Ascendant Resources Inc. Announces Submission of the Environmental Impact Assessment  for its Lagoa Salgada VMS Project, in Portugal

Ascendant Resources Inc. Announces Submission of the Environmental Impact Assessment for its Lagoa Salgada VMS Project, in Portugal

  • Environmental Impact Assessment ("EIA") submitted to the Portuguese Environmental Authority, APA ("AgĂȘncia Portuguesa do Ambiente").
  • Approval of the EIA is expected by the end of June 2024 following which, the Company will enter the RECAPE phase, allowing for a formal construction decision.
  • Application for construction of 30MW Photovoltaic plant submitted in parallel.

Ascendant Resources Inc. (TSX:ASND)(OTCQB:ASDRF)(FRA:2D9) ("Ascendant" or the "Company"), through its subsidiary, Redcorp - Empreendimentos Mineiros, Lda ("REM"), is pleased to announce that it has submitted the Environmental Impact Assessment Report ("EIA") for its Lagoa Salgada Project to the Portuguese Environmental Authority, APA ("AgĂȘncia Portuguesa do Ambiente") on December 21th 2023

The submission of the EIA is the culmination of more than 18 months of data collection, aggregation and analysis prepared by management and internationally renowned consulting experts. The EIA document includes complete environmental baseline studies, hydrological and hydrogeological modelling, human, archaeological, fauna and flora characterization and impact evaluation, along with the mitigation, controls and benefits that will be present over the Life of Mine ("LoM") of the Project, from construction to final closure.

It also represents extensive collaboration and relationship development with National and regional authorities and local organizations. In particular, the company has undertaken complex and detailed hydrological and hydrogeological modelling in excess of statutory requirements which has provided positive outcomes and provides confidence the Lagoa Salgada Project has been carefully planned to avoid and mitigate any potential impacts on surface and underground aquifers.

Approval of the EIA is expected to be obtained by the end of June 2024 for REM, followed by the RECAPE phase - Environmental Compliance Report of the Execution Project ("RECAPE"). The RECAPE phase aims to verify that the execution of the project complies with the criteria established in the Environmental Impact Statement ("EIA"); complying with the terms and conditions set forth therein would position the project to be ready for the execution of a formal construction decision once all criteria are determined.

The Company is also submitting as a complementary project, plans to construct a 30MW PV (photovoltaic) plant as part of the environmental licensing process demonstrating our commitment to sustainability reduce carbon emissions. Integrating renewable energy sources like solar power into our Lagoa Salgada project mine operations to meet future mine requirements will have multiple benefits, both in terms of environmental impact and long-term cost savings. In addition to the environmental benefits, incorporating solar energy aligns with best practices for Environmental, Social, and Governance ("ESG") standards and at the same time will make significant strides towards reducing Lagoa Salgada's carbon emissions, operating costs and promote sustainable practices.

Mark Brennan, Executive Chairman of Ascendant commented, "We are very pleased to have submitted our EIA assessment which has been the culmination of an extensive and detailed period of study and analysis by our team and consultants. This submission reflects the next step in bringing the Lagao Salgada project into full development and eventual production. Additionally, the engagement with the local communities has enabled the project to be welcomed in the GrĂąndola and AlcĂĄcer do Sal municipalities and we are confident that we can expect positive outcomes from the EIA review process."

JoĂŁo Barros, Ascendant President commented: "The extensiveness of our EIA submission and project development work demonstrates our commitment to the advancement and value of the Lagoa Salgada Project and represents a key step forward for the Lagoa Salgada Project on its development path to become the next operating mine in Portugal, contributing significantly to the country and local communities in which we operate".

About Ascendant Resources Inc.

Ascendant Resources is a Toronto-based mining company focused on the exploration and development of the highly prospective Lagoa Salgada VMS project located on the prolific Iberian Pyrite Belt in Portugal. The Lagoa Salgada project is a high-grade polymetallic project, demonstrating a typical mineralization endowment of zinc, copper, lead, tin, silver, and gold. Extensive exploration upside potential lies both near deposit and at prospective step-out targets across the large 7,209-hectare property concession.

Located just 80km from Lisbon and surrounded by exceptional infrastructure, Lagoa Salgada offers a low-cost entry to a significant exploration and development opportunity, already showing its mineable scale and cashflow generation potential.

