Victory Updates Management

Victory Updates Management

Victory Battery Metals CORP. (CSE:VR)(OTC PINK:VRCFF)(FWB:VR6) is pleased to announce that its board of directors now consist of Gerald Tritt, David Stadnyk and George Tsafalas, all of Vancouver, BC. David Stadnyk has assumed the role of president and CEO. The Company intends to close its recently announced Yellow Chief Uranium acquisition in the next 10 days

The Company wishes to thank Mark Ireton for his service to the company and wishes him well in his future endeavors.

About Victory Battery Metals Corp.

Victory Battery Metals CORP. (CSE:VR) is a publicly traded diversified investment corporation with mineral interests in North America. The company is also actively seeking other exploration opportunities.

For further information, please contact:

David Stadnyk, President
Telephone: TOLL FREE 1 (855) 665-GOLD (4653)
E-mail: info@victorybatterymetals.com

Neither the Canadian Securities Exchange nor its Regulation Services Provider (as that term is defined in the policies of the Canadian Securities Exchange) accepts responsibility for the adequacy or accuracy of this release.

Forward Looking Statements

Certain information set forth in this news release may contain forward-looking statements that involve substantial known and unknown risks and uncertainties. All statements other than statements of historical fact are forward-looking statements, including, without limitation, statements regarding future financial position, business strategy, use of proceeds, corporate vision, proposed acquisitions, partnerships, joint-ventures and strategic alliances and co-operations, budgets, cost and plans and objectives of or involving the Company. Such forward-looking information reflects management's current beliefs and is based on information currently available to management. Often, but not always, forward-looking statements can be identified by the use of words such as "plans", "expects", "is expected", "budget", "scheduled", "estimates", "forecasts", "predicts", "intends", "targets", "aims", "anticipates" or "believes" or variations (including negative variations) of such words and phrases or may be identified by statements to the effect that certain actions "may", "could", "should", "would", "might" or "will" be taken, occur or be achieved. A number of known and unknown risks, uncertainties and other factors may cause the actual results or performance to materially differ from any future results or performance expressed or implied by the forward-looking information. These forward-looking statements are subject to numerous risks and uncertainties, certain of which are beyond the control of the Company including, but not limited to, the impact of general economic conditions, industry conditions and dependence upon regulatory approvals. Readers are cautioned that the assumptions used in the preparation of such information, although considered reasonable at the time of preparation, may prove to be imprecise and, as such, undue reliance should not be placed on forward-looking statements. The Company does not assume any obligation to update or revise its forward-looking statements, whether as a result of new information, future events, or otherwise, except as required by securities laws.

SOURCE: Victory Battery Metals Corp.



View the original press release on accesswire.com

News Provided by ACCESSWIRE via QuoteMedia

VR:CC
Victory Battery Metals

Victory Battery Metals Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

The Conversation (0)
Victory Resources (CSE:VR)

Victory Battery Metals

Overview

Victory Battery Metals (CSE:VR,FWB:VR61,OTCPINK:VRCFF) is a Vancouver-based junior mining and exploration company operating primarily out of North America. The company recently underwent restructuring and rebranding to pivot to battery metals, recognizing the significant opportunity brought about by the global efforts toward electrification and decarbonization.

As the push for clean energy and the global transition to net-zero continue to ramp up, lithium has never been more important. The burgeoning electric vehicle market exemplifies this, with sales of electric cars topping 6.6 million in 2021 and over 10 million in 2022. On the plus side, this explosive market growth will, according to the International Energy Agency, eliminate the need for roughly 5 million barrels of oil per year by 2030.

Victory’s flagship project, Smokey Lithium, has the distinction of being situated very close to the only lithium-producing silver mine in North America. In addition to Smokey Lithium, Victory maintains five other projects: Stingray Lithium Array in James Bay, Quebec; Georgia Lake Lithium property, Ontario; Tahlo Lake, in the Babine Copper-Gold Porphyry District, British Columbia; Saguenay Nickel Project, Quebec; and Black Diablo Copper and Manganese in Nevada.

