a "U.S. person" (as defined in Regulation S of the U.S. Securities Act) unless pursuant to an exemption therefrom. This press release is for information purposes only and does not constitute an offer to sell or a solicitation of an offer to buy any securities of the Company in any jurisdiction.

Cautionary Note Regarding Forward Looking Statements

This announcement includes certain "forward-looking statements" within the meaning of Canadian securities legislation. All statements, other than statements of historical fact, included herein, without limitation the use of net proceeds, are forward-looking statements. Forward- looking statements involve various risks and uncertainties and are based on certain factors and assumptions. There can be no assurance that such statements will prove to be accurate, and actual results and future events could differ materially from those anticipated in such statements. Important factors that could cause actual results to differ materially from the Company's expectations include uncertainties relating to interpretation of drill results and the geology, continuity and grade of mineral deposits; uncertainty of estimates of capital and operating costs; the need to obtain additional financing to maintain its interest in and/or explore and develop the Company's mineral projects; uncertainty of meeting anticipated program milestones for the Company's mineral projects; and other risks and uncertainties disclosed under the heading "Risk Factors" in the prospectus of the Company dated March 2, 2012 filed with the Canadian securities regulatory authorities on the SEDAR website at www.sedar.com



Primary Logo

News Provided by GlobeNewswire via QuoteMedia

ATY:CA
The Conversation (0)
Atico Mining Announces Completion NI 43-101 Feasibility Study for the La Plata Project in Ecuador

Atico Mining Announces Completion NI 43-101 Feasibility Study for the La Plata Project in Ecuador

Atico Mining Corporation (the "Company" or "Atico") (TSX.V: ATY | OTC: ATCMF) is pleased to announce the results of the Definitive Feasibility Study (the "DFS" or the "Study") for its 100% owned La Plata Project ("La Plata") located in Ecuador. The DFS was prepared in accordance with the National Instrument 43-101 Standards of Disclosure for Mineral Projects ("NI 43-101"). Please note that all financial figures in this press release are in United States dollars, unless otherwise noted.

Key Highlights:

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
Atico Reports Consolidated Financial Results for First Quarter of 2024

Atico Reports Consolidated Financial Results for First Quarter of 2024

Atico Mining Corporation (the "Company" or "Atico") (TSX.V: ATY | OTC: ATCMF) today announced its financial results for the three months ended March 31, 2024, posting income from mining operations of $2.8 million and a net loss of $0.4 million. Production for the period at Atico's El Roble mine totaled 3.3 million pounds ("lbs") of copper and 2,185 ounces ("oz") of gold in concentrate at a cash cost (1) of $2.57 per payable pound of copper (2) .

Fernando E. Ganoza, CEO and Director, commented, "the operational and financial results for this quarter were in line with Company expectations. We are already into development of the newly discovered reserves and have been making additional investments in preparation for ore extraction from these areas." Mr. Ganoza continued, "for the remainder of the year, we should start to see an improvement in our operating costs as we progressively gain access to mining the upper areas of the mine, while at the same time the recent increase in metals prices, particularly in copper should be positively reflected in our revenue and margin."

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
Atico Produces 3.34 Million Pounds of Cu and 2,156 Ounces of Au in First Quarter 2024

Atico Produces 3.34 Million Pounds of Cu and 2,156 Ounces of Au in First Quarter 2024

Atico Mining Corporation (the "Company" or "Atico") (TSX.V: ATY | OTCQX: ATCMF) announces its operating results for the three months ended March 31, 2024 from its El Roble mine. Production for the quarter totaled 3.34 million pounds of copper and 2,156 ounces of gold in concentrates, an increase of 44% for copper and a decrease of 16% for gold, respectively, over the same period in 2023.

"The El Roble mine operated in line with set expectations for this quarter as we improved on almost all metrics over the same period last year," said Fernando E. Ganoza, CEO. "For the remainder of the year, the team will be focused on optimizing production to take advantage of the higher metal price environment and to deliver on this year's set guidance. In parallel, we continue to drill new high-grade resources in the mine vicinity target areas. These new areas will be incorporated into our mine plan as well as the new resource update which is planned to be published imminently."

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
Atico Reports Consolidated Financial Results for 2023

Atico Reports Consolidated Financial Results for 2023

(All amounts expressed in US dollars, unless otherwise stated)

Atico Mining Corporation (the "Company" or "Atico") (TSX.V: ATY | OTC: ATCMF) today announced its financial results for the year ended December 31, 2023, posting income from mining operations of $7.4 million and a net loss of $5.8 million. Production for the year at Atico's El Roble mine totaled 13.2 million pounds ("lbs") of copper and 10,149 ounces ("oz") of gold in concentrate at a cash cost ( 1) of $2.04 per payable pound of copper (2) .