Ascendant currently holds an 80% interest in the Lagoa Salgada project through its position in Redcorp - Empreendimentos Mineiros, Lda, ("Redcorp"). The Company's common shares are principally listed on the Toronto Stock Exchange under the symbol "ASND". For more information on Ascendant, please visit our website at http://www.ascendantresources.com/.

Additional information relating to the Company is available on SEDAR+ at www.sedarplus.com

For further information, contact:

Mark Brennan
Executive Chairman, Founder

Mike McAllister
Vice President, Investor Relations
Tel: +1-647-805-5662
mmcallister@ascendantresources.com

Forward Looking Information

This press release contains statements that constitute "forward-looking information" (collectively, "forward-looking statements") within the meaning of the applicable Canadian securities legislation. All statements, other than statements of historical fact, are forward-looking statements and are based on expectations, estimates and projections as at the date of this news release. Any statement that discusses predictions, expectations, beliefs, plans, projections, objectives, assumptions, future events or performance (often but not always using phrases such as "expects", or "does not expect", "is expected", "anticipates" or "does not anticipate", "plans", "budget", "scheduled", "forecasts", "estimates", "believes" or "intends" or variations of such words and phrases or stating that certain actions, events or results "may" or "could", "would", "might" or "will" be taken to occur or be achieved) are not statements of historical fact and may be forward-looking statements.

Forward-looking statements contained in this press release include, without limitation, statements regarding the business, the Lagoa Salgada project and timing of completion of studies. In making the forward- looking statements contained in this press release, Ascendant has made certain assumptions, including, but not limited to securing approval of the EIA for the Lagoa Salgada Project, and the entering and completion thereof of the RECAPE phases and a construction decision including but not limited to those described in this news release. Although Ascendant believes that the expectations reflected in forward-looking statements are reasonable, it can give no assurance that the expectations of any forward-looking statements will prove to be correct. Known and unknown risks, uncertainties, and other factors which may cause the actual results and future events to differ materially from those expressed or implied by such forward-looking statements. Such factors include, but are not limited to general business, economic, competitive, political and social uncertainties. Accordingly, readers should not place undue reliance on the forward-looking statements and information contained in this press release. Except as required by law, Ascendant disclaims any intention and assumes no obligation to update or revise any forward-looking statements to reflect actual results, whether as a result of new information, future events, changes in assumptions, changes in factors affecting such forward-looking statements or otherwise. Forward-looking information is subject to a variety of risks and uncertainties, which could cause actual events or results to differ from those reflected in the forward-looking information, including, without limitation, the risks described under the heading "Risks Factors" in the Company's Annual Information Form dated March 31, 2023 and under the heading "Risks and Uncertainties" in the Company's most recent Management's Discussion and Analysis and other risks identified in the Company's filings with Canadian securities regulators, which filings are available on SEDAR+ at www.sedarplus.com. The risk factors referred to above are not an exhaustive list of the factors that may affect any of the Company's forward-looking information. The Company's statements containing forward-looking information are based on the beliefs, expectations and opinions of management on the date the statements are made, and the Company does not assume any obligation to update such forward-looking information if circumstances or management's beliefs, expectations or opinions should change, other than as required by applicable law. For the reasons set forth above, one should not place undue reliance on forward-looking information.

SOURCE: Ascendant Resources, Inc.



View the original press release on accesswire.com

News Provided by ACCESSWIRE via QuoteMedia

ASND:CA
Ascendant Resources

Ascendant Resources Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

The Conversation (0)
Ascendant Resources (Ascendant Resources)

Ascendant Resources


Keep reading...Show less
Ascendant Appoints Senior IPB Veteran Guy Lauzier, P.Eng. As Technical Advisor For Development Of Lagoa Salgada Project

Ascendant Appoints Senior IPB Veteran Guy Lauzier, P.Eng. As Technical Advisor For Development Of Lagoa Salgada Project

  • Senior Mining Engineer with oversight expertise in mine planning, design, construction and project management for Matsa, Aljustrel and Neves Corvo's VMS projects on the Iberian Pyrite Belt;
  • Strengthens Ascendant's Technical capability during transition for project development