Lithium

These projects’ strategic locations in mining-friendly and infrastructure-ready jurisdictions position Victory to not only explore new sources of critical battery metals required to meet the growing demand, but also help disrupt the currently unbalanced supply chain, with China dominating roughly 70 percent of global lithium production despite the fact it only supplies 13 percent of the world's lithium.

Given China's questionable mining practices and propensity for leveraging the global supply chain as a political weapon, the status quo is far from ideal. Unsurprisingly, many countries — Canada and the United States among them — are investing heavily into establishing a domestic lithium supply chain. Victory Battery Metals is ideally positioned to take advantage of these investment efforts.

Company Highlights

  • Recently completed a successful private placement for $2 million, and holds several million dollars in treasury.
  • Smokey Lithium flagship project operates out of Nevada, one of the most mining-friendly jurisdictions in North America.
  • Victory's primary focus is on bridging the considerable gap between supply and demand, and is benefitting considerably from federal mandates around lithium and critical battery metals production in both Canada and the United States.
  • Work programs are planned for all major assets within the next twelve months.
  • Maintains an incredibly diverse mining portfolio primarily geared towards the needs of the growing electric vehicle market. However, its assets also include precious metals such as gold and silver.
  • Victory is actively working to identify opportunities in regions conducive to mining and geographic locations suited to year-round exploration and development.

Get access to more exclusive Lithium Investing Stock profiles here

Victory is Pleased to Announce the Appointment of Gary Musil to the Company's Board of Directors and a Private Placement

Victory is Pleased to Announce the Appointment of Gary Musil to the Company's Board of Directors and a Private Placement

Victory Battery Metals Corp. (CSE:VR)(OTC PINK:VRCFF)(FWB:VR6) welcomes Gary Musil as a director of the Company, effective July 1, 2024. Gary Musil has more than 35 years of management and financial consulting experience and has served as an officer and director on numerous public companies since 1988. This experience has resulted in his overseeing the financial aspects and expenditures on exploration projects in Peru, Chile, Eastern Europe (Slovak Republic), and British Columbia, Ontario, Quebec, Saskatchewan and New Brunswick (Canada). Prior to his public company work, he was employed for 15 years with Dickenson Mines Ltd. and Kam-Kotia Mines Ltd., as the Controller for their producing silverleadzinc mine in the interior of British Columbia

News Provided by ACCESSWIRE via QuoteMedia

Keep reading...Show less
Victory Acquires Yellow Chief Uranium Project, Utah and Saskatchewan Uranium Portfolio

Victory Acquires Yellow Chief Uranium Project, Utah and Saskatchewan Uranium Portfolio

Victory Battery Metals CORP. (CSE:VR)(OTC PINK:VRCFF)(FRA:VR6) is pleased to announce that it has significantly expanded it's focus on uranium, with the acquisition of the Yellow Chief uranium property in Utah, and a portfolio of four uranium properties in Saskatchewan. When combined with the previously announced Chariot River property in Saskatchewan, the companies holdings comprise 3,643 hectres

Terms of the Option Agreement are:

News Provided by ACCESSWIRE via QuoteMedia

Keep reading...Show less
Victory Sells Tahlo Lake Property in British Columbia

Victory Sells Tahlo Lake Property in British Columbia

Victory Battery Metals Corp. (CSE:VR)(FWB:VR61)(OTC PINK:VRCFF) ("Victory" or the "Company") is pleased to announce its sale of its Tahlo Lake, British Columbia property to a private company, Trimera Metals Corp., of Vancouver, British Columbia

Highlights of the Tahlo Lake Sale:

News Provided by ACCESSWIRE via QuoteMedia

Keep reading...Show less
Victory Battery Metals Corp. Options Kachiwiss Uranium Project and Other Uranium Anomalies

Victory Battery Metals Corp. Options Kachiwiss Uranium Project and Other Uranium Anomalies

