Noram Lithium Provides Update

Noram Lithium Provides Update

noram lithium corp. ("noram" or the "Company") (TSXV:NRM)(OTCQB:NRVTF)(Frankfurt:N7R) is providing a corporate update and an update on its 100% owned Zeus Lithium Project ("Zeus" or the "Project"), located in Clayton Valley, Nevada

Zeus Lithium Project Update

In mid-March, the Company produced an updated Mineral Resource Estimate (MRE) for Zeus which outlined a Measured and Indicated resource estimate of 5.2 Mt Lithium Carbonate Equivalent ("LCE", 1034 Mt at 941 ppm lithium), and an additional Inferred resource estimate of 1.1 Mt LCE (235 Mt at 871 ppm lithium) utilizing a 400 ppm Li cut-off1. Following the updated MRE, the Company initiated a number of Project de-risking initiatives:

  • Engaged SRK Consulting to optimize the Zeus mine plan, focusing on the high-grade core of the Zeus deposit;
  • Initiated a further round of metallurgical test work to confirm and refine the proposed flowsheet for the Project, which is based on known technology to produce high-purity lithium carbonate from Zeus mineralized material, and
  • Engaged Ausenco to complete a Pre-Feasibility for the Project.

"The last four months have been very successful at de-risking the Zeus Project," stated Greg McCunn, CEO of noram. "Early results from the metallurgical test program are confirming and validating our process flowsheet as well as identifying efficiencies to reduce overall operating costs. By focusing the project on the high-grade core of the Zeus Project, we are expecting to materially increase grades of material fed to the processing plant for the first 15-20 years of operations. This will allow us to reduce the scale of the process facility, which is expected to result in lower capital costs, while still maintaining meaningful levels of lithium carbonate production for the electric vehicle battery market.

Preliminary results from Phase 1 of the PFS have outlined a robust business case for the Project and we are now optimizing the business case based on a series of trade off studies. We are expecting to begin releasing preliminary result from this important work when it becomes available later in the third quarter."

Corporate Update

On May 31st, the Company announced that it had engaged Creative Direct Marketing Group, Inc. (CDMG) to provide the Company with marketing services and to raise public awareness of the Company. Over the past two months, the Company has been working with CDMG to prepare for the upcoming campaign which is expected to include both digital and direct mail campaigns. The campaign is expected to get underway in September.

Executive Chairman, Sandy MacDougall said "We are looking forward to communicating the exciting results from our technical work so far this year as they become available later this quarter. We are making extensive efforts with this new investor awareness campaign. noram is looking forward to widening its reach by broadening our audience and sharing the merits of this incredible project with a largely untapped investor base. While the campaign will be focused largely on the United States, our existing investor base in Europe will continue to be communicated with through our VP of Corporate Development, Simon Studer, who is multi-lingual and based in Switzerland."

For additional information:

Contacts:

In Europe: VP Corporate Development simon.studer@noramlithium.com

Elsewhere: Investor Relations at ir@normanlithiumcorp.com

Website: www.noramlithiumcorp.com

ON BEHALF OF THE BOARD OF DIRECTORS

Sandy MacDougall
Founder and Executive Chairman

About noram lithium corp.

noram lithium corp. (TSXV: NRM | OTCQB: NRVTF | Frankfurt: N7R) is focusing on advancing its 100%-owned Zeus Lithium Project located in Clayton Valley, Nevada an emerging lithium hub within the United States. With the upsurge in the electric vehicle and energy storage markets the Company aims to become a key participant in the domestic supply of lithium in the United States. The Company is committed to creating shareholder value through the strategic allocation of capital.

Footnote
1 Refer to the report entitled "Updated Resource Estimate Zeus Lithium Project, Esmeralda County Nevada" with an effective date of March 17, 2023 and filed under the Company's filings on www.sedar.com

Qualified Person

The technical information contained in this news release has been reviewed and approved by Brad Peek, M.Sc., CPG, who is a Qualified Person with respect to noram's Clayton Valley Lithium Project as defined by National Instrument 43-101 Standards of Disclosure for Mineral Projects, and also Vice President of Exploration for noram.