Ascendant Resources Inc. (TSX:ASND)(OTCQX:ASDRF)(FRA:2D9) ("Ascendant" or the "Company") is pleased to announce that it has strengthened its management team with the appointment of Mr. Guy Lauzier, P.Eng., who has been appointed as Technical Adviser for its Lagoa Salgada project. Mr. Lauzier will work with the management team to enhance the design, construction and delivery of the Lagoa Salgada VMS Project, located on the Iberian Pyrite Belt, in Portugal

Mr. Lauzier is a mining engineer with over 45 years' experience in both underground and open pit mining. Previous employment experience includes a tenure at projects located on the Iberian Pyrite Belt including MATSA - Trafigura, as Project Manager specializing in project design, control and construction of a 2.2 Mtpa processing plant. He was Project Manager at Lundin Mining's previously owned Aljustrel Project in Portugal, where he was responsible for the engineering and upgrade of Lead/Zinc/Copper circuit, fine crushing and fine grinding system. He organized the reopening of the Moinho mine and the development of the the Feitais mine for 3000 tpd. Prior to Lundin, Mr. Lauzier was a Technical Advisor at Eurozinc Neves Corvo's Mine (IBP) where his responsibilities included Mine Planning, Design, Construction and Project Management as well as the refurbishment of the Lead Zinc plant.

News Provided by ACCESSWIRE via QuoteMedia

Keep reading...Show less
Ascendant Reports Significant Metallurgical Improvements at Its Lagoa Salgada VMS Project, Portugal

Ascendant Reports Significant Metallurgical Improvements at Its Lagoa Salgada VMS Project, Portugal

  • Results demonstrate ability to produce saleable and highly marketable Zinc and Lead concentrates from the Primary Massive Sulphide domain.
  • Significant improvement in Zinc recoveries (13% increase) and concentrate grades (22% increase) compared to the Feasibility Study.
  • Metallurgical results, completed at coarser grind sizes supporting simplified flow sheet and lower capital and operating costs relative to the Feasibility Study.
  • Further improvement anticipated from additional ongoing metallurgical optimization test work.

Ascendant Resources Inc. (TSX:ASND)(OTCQX:ASDRF);(FRA:2D9) ("Ascendant" or the "Company") provides an update on the optimization metallurgical test program on the primary massive sulphides ("PMS") domain at Lagoa Salgada. The Massive Sulphides are the highest margin domain and a large value driver of NPV for the Lagoa Salgada Project. Bench scale metallurgical testing on composite samples from the PMS ore body were completed by Maelgwyn Metallurgical Laboratories (South Africa) with oversight from Minepro Solutions (Spain) and DRA Global (South Africa

Following completion of the July 2023 43-101 Feasibility Study ("FS"), Ascendant initiated an optimization program for metallurgical performance to improve metal recoveries, concentrate grades and characterization of the deleterious elements in order to enhance the revenue potential for its Lagoa Salgada Project. The initial phase of the optimization program has been focused on the Primary Massive Sulphide mineralization from its Venda Nova North Sector, as this zone is the major revenue contributor for the project and is exploited early in the mine life. In addition to the metallurgical work, the company continues to progress its environmental permitting activities and expects to be granted the permit in Q3/24 which would position Lagoa Salgada as the next mine ready project on the Iberian Pyrite belt.

News Provided by ACCESSWIRE via QuoteMedia

Keep reading...Show less
Gravity Survey Results Identify High Impact Near Deposit Massive Sulphide Exploration Targets at its Lagoa Salgada VMS Project, in Portugal

Gravity Survey Results Identify High Impact Near Deposit Massive Sulphide Exploration Targets at its Lagoa Salgada VMS Project, in Portugal

  • New High-Resolution gravity survey suggests potential to rapidly expand Massive Sulphide Mineralization at current Venda Nova North and South Deposits
  • Multiple additional gravity anomalies identified to potentially add to the Massive Sulphide Ore Bodies near Venda Nova
  • EDM's Option to gain a 15% interest in the Project extended to September 30, 2024 due to upcoming elections and government change

Ascendant Resources Inc. (TSX:ASND)(OTCQB:ASDRF)(FRA:2D9) ("Ascendant" or the "Company") is pleased to announce the results of its recent high-resolution gravity survey completed over the Venda Nova North and South Deposits at its Lagoa Salgada VMS Project, in Portugal

Key Highlights

News Provided by ACCESSWIRE via QuoteMedia

Keep reading...Show less
Ascendant Provides Summary of 2023 Achievements and Outlook for 2024