Victory Battery Metals CORP. (CSE:VR)(OTC PINK:VRCFF)(FWB:VR6) is pleased to announce that it has entered into an option agreement dated April 11, 2024 to acquire 100% interest in four claim groupings in the Sept Iles region of Quebec. These claims are being optioned from GLOBEX MINING ENTERPRISES INC. (GMX - Toronto Stock Exchange, G1MN - Frankfurt, Stuttgart, Berlin, Munich, Tradegate, Lang & Schwarz, LS Exchange, TTMzero, Düsseldorf and Quotrix Düsseldorf Stock Exchangesand GLBXF - OTCQX International in the US). Under terms of the agreement Victory will pay to Globex $400,000 in cash and 1,500,000 Victory shares over 3 years. In addition, Victory commits to execute a work program of a minimum of $3,000,000 on the claims over a 4-year period

News Provided by ACCESSWIRE via QuoteMedia

Keep reading...Show less
Victory Announces Private Placements

Victory Announces Private Placements

NOT FOR DISTRIBUTION TO UNITED STATES NEWSWIRE SERVICES OR FOR DISSEMINATION IN THE UNITED STATES

Victory Battery Metals Corp. (CSE:VR)(FRA:VR6) (OTC PINK:VRCFF) ("Victory" or the "Company") announces today that it will undertake a non-brokered private placement of up to $500,000 by the issuance of 10,000,000 units at $0.05, each unit consisting of one share and one half a warrant. Each whole warrant entitles the holder to additional share for 2 years at a price of $0.10

News Provided by ACCESSWIRE via QuoteMedia

Keep reading...Show less
GMV Minerals Inc. Reaffirms Commitment to Mexican Hat Gold Project - Drill Permit Received for Nevada Project

GMV Minerals Inc. Reaffirms Commitment to Mexican Hat Gold Project - Drill Permit Received for Nevada Project

GMV Minerals Inc. (the "Company" or "GMV") (TSXV:GMV)(OTCQB:GMVMF) is pleased to announce the following update

The Company continues to be highly encouraged by its primary core project known as the Mexican Hat gold deposit located in SE Arizona. The Company's Preliminary Economic Assessment" PEA" reports 36.7 million tonnes grading 0.58 gpt gold in a 688,000 ounce Inferred Mineral Resource. An open pit with a 1.87:1 strip ratio was modeled to extract 32.6 million tonnes of this deposit recovering 525,000 ounces of gold over a 10-year mine life. This is a low capital cost operation, total cost of US$67.8 million, which includes US$12 million in contingency and US$13 million in sustaining capital. Heap leach testing demonstrates an exceptional recovery of 88% of the gold from a two-stage crushing circuit.

News Provided by ACCESSWIRE via QuoteMedia

Keep reading...Show less
CENTURY LITHIUM CHANGES PROJECT NAME TO ANGEL ISLAND MINE

CENTURY LITHIUM CHANGES PROJECT NAME TO ANGEL ISLAND MINE

Century Lithium Corp. (TSXV: LCE) (OTCQX: CYDVF) (Frankfurt: C1Z) (Century Lithium or the Company) announces it has changed the name of its 100%-owned Clayton Valley Lithium Project in Nevada, USA to the Angel Island Mine (the Project). In April 2024 the Company announced a positive Feasibility Study for the Project, making it one of the few advanced lithium projects being developed in the United States . As the Company now continues to work towards permitting the Project, regulators encouraged a name change for clarity in the permitting process. The Angel Island name distinguishes it from other mining and energy projects in the area by using the name of a topographical feature from the Project.

News Provided by PR Newswire via QuoteMedia

Keep reading...Show less
Brunswick Exploration Outlines New Spodumene Rich Boulder Trains at Mirage and Launches Summer Drill Campaign

Brunswick Exploration Outlines New Spodumene Rich Boulder Trains at Mirage and Launches Summer Drill Campaign

Brunswick Exploration Inc. (" BRW " or the " Company ") is pleased to announce the completion of the 2024 prospecting program and start of a 5,000-metre summer drill program at the Mirage Project, located in the Eeyou Istchee-James Bay region of Quebec. To date, 71 drill holes and more than12,000 meters have been drilled on the Mirage project which have delineated nine near-surface spodumene-bearing pegmatite dykes, all of which remain open at depth and along strike. Approximately two dozen additional dykes, with widths ranging from 8 metres to approximately 20 metres, have also been intercepted in the two previous campaigns with minimal to no follow-up work. The proposed program will focus on MR-6, MR-3 and MR-4 as well as new targets that were delineated using drilling, geophysics, till mineralogy and prospecting.