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
Atico Reports Multiple High Grade Intercepts up to 20.70m of 5.76% Cu, 4.46 g/t Au and 11.50m of 8.16% Cu, 8.09 g/t Au and Continues to Extend the Ore Body at El Roble Mine in Colombia

Atico Reports Multiple High Grade Intercepts up to 20.70m of 5.76% Cu, 4.46 g/t Au and 11.50m of 8.16% Cu, 8.09 g/t Au and Continues to Extend the Ore Body at El Roble Mine in Colombia

Atico Mining Corporation (TSX.V: ATY | OTCQX: ATCMF) ("Atico" or the "Company") is pleased to announce positive results for the latest 49 drill holes being carried out in an area of historical mining to expand tonnage at the El Roble mine. In addition, the Company reports the results for sixteen diamond drill core holes (see first table below), which included 20.70m of 5.76% Cu, 4.46 gt Au and 11.50m of 8.16% Cu, 8.09 gt Au. Ore grade intercepts in another fourteen drill holes are also reported over narrower widths of approximately 1 to 2 meters in areas with limited drilling which highlights the possibility of further extending the ore body with additional drill programs.

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
Quetzal Copper Provides Update on Financing

Quetzal Copper Provides Update on Financing

Quetzal Copper Corp. (TSXV: Q) ("Quetzal" or the "Company") announces a non-brokered private placement (the "Offering") for aggregate gross proceeds of up to C$3,000,000, from the sale of the following:

  • up to 6,666,666 units of the Company (the "Units") at a price of C$0.15 per Unit for gross proceeds of up to C$1,000,000 from the sale of Units; and
  • up to 11,764,705 flow through units of the Company (the "FT Units") at a price of C$0.17 per FT Unit for gross proceeds of up to C$2,000,000 from the sale of FT Units. Each FT Share will be issued as a "flow-through share" within the meaning of the Income Tax Act (Canada).

Each Unit and FT Unit issued under the Offering shall consist of one common share in the capital of the Company (each, a "Common Share") and one-half of one Common Share purchase warrant (each whole warrant, a "Warrant"). Each Warrant will entitle the holder thereof to acquire one Common Share at an exercise price of $0.25 per Common Share for a period of 24 months from the closing of the Offering (the "Closing").

News Provided by Newsfile via QuoteMedia

Keep reading...Show less
Silver47 Exploration Corp.  Opens the Market

Silver47 Exploration Corp. Opens the Market

Gary Thompson, Chief Executive Officer, Silver47 Exploration Corp. ("Silver47" or the "Company") (TSXV: AGA), and his team, joined Dean McPherson, Head, Business Development, Global Mining, Toronto Stock Exchange (TSX), to open the market to celebrate the Company's new listing on the TSX Venture Exchange.

Silver47 Exploration Corp. is focused on rapidly expanding its resource base of silver, gold, copper, zinc and lead, with the aim of reaching a milestone development decision in the next 3-5 years, while also driving new discoveries.

Backed by industry leaders, the Company is advancing its flagship Red Mountain project in Alaska, which currently hosts 168.6 million ounces of silver at 336 g/t AgEq, equivalent to 1 million tonnes of zinc at 7% ZnEq or 2 million ounces of gold at 4 g/t AuEq.

Silver47's initial focus is on increasing the silver-gold rich Dry Creek and West Tundra Flats resources at the eastern end of this district-scale land package, with an exploration target of 50Mt in the 300-400 g/t AgEq grade range for 480Moz Eq. The company's extensive land holdings of 942 state mining claims and one mining lease cover a 60km trend of polymetallic mineralization.

MEDIA CONTACT:
Gary Thompson
President & CEO
info@silver47.ca
403-870-1166

To view the source version of this press release, please visit https://www.newsfilecorp.com/release/233679

News Provided by Newsfile via QuoteMedia

Keep reading...Show less
Osisko Metals Corporate Update

Osisko Metals Corporate Update

NOT FOR DISTRIBUTION TO U.S. NEWSWIRE SERVICES OR FOR DISSEMINATION IN THE UNITED STATES

Osisko Metals Incorporated (the " Company " or " Osisko Metals ") ( TSX-V: OM ; OTCQX: OMZNF ; FRANKFURT: OB51 ) announces, further to its news release dated November 18, 2024 (entitled " Osisko Metals Expands Leadership Team and Announces C$100 Million Bought Deal Financing " ), the following changes to Osisko Metals' leadership team:

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
Bold Ventures Identifies New Gold Zone at Its Burchell Gold and Copper Property

Bold Ventures Identifies New Gold Zone at Its Burchell Gold and Copper Property

Bold Ventures Inc. (TSXV: BOL) (the "Company" or "Bold") is pleased to announce that it has received assays up to 56.9 gt gold (Au) from a newly identified zone at its Burchell Property ("the Property"), sampled during a prospecting and field reconnaissance program in November of this year. The high-grade sample was collected approximately 15 meters southwest of 2023 samples which returned between 0.04 and 0.51 gt Au. The zone has now been named the 111 (one-eleven) Zone. A geological sketch map of the outcrop exposure was made and three grab samples were collected along or near the zone during the 2024 program (see Table 1 below for coordinates, descriptions, and results). Assay results ranged from

News Provided by Newsfile via QuoteMedia

Keep reading...Show less

Latest Press Releases