Ascendant Provides Summary of 2023 Achievements and Outlook for 2024

Ascendant Resources Inc. (TSX:ASND)(OTCQB:ASDRF)(FRA:2D9) ("Ascendant" or the "Company"), is pleased to provide a summary of the significant milestones achieved during 2023 and looks forward to another year of continued de-risking and key value creation objectives in 2024 for its Lagao Salgada polymetallic project in Portugal

Key Milestones Delivered in 2023

News Provided by ACCESSWIRE via QuoteMedia

Keep reading...Show less
Ascendant Closes First Tranche of C$2.7 Million Non-Brokered Private Placement

Ascendant Closes First Tranche of C$2.7 Million Non-Brokered Private Placement

NOT FOR DISTRIBUTION TO U.S. NEWS WIRE SERVICESOR FOR DISSEMINATION IN THE UNITED STATES

AscendantResources Inc. (TSX:ASND) ("Ascendant" or the "Company") is pleased to announce the close of the first tranche ("First Tranche") of its non-brokered private placement (the "Offering") announced December 7, 2023. The second and final tranche to complete the Offering is expected to close on or about January 5, 2024. The Offering is fully subscribed and the Company is completing final settlement for the balance of the Offering

News Provided by ACCESSWIRE via QuoteMedia

Keep reading...Show less
World Copper Closes Final Tranche of Over-Subscribed Non-Brokered Private Placement

World Copper Closes Final Tranche of Over-Subscribed Non-Brokered Private Placement

World Copper Ltd. (TSXV: WCU) (OTCQB: WCUFF) (FSE: 7LY0) ("World Copper" or the "Company") reports that pursuant to their news releases dated February 27, 2024 and April 12, 2024, the Company has closed the final tranche of their non-brokered financing, issuing an additional 16,531,957 units for proceeds of $1,157,237. Aggregate totals from both tranches total 69,547,069 units for gross proceeds of $4,868,294.89.

Each unit consisted of one common share of the Company (a "Share") and one-half of one common share purchase warrant (a "Warrant"). Each whole Warrant entitles the holder to acquire one additional share of the Company for a period of two years from the date of issuance at a price of $0.17 per share. The expiry of the Warrants may be accelerated if the closing price of the Company's common shares on the TSX Venture Exchange ("TSXV") is equal to or greater than $0.30 for a minimum of twenty consecutive trading days and a notice of acceleration is provided in accordance with the terms of the Warrants.

News Provided by Newsfile via QuoteMedia

Keep reading...Show less
Quetzal Copper Samples 3.8 M of 2.4% Copper Associated with EM Geophysical Target Extending to 350M Depth at Cristinas Project

Quetzal Copper Samples 3.8 M of 2.4% Copper Associated with EM Geophysical Target Extending to 350M Depth at Cristinas Project

Highlights:

  • Surface rock chip channel sample returns 3.8m of 2.4% Copper and 162 g/t Silver at the Cristinas mine target.
  • Geophysical survey over the mine target area shows a conductor associated with mineralization that extends, untested, to at least 350m depth beneath historic shallow drilling.
  • A second conductor in the hanging wall of the mine target adds an additional drill target.
  • Drilling commencing in May 2024 to test open copper intercepts and geophysical targets at the Cristinas project.

Quetzal Copper Corp. (TSXV: Q) ("Quetzal" or the "Company"), a copper-focused exploration company, is pleased to announce the results of the due diligence surface rock sampling campaign and geophysical survey at the Cristinas Project, Chihuahua Mexico.

News Provided by Newsfile via QuoteMedia

Keep reading...Show less
Interra Provides Rip Copper Molybdenum Project Exploration Update

Interra Provides Rip Copper Molybdenum Project Exploration Update

Interra Copper Corp. (CSE: IMCX) (OTCQB: IMIMF) (FSE: 3MX) ("Interra" or the "Company") is pleased to provide detail of the first phase exploration program at the Rip Copper Project (the "Project" or "Rip") in the Stikine region of British Columbia. The Rip Project is situated approximately 33 km northeast of Imperial Metals' past producing Huckleberry copper-molybdenum ("Cu-Mo") mine (see Figure 1), which is presently on care and maintenance. Imperial Metals Corporation is exploring Huckleberry and its surrounding claims for additional Cu-Mo resources.