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
Lithium Universe Ltd  Becancour Lithium Refinery Project Update

Lithium Universe Ltd Becancour Lithium Refinery Project Update

Melbourne, Australia (ABN Newswire) - Lithium Universe Limited (ASX:LU7) (OTCMKTS:ESMAF) is pleased to announce a project update of the Becancour Lithium Refinery Project. The project is advancing well and remains on track. Key milestones include finalizing the plant layout, issuing technical specifications for capex estimation, and progressing with supplier quotation activities. Environmental site visits and studies are ongoing, with no significant issues identified. Hatch's transition from Brisbane to Montreal offices is smoothly underway, ensuring continuity in project management. Early contractor engagement and strategic risk assignment are mitigating potential delays. Overall, the project is adhering to its timeline, with significant progress in engineering and procurement, ensuring readiness for a capital cost estimate and commitment to ensure environmental compliance with the regulatory framework.

Highlights

- Project is advancing well and remains on track

- Engineering milestones include plant layout, equipment packages, datasheets, scopes of work, and specifications

- Procurement priority one packages for quotes about 60% complete

- Early contractor engagement and strategic risk assignment

- Environmental work is progressing with no show-stoppers identified to date

- Strong engagement from Federal, Provincial and Local Government

- Becancour Lithium Refinery well aligned with Provincial strategy

- Mature local government support and project understanding

Procurement

Procurement activities include sending technical specifications to suppliers for detailed quotations to build the capex estimation. For priority one mechanical equipment, nine packages have been issued, with seven offers received and evaluations currently underway. Five priority one electrical equipment supply packages will be issued for inquiry within the next week. The goal is to evaluate all priority one packages by the end of September.

Due to potential lead times for electrical transformers, the tenderer list will be expanded to reduce these lead times.

Engineering

The major engineering activities include finalizing the plant layout and preparing documentation for equipment packages, such as datasheets, scopes of work, and specifications. Key tasks also involve creating the main power distribution single line diagram and providing clarifications during the tender period. Additionally, proposals received are being thoroughly reviewed to ensure they meet project requirements. Effective handling of process effluent and site runoff is another critical focus area. The development of the package register, material take-offs (MTOs), and comprehensive equipment lists are ongoing, ensuring all necessary components and details are accurately documented and organized for the project's successful execution.

Plant Layout

The first release of the plant layout has been published, with several features still under development. These include new plant areas such as the boiler plant and process effluent treatment. Structural framing of buildings and HVAC systems are in progress, along with civil works encompassing drainage, road pavements, vehicle paths, sedimentation ponds, and car parking. The location and number of plant switch rooms is being optimised.

Efforts are being made to enhance spodumene and residue storage, focusing on materials handling and capacity. Additionally, the routing of major pipe and cable racks is being planned. The layout on-site is being designed with consideration of likely environmental constraints to ensure compliance and sustainability. These developments aim to enhance the overall efficiency and effectiveness of the project.

Environmental Work

The team is actively involved in field inventories to develop knowledge of the biodiversity present on site. Four field campaigns have been carried-out to survey the presence of short-eared owls, breeding birds, fish and fish habitat, and wetlands. Based on preliminary results, no species at risk nor species of concern as listed under the Canadian Species at Risk Act (SARA) have been identified so far. The project team is also engaged in activities to optimize the site layout and reduce encroachment on wetlands identified on the property. Surveys are expected to be completed during the Canadian Summer. Field inventory results will be used to support environmental permitting activities and discussions with the Regulators to ensure site layout and the design of the industrial facility are developed in full compliance with the environmental regulatory framework.

A Phase I study to understand previous uses of the site is progressing and no potential environmental liability has been identified based on preliminary results. The Phase I Study is expected to be completed by the end of July. Over the coming months, the team is expected to initiate the preparation of permitting documents to ensure the Project follows formal approval lines.