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

Cautionary Statement Regarding Forward Looking Information

This news release may contain forward-looking information which is not comprised of historical facts. Forward-looking information involves risks, uncertainties and other factors that could cause actual events, results, performance, prospects and opportunities to differ materially from those expressed or implied by such forward-looking information. Forward-looking information in this news release includes statements regarding, among other things, plans for ongoing development of the Zeus Lithium Project. Factors that could cause actual results to differ materially from such forward-looking information include, but are not limited to, regulatory approval processes, results of further exploration work, and availability of capital on terms acceptable to the Company. Although noram believes that the assumptions used in preparing the forward-looking information in this news release are reasonable, including that all necessary regulatory approvals will be obtained in a timely manner, undue reliance should not be placed on such information, which only applies as of the date of this news release, and no assurance can be given that such events will occur in the disclosed time frames or at all. noram disclaims any intention or obligation to update or revise any forward-looking information, whether as a result of new information, future events or otherwise, other than as required by applicable securities laws.

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

SOURCE: noram lithium corp.



View source version on accesswire.com:
https://www.accesswire.com/771106/Noram-Lithium-Provides-Update

News Provided by ACCESSWIRE via QuoteMedia

NRM:CA
The Conversation (0)
Noram Lithium Engages CDMG for Marketing Services

Noram Lithium Engages CDMG for Marketing Services

noram lithium corp. ("noram" or the "Company") (TSXV:NRM)(OTCQB:NRVTF)(Frankfurt:N7R) announces that it has engaged Creative Direct Marketing Group Inc. ("CDMG") to provide the Company with marketing services and to raise public awareness of the Company

"A leader in targeted advertising, Creative Direct Marketing Group, Inc is a full-service, direct response advertising and digital marketing agency with one goal in mind: increasing your response, market presence, and profits through ‘accountable advertising.' For more than 40 years, we've helped turn entrepreneurial start-ups into large companies and large companies into multibillion-dollar businesses" commented CDMG.

News Provided by ACCESSWIRE via QuoteMedia

Keep reading...Show less
Noram Lithium Announces Appointment of Vice President, Project Development

Noram Lithium Announces Appointment of Vice President, Project Development

noram lithium corp. ("noram" or the "Company") (TSXV:NRM)(OTCQB:NRVTF)(Frankfurt:N7R) announced today it has appointed Mr. Glenn Barr as Vice President, Project Development, effective immediately

Mr. Barr has more than 25 years of experience in complex mining project development. Most recently he was Vice President, Project Development at Twin Metals Minnesota (TMM). His work included leading engineering studies, overseeing metallurgical test work programs and integrating environmental protection measures into project design. Prior to TMM, he held various roles at Stantec and Teck. As an Engineering Liaison at Stantec, he guided the environmental and engineering consultants in ensuring alignment and work efficiencies. While at Teck, he was integral in the development and commercialization of a novel hydrometallurgical process, and was a key member of the team that engineered and constructed a hydrometallurgical processing plant in Brazil. Mr. Barr holds a Bachelor of Science, Chemistry from the University of Victoria.

News Provided by ACCESSWIRE via QuoteMedia

Keep reading...Show less
Noram Lithium Engages Ausenco To Complete the Pre-Feasiblity Study for the Zeus Lithium Project

Noram Lithium Engages Ausenco To Complete the Pre-Feasiblity Study for the Zeus Lithium Project

noram lithium corp. ("noram" or the "Company") (TSXV:NRM)(OTCQB:NRVTF)(Frankfurt:N7R) announces it has engaged Ausenco Engineering Canada Inc. ("Ausenco") to lead the Pre-Feasibility Study ("PFS") of its 100% owned Zeus Lithium Project ("Zeus" or the "Project") in Clayton Valley, Nevada

The Company recently engaged SRK Consulting Inc ("SRK") to produce an optimized mine plan for Zeus (see news release dated February 7, 2023) and initiated a further round of metallurgical testing with Kemetco Research Inc ("Kemetco") to confirm and refine the process design for the Project (see news release dated February 14, 2023). Both of these ongoing work streams will form the basis of the PFS, now being managed by Ausenco.