In late 2023, the Company first announced its option agreement with ArcWest Exploration Inc. ("ArcWest") to acquire an 80% interest in ArcWest's Rip Cu-Mo project. Interra can earn the first tier of its interest in the project by completing staged exploration work totalling C$2.0 million and direct payment of C$100,000 and annual share payments over 4 years until end of 2027. Interra is currently funded for, and anticipates, it will meet and likely exceed its 2024 and 2025 obligations for the earn-in of C$300,000 and C$500,000 in expenditures respectively with the budget outlined in this 2 stage program. The initial program is staged into 2 work phases: 1) A geophysical program to define drill targets, commencing in late April and; 2) A diamond drilling program tentatively scheduled for Q3/Q4 of 2024.

News Provided by Newsfile via QuoteMedia

Keep reading...Show less
Ramp Metals Inc.  Opens the Market

Ramp Metals Inc. Opens the Market

Jordan Black Chief Executive Officer and Director, Ramp Metals Inc. (TSXV: RAMP) ("Ramp Metals" or the "Company"), and his team joined Omar Khafagy Manager, Corporate Access, Toronto Stock Exchange (TSX), to open the market and celebrate the Company's listing to TSX Venture Exchange (TSXV).

Ramp Metals is a battery and base metal exploration company with two flagship properties located in northern Saskatchewan and one property in Nye County, Nevada .

Cision View original content to download multimedia: https://www.prnewswire.com/news-releases/ramp-metals-inc-tsxv-ramp-opens-the-market-302127855.html

SOURCE Toronto Stock Exchange

Cision View original content to download multimedia: http://www.newswire.ca/en/releases/archive/April2024/25/c9697.html

News Provided by Canada Newswire via QuoteMedia

Keep reading...Show less
Canadian North Resources Inc. Reports Operational and Financial Results for the Year Ended December 31, 2023

Canadian North Resources Inc. Reports Operational and Financial Results for the Year Ended December 31, 2023

2023 Operational and Project Highlights:

  • The Company raised over $17 million for exploration, with cash and cash equivalents of $5,540,312 at the year end
  • Completed aggressive exploration programs with 21,126 meters in 47 holes drilled in 2023.
  • Adding results of 39,270 meters in 145 holes of new diamond drilling to the project database for the updated Mineral Resources estimation reported in Q1 2024, which includes:

    • A 172% increase of Indicated Mineral Resources to 66.1 million tonnes (Mt) containing 1,093 million pounds (Mlb) copper at 0.75%, 678Mlb nickel at 0.47%, 79Mlb cobalt at 0.05%, 2.34 million ounces (Moz) palladium at 1.10 g/t and 0.42Moz platinum at 0.19 g/t.
    • 80% of the Indicated Mineral Resources is Open Pit with 52.7Mt at 0.65% Cu, 0.43% Ni, 0.05% Co, 0.97g/t Pd and 0.17% Pt.
    • Inferred Mineral Resources of 25.9Mt containing 558Mlb copper at 0.98%, 333Mlb nickel at 0.58%, 40Mlb cobalt at 0.07%, 1.12Moz palladium at 1.43 g/t and 0.21Moz platinum at 0.25 g/t.

Canadian North Resources Inc. ("the Company", TSXV: CNRI; OTCQX: CNRSF; FSE: EO0 (E-O-zero)) is pleased to announce the operational and financial results for the year ended December 31, 2023.

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
Aston Bay Holdings Announces Non-Brokered Private Placement

Aston Bay Holdings Announces Non-Brokered Private Placement

(NOT FOR DISTRIBUTION TO U.S. NEWS WIRE SERVICES OR FOR DISSEMINATION IN THE U.S.)

Aston Bay Holdings Ltd. (TSX-V:BAY)(OTCQB:ATBHF) ("Aston Bay" or the "Company") is pleased to announce that it will conduct a non-brokered private placement (the "Offering"), subject to acceptance by the TSX Venture Exchange (the "Exchange"), for aggregate gross proceeds of up to $5,000,000. The Offering will consist of non-flow through units (the "Units") at a price of $0.12 per Unit (the "LIFE Offering"), and flow-through shares (the "FT Shares") at a price of $0.15 per FT Share

News Provided by ACCESSWIRE via QuoteMedia

Keep reading...Show less
Ascendant Resources

Ascendant Resources Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

Latest Press Releases

Related News

×