Priorities

The highest priorities for the next few months include finalising the environmental permitting and approvals program, which entails completing the initial field survey, briefing with the Ministry, finalising the Phase 1 Report, and preparing the first application. Engineering work necessary for the environmental permit application is also a top priority, focusing on civil design, updated plant layout, and water management strategy. In parallel, equipment procurement will involve preliminary engineering, securing vendor proposals, and establishing schedules. Confirming the treatment of process effluent and site runoff is crucial for environmental compliance.

Additionally, commencing civil and structural engineering work is essential to maintain project momentum.

Finalising the plant layout will ensure all components are correctly positioned and integrated. Lastly, execution phase planning will be progressed, contingent on the monthly budget, to ensure that all activities are appropriately funded and scheduled for efficient project advancement.

Government and Community Engagement

A trip by key leadership members to Eastern Canada. The delegation, led by CEO Alex Hanly and including Chairman Iggy Tan, Board Directors Patrick Scallan and Dr. Jingyuan Liu, and Canadian Director, Victoria Vargas, engaged with government stakeholders, community partners, and industry peers. The meetings in Montreal, Becancour, Quebec City, and Ottawa reinforced the Company's strategy to address the Lithium Conversion Gap in North America and provided updates on our engineering progress and commercial discussions.

Ministry of Economics, Innovation, and Energy

A meeting was held in Quebec City with the Honourable Minister Pierre Fitzgibbon, Minister of Economics, Innovation, and Energy. This follows the Company's initial presentation of the Company's unique strategy in November 2023 in Dubai. Once again, Minister Fitzgibbon expressed enthusiasm for our engineering progress, the acquisition of the Option agreement within the Becancour Industrial Park, and the Hydro-Quebec application for an estimated 22.5MW energy allocation for our Becancour Lithium Refinery.

Lithium Universe emphasized Quebec's strategic benefits, including hydroelectric power, proximity to the James Bay region, and logistic advantages with port access to the transatlantic region. The Minister reiterated his support for our vision of transforming Quebec into the Centre of Lithium Conversion for the transatlantic region.

The Company is impressed with the forward-thinking provincial government of Quebec and the progress of the Strategic Innovation Zone under the pragmatic guidance of Minister Fitzgibbon.

Becancour Lithium Refinery Site

In February 2024, the Company successfully executed an option agreement to acquire a refinery site strategically located within the Becancour Waterfront Industrial Park (BWIP). The site in Becancour, close to Trois-Rivieres, lies between Montreal and Quebec City and is near major highways and railways. The Port of Becancour supports year-round operations with deep-water access. The site offers low-cost hydroelectric power, robust infrastructure, and comprehensive water and waste facilities, ideal for the proposed Lithium Refinery.

The Company once again met with key executives from the BWIP in Becancour. The meeting focused on the Company's progress in site evaluation activities and included a presentation on the process design, featuring pictures from a reference lithium carbonate refinery. The port was confirmed to have the capacity to manage 50,000-ton bulk shipments, exceeding the Company's initial requirements. The Company had the opportunity to inspect Lot 22, encompassing an area of 27-hectare, and view the proximity to infrastructure and immediate tiein to existing BWIP utilities. The SPIPB team provided an overview of planned expansions and facility upgrades to the onsite infrastructure, positioning Becancour as a leader in offering prime industrial real estate in Quebec.

The Company will be looking to commence various community initiatives to integrate the industrial site into the wider community.

Municipality of Becancour

The Company met with the Mayoress of Becancour to discuss the Company's objectives to contribute to the local economy by providing hundreds of employment opportunities and helping to realize its economic potential.

LU7 reaffirmed its commitment to the Becancour and wider Trois-Rivieres region, pledging to support various social, community, and environmental initiatives in the coming years. The Mayoress expressed enthusiasm for the Company's plans within the SPIPB, recognizing the development of a proven and reliable design with internationally aligned process outputs.