News Provided by ACCESSWIRE via QuoteMedia

Keep reading...Show less
Noram Lithium Files NI43-101 Technical Report for Zeus Lithium Project

Noram Lithium Files NI43-101 Technical Report for Zeus Lithium Project

noram lithium corp. ("noram" or the "Company") (TSXV:NRM)(OTCQB:NRVTF)(Frankfurt:N7R) announced today that it has filed on SEDAR a National Instrument 43-101 ("NI 43-101") technical report (the "Report") titled "Updated Resource Estimate Zeus Lithium Project". The technical report supports the updated Mineral Resource Estimate announced on January 30, 2023 and is available for review on both SEDAR (www.sedar.com) and the Company's website (www.noramlithiumcorp.com). There are no material differences in the mineral resources reported in the news release of January 30, 2023 and those described in the report

About noram lithium corp.

News Provided by ACCESSWIRE via QuoteMedia

Keep reading...Show less
Noram Lithium Announces Results From 2023 Annual General Meeting

Noram Lithium Announces Results From 2023 Annual General Meeting

noram lithium corp. ("noram" or the "Company") (TSXV:NRM)(OTCQB:NRVTF)(Frankfurt:N7R) announces that all motions put forward for approval at its 2023 Annual General Meeting held March 14th in Vancouver, British Columbia (the "AGM") were passed

2023 Annual General Meeting Results

News Provided by ACCESSWIRE via QuoteMedia

Keep reading...Show less
Altech Batteries Ltd  Cerenergy Battery Project Funding Progressing Well

Altech Batteries Ltd Cerenergy Battery Project Funding Progressing Well

Perth, Australia (ABN Newswire) - Altech Batteries Limited (ASX:ATC,OTC:ALTHF) (FRA:A3Y) (OTCMKTS:ALTHF) is pleased to announce an update on funding of the CERENERGY(R) sodium-chloride solid-state battery project in Saxony, Germany.

DEBT PROCESS

As previously mentioned, Altech has engaged ten commercial banks and two venture debt funds in the first round of financing discussions, receiving largely positive initial feedback. Based on this feedback, the Company has selected a preferred financial institution- a European bank with a proven track record in providing debt funding for technology-driven projects, particularly those within the innovation sector.

Although the mandate has not yet been formally executed, Altech intends to make an official announcement once this step is complete.

Meanwhile, the bank's commercial and technical teams have been diligently conducting a comprehensive review of the Cerenergy projects and its technology. The technical due diligence process is critical for ensuring that the project meets the bank's financing and risk criteria. As part of this process the onsite Altech experts are in detailed discussions with the bank's representative. The banks have visited Dresden and the Fraunhofer testing facilities and visit Hermsdorf, Germany where the prototype production is located in the coming weeks, which will be a key step in concluding the technical evaluation.

In parallel with these efforts, Altech is progressing discussions for securing a federal government guarantee, which would further strengthen its ability to secure the necessary debt funding for the project. Officials from the Ministry of Finance have already been briefed on the initiative, and the due diligence process for the application is actively underway. This federal guarantee will serve as an underwriter and therewith derisk any debt funding for the project substantially.

EQUITY FUNDING

In parallel with ongoing debt financing efforts, the Group has engaged several equity advisers to assist in securing the equity component of the project's funding package. As part of this strategy, Altech plans to divest a minority interest in the project to one or two strategic investors. This partial divestment is intended to attract investors who can contribute not only capital, but also strategic value, aligning with the CERENERGY(R) project's long-term goals of growth and sustainability.