Provincial Government - Quebec

The Company also met with key delegates in Montreal from Investissement Quebec (IQ), the Ministry of Natural Resources and Forests (MRNF), Energy Transition Valley Innovation Zone, and the Ministry of the Environment, the Fight Against Climate Change, Wildlife and Parks. The provincial government has identified a lithium conversion gap within the supply chain, crucial for servicing the expected increase in spodumene supply from the James Bay region in the coming years. Quebec is a North American leader in attracting foreign direct investment, sustainable development, and supporting battery metals projects. The province has a strong history of supporting lithium battery supply chain development, with significant provincial and federal government incentives.

Recent government support includes the General Motors (GM) and Korea-based POSCO Chemicals' US$1 billion cathode active material (CAM) factory, the Ford/EcoPro BM US$800 million cathode factory, and Northvolt's US$7 billion EV Battery Facility at Saint-Basile-le-Grand. This creates a favourable regulatory environment for the Company's project, ensuring robust support throughout the cycle.

Canadian Federal Government - Ottawa

The Company met with various federal government stakeholders from Invest in Canada (IIC), Natural Resources Canada (NRCAN), Innovation, Science and Economic Development (ISED), and Export Development Canada (EDC). Given the lack of refining capacity in Canada, LU7's lithium carbonate plant is an innovative project, as there are no current operating or planned facilities of this kind within the country. Building lithium conversion capacity alongside spodumene mines will enable Canada to become wholly self-sufficient in the lithium chemical supply chain.

Hatch - Montreal

The Company and its engineering partner, Hatch, held a productive meeting at the Montreal office to align their shared culture and fast-track development vision. They reinforced the philosophy of "same process, same equipment, same supplier," which minimizes technical risks, ensures quality, and reduces costs. The operational environments in Australia and Canada share many similarities, facilitating the integration of skills into Quebec.

Hatch's leadership in building lithium conversion facilities and tackling challenging projects validates the decision to partner with them. Through this collaboration, the Company acknowledges Hatch's expertise as the premier lithium refinery engineering expert.

Lithium Universe Chairman, Iggy Tan said, "The project is on track, finalizing plant layout, issuing capex specs, progressing supplier quotes, with smooth office transition, and no environmental issues, ensuring readiness for capex cost estimate. The reception from federal, provincial and local government delegates has left a very positive impression on the LU7 Board of Directors. The region has made strong commitments since releasing the Critical Minerals Strategies four years ago and we have seen that in the significant investments made within the battery supply chain and pragmatic discussions held with key government executives. We look forward to advancing the Company's Becancour Lithium Refinery to contribute in making Quebec the lithium conversion centre within the Transatlantic region."

*To view tables and figures, please visit:
https://abnnewswire.net/lnk/82C8D877



About Lithium Universe Ltd:

Lithium Universe Ltd (ASX:LU7) (OTCMKTS:ESMAF), headed by industry trail blazer, Iggy Tan, and the Lithium Universe team has a proven track record of fast-tracking lithium projects, demonstrated by the successful development of the Mt Cattlin spodumene project for Galaxy Resources Limited.

Instead of exploring for the sake of exploration, Lithium Universe's mission is to quickly obtain a resource and construct a spodumene-producing mine in Quebec, Canada. Unlike many other Lithium exploration companies, Lithium Universe possesses the essential expertise and skills to develop and construct profitable projects.



Source:
Lithium Universe Ltd

News Provided by ABN Newswire via QuoteMedia

Keep reading...Show less
Albemarle Announces Quarterly Common Stock Dividend

Albemarle Announces Quarterly Common Stock Dividend

The Board of Directors of Albemarle Corporation (NYSE: ALB) announces that it has declared a quarterly common stock dividend of $0.405 per share. The dividend, which has an annualized rate of $1.62 is payable Oct. 1, 2024 to shareholders of record at the close of business as of Sept. 13, 2024 . For 30 consecutive years, Albemarle has raised its dividend.

Albemarle Corp. Logo. (PRNewsFoto/Albemarle Corporation)

About Albemarle
Albemarle Corporation (NYSE: ALB) leads the world in transforming essential resources into critical ingredients for mobility, energy, connectivity and health. We partner to pioneer new ways to move, power, connect and protect with people and planet in mind. A reliable and high-quality global supply of lithium and bromine allows us to deliver advanced solutions for our customers. Learn more about how the people of Albemarle are enabling a more resilient world at Albemarle.com , LinkedIn and on X (formerly known as Twitter) @AlbemarleCorp .

Albemarle regularly posts information to www.albemarle.com , including notification of events, news, financial performance, investor presentations and webcasts, non-GAAP reconciliations, U.S. Securities and Exchange Commission filings and other information regarding the company, its businesses and the markets it serves.

Forward-Looking Statements

Some of the information presented in this press release, including, without limitation, information related to future dividends and results, and all other information relating to matters that are not historical facts may constitute forward- looking statements within the meaning of the Private Securities Litigation Reform Act of 1995. Actual results could differ materially from the views expressed. Factors that could cause actual results to differ materially from the outlook expressed or implied in any forward-looking statement include, without limitation: changes in economic and business conditions; adverse changes in liquidity or financial or operating performance; changes in the demand for our products or the end-user markets in which our products are sold and the other factors detailed from time to time in the reports we file with the U.S. Securities and Exchange Commission, including those described under "Risk Factors" in our Annual Report on Form 10-K and our Quarterly Reports on Form 10-Q. These forward-looking statements speak only as of the date of this press release. We assume no obligation to provide any revisions to any forward-looking statements should circumstances change, except as otherwise required by securities and other applicable laws.

Investor Relations Contact: Meredith Bandy , +1 (980) 999-5768, meredith.bandy@albemarle.com
Media Contact: Peter Smolowitz
, +1 (980) 308-6310, media@albemarle.com

Cision View original content to download multimedia: https://www.prnewswire.com/news-releases/albemarle-announces-quarterly-common-stock-dividend-302198618.html

SOURCE Albemarle Corporation

News Provided by PR Newswire via QuoteMedia

Keep reading...Show less
Altech Batteries Ltd  Update on CERENERGY ABS60 Battery-pack Prototypes

Altech Batteries Ltd Update on CERENERGY ABS60 Battery-pack Prototypes

Perth, Australia (ABN Newswire) - Altech Batteries Limited (ASX:ATC) (FRA:A3Y) (OTCMKTS:ALTHF) is pleased to provide an update on the production of its CERENERGY(R) ABS60 BatteryPack prototypes. All 240 cells for the first ABS60 BatteryPack Prototype have now been fabricated, assembled and initialized at Fraunhofer IKTS Hermsdorf's pilot plant.

Highlights

- Prototype production is progressing well

- All CERENERGY(R) cells for the first 60 KWh Prototype completed

- Cell contacting system manufacturing finished and delivered

- Improved cell electrode design showing excellent results

- Cell quality tests by Fraunhofer delivering better than expected capacity

- Welding of cells to cell contacting system underway

- Completed modules will be mounted into ABS60 BatteryPack next week

To validate a homogeneous cathode material distribution, all cells were cycled through several testing stations at Fraunhofer IKTS Hermsdorf and Arnstadt.

IMPROVED CELL ELECTRODE DESIGN

During the fabrication of the two 60kWh CERENERGY(R) ABS60 BatteryPack prototypes, the Altech and Fraunhofer team made several design improvements to the cell's positive probe. These enhancements aimed to boost the cell's energy capacity and reduce the nickel content. The "V2" design of the positive probe allows for slightly faster charging and discharging while lowering the unit costs of the battery. Testing revealed that most cells had higher-than-expected energy capacities, an outstanding result that strongly supports the chosen electrode design. With all cells manufactured according to the series design and optimized processes, the best cells to date have been completed. The table below demonstrates that all the cells are meeting the expected specifications.

CELL CONTACTING SYSTEM COMPLETED

The Cell Contacting System (CCS) has undergone stringent testing and has now been completed and delivered by key supplier Hofer AG. The CCS was delivered to Fraunhofer IKTS in Dresden, where all parts of the modules will be collected to assemble each of the five modules. Each module contains 48 cells, that are currently being welded to the CCS by an external service provider.

After welding is completed, the ABS60 BatteryPack with its 60 kWh capacity can be completely assembled.