The Group on one hand is specifically targeting large utility companies, data centre operators, investment funds, and corporations that are deeply committed to the green energy transition and on the other hand industrial partners with access and know-how and resources relevant to Cerenergy battery production, implementation or market access. These potential partners are seen as ideal due to their strong alignment with the project's sustainable energy focus and their ability to provide significant financial support. Progress in equity discussions has been promising, with several Non-Disclosure Agreements (NDAs) signed, enabling deeper engagement with prospective investors. Additionally, draft term sheets have been circulated to interested parties, outlining the key terms and conditions for investment. These documents provide a foundation for negotiations and facilitate more detailed discussions around the equity stake and partnership structure.

The decision to divest part of the project is strategically aimed at easing the Company's financial burden while bringing in experienced partners who can contribute to the project's success. By securing both equity and debt financing, Altech aims to finalize the full funding package, ensuring the timely construction and commissioning of the CERENERGY(R) battery plant. Moving forward, the focus will be on advancing these discussions and converting interest into formal commitments, which are critical for the project's progression.

GRANT APPLICATIONS

Altech has been actively applying for various grants offered by the State of Saxony, Federal Government of Germany, and the European Union. The State of Saxony and Brandenburg, along with the European Union, offer substantial support for renewable energy projects, including grants aimed at converting lignite coal to renewable energy sources. These grants are part of broader efforts to transition regions dependent on fossil fuels toward sustainable energy solutions. Altech's site, located in these areas, stands to benefit from various funding programs designed to support clean energy projects, including EU grants for energy transformation and innovation. Altech has applied for several of these grants to advance its CERENERGY(R) project, securing essential financial backing for technology development, high-tech industries, expert employment and infrastructure upgrades.

OFFTAKE ARRANGEMENTS

Altech has secured three key Offtake Letters of Intent (LOIs) for 100% of its CERENERGY(R) production.

1. Zweckverband Industriepark Schwarze Pumpe (ZISP): An agreement was signed on 13 September 2024 for ZISP to purchase 30 MWh of energy storage capacity annually, consisting of 1MWh GridPacks, for the first five years of production. The purchase is contingent on performance tests and battery specifications meeting customer requirements.

2. Referenzkraftwerk Lausitz GmbH (RefLau): A second LOI was executed with RefLau, a joint venture between Enertrag SE and Energiequelle GmbH. RefLau will buy 30 MWh of CERENERGY(R) storage n the first year, increasing to 32 MWh annually for the next four years. Additionally, Altech will purchase green electricity for its planned production plant.

3. Axsol GmbH: A third LOI was signed with Axsol, a leading renewable energy solutions provider. Axsol will exclusively distribute CERENERGY(R) batteries to the Western defense industry, facilitating early market entry and sales. These agreements are crucial for financing and advancing the CERENERGY(R) project.

 

About Altech Batteries Ltd:  

Altech Batteries Limited (ASX:ATC,OTC:ALTHF) (FRA:A3Y) is a specialty battery technology company that has a joint venture agreement with world leading German battery institute Fraunhofer IKTS ("Fraunhofer") to commercialise the revolutionary CERENERGY(R) Sodium Alumina Solid State (SAS) Battery. CERENERGY(R) batteries are the game-changing alternative to lithium-ion batteries. CERENERGY(R) batteries are fire and explosion-proof; have a life span of more than 15 years and operate in extreme cold and desert climates. The battery technology uses table salt and is lithium-free; cobalt-free; graphite-free; and copper-free, eliminating exposure to critical metal price rises and supply chain concerns.

The joint venture is commercialising its CERENERGY(R) battery, with plans to construct a 100MWh production facility on Altech's land in Saxony, Germany. The facility intends to produce CERENERGY(R) battery modules to provide grid storage solutions to the market.

 

News Provided by ABN Newswire via QuoteMedia

Keep reading...Show less