MODULE WELDING TRIALS

To guarantee the most time-efficient welding, a unique tool was designed and built at Xenon, which is responsible for welding and quality control across the 120 MWh battery plant. After completing the welding tool, it was shipped to an external laboratory, accompanied by a test module and several trial cells. The aim was to determine the best working parameters and to proof the handling of certain parts of the module.

The trials were successfully finished.

CELL MANUFACTURING PROGRESSING WELL

All 240 cells for the first ABS60 BatteryPack Prototype have been assembled and initialised at Fraunhofer IKTS, Hermsdorf. To validate a homogeneous cathode material distribution, all cells were cycled through several testing stations at Fraunhofer IKTS Hermsdorf and Arnstadt.

INTERIM CELL TESTING

At Fraunhofer IKTS in Hermsdorf, all cells were scanned using a unique X-ray microtomography device that enables the ability to look inside cells after they are hermetically closed. This is required to ensure the most homogeneous material distribution inside the cells as well as the best possible alignment of cell components e.g. electrode. The results have been excellent to date. Another quality assurance procedure involved cycling cells to ensure the electrical requirements and parameters are operating as designed.

MODULE WELDING AND BATTERYPACK ASSEMBLY

After every cell passed all quality checks, the modules containing the cells were shipped to the laboratory for welding onto the CCS. By using the predetermined parameters for welding, all modules have been successfully welded. After completion, the modules will be shipped to Fraunhofer IKTS, Dresden, where all five modules will then be mounted into the ABS60 BatteryPack and the first Prototype will be completed.

This will enable testing and demonstration to potential customers, to prove individual use cases for each customer.

ABOUT THE ABS60 - BATTERYPACK

The 60kWh Altech Battery Pack consists of five 12kWh modules with 48 cells each, mounted on top of each other and sealed in a thermal isolated stainless steel hood housing. The Battery management system is mounted at the base. To maintain thermal self-sufficiency, an insulation hood was designed, where the required heat of the system can be maintained inside the BatteryPack as long as possible, although the outer surface only has ambient temperature. This was achieved by using vacuum insulation. The base of each module is designed to accommodate folklift transport for easy mounting into the GridPack.

Commenting on the progress, MD and CEO Iggy Tan stated "Altech's team in Germany, together with its joint venture partner Fraunhofer, and with the assistance of key suppliers, have made excellent progress on the fabrication of two 60kWh CERENERGY(R) ABS60 BatteryPack prototypes. All components for the first BatteryPack have now been fabricated. Altech is now completing the welding of the cells to the Cell Contacting System, after which the five completed battery modules will be delivered to Fraunhofer IKTS in Dresden, where all five modules will be mounted into the ABS60 BatteryPack and the first ABS60 Prototype will be completed. The BatteryPack will then be available for testing and demonstration to potential customers, thereby assisting Altech in securing offtake and finance for the 120MWh CERENERGY(R) battery plant to be constructed on Altech's land in Germany".

*To view tables and figures, please visit:
https://abnnewswire.net/lnk/O449B2I4



About Altech Batteries Ltd:

Altech Batteries Limited (ASX:ATC) (FRA:A3Y) is a specialty battery technology company that has a joint venture agreement with world leading German battery institute Fraunhofer IKTS ("Fraunhofer") to commercialise the revolutionary CERENERGY(R) Sodium Alumina Solid State (SAS) Battery. CERENERGY(R) batteries are the game-changing alternative to lithium-ion batteries. CERENERGY(R) batteries are fire and explosion-proof; have a life span of more than 15 years and operate in extreme cold and desert climates. The battery technology uses table salt and is lithium-free; cobalt-free; graphite-free; and copper-free, eliminating exposure to critical metal price rises and supply chain concerns.

The joint venture is commercialising its CERENERGY(R) battery, with plans to construct a 100MWh production facility on Altech's land in Saxony, Germany. The facility intends to produce CERENERGY(R) battery modules to provide grid storage solutions to the market.

News Provided by ABN Newswire via QuoteMedia

Keep reading...Show less
Victory Battery Metals

Victory Battery Metals Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

Latest Press Releases

Related News

×