Endeavour Silver Provides Update on Guanacevi Trunnion Failure

Endeavour Silver Corp. ("Endeavour" or the "Company") (NYSE: EXK; TSX: EDR) provides an update to the Guanacevi primary ball mill trunnion failure that was reported on August 12, 2024.

Processing has resumed at the Guanacevi mine site. Temporary modifications have been completed within the plant to re-purpose one of the regrind mills as the primary ball mill which is currently milling at a rate of 400 tonnes per day (tpd). While the grinding circuit is being closely monitored, there is potential for the plant to operate near 500 tpd or close to half of its planned production capacity of 1,200 tpd during this temporary phase.

During this time, mining operations will continue at a reduced rate without comprising safety or the long-term viability of the ore body. The operations will focus on feeding the highest-grade ore to the mill and stockpiling the remaining material. Contract mining activities and local third-party material purchases will cease until the process plant operations have returned to full capacity. These temporary solutions are intended to manage cash flows until the primary mill is fully operational. Using current metal prices, the preliminary estimate indicates a cash shortfall could be limited to during this period of reduced processing is less than US$5 million over an estimated 15-week period. This cash outflow includes accumulating ore stockpile with self-mining activities.

Constructive discussions have been held with our workforce, communities and suppliers to address the potential implications and broader social impact of these temporary measures.

Initial quotes for the trunnion fabrication and installation have been obtained with an estimated fabrication cost of US$0.5 million and a period of 16-weeks to installation. Management is assessing several alternatives to shorten the estimated downtime of the primary ball mill.

During this reduced processing period, Guanacevi production is estimated to decrease by 0.9 million to 1.1 million silver ounces and by 2,000 to 3,000 gold ounces compared to its original operating plan. Annual consolidated silver production for 2024 is expected to range from 4.4 to 4.6 million ounces, and gold production is expected to be between 36,000 ounces and 38,000 ounces. Silver equivalent production for 2024 is now forecast to total between 7.3 million and 7.6 million ounces. We achieved 4.4 million silver equivalent ounces in the first half of the year.

Due to the reduced operating capacity for 15 weeks, operating costs and all in sustaining cost metrics will be higher than originally guided for 2024. Due to the number of variables, estimates and remaining uncertainties, management is withdrawing its cost guidance at this time.

About Endeavour Silver   Endeavour is a mid-tier precious metals company with a strong commitment to sustainable and responsible mining practices. With operations in Mexico and the development of the new cornerstone mine in Jalisco state, the company aims to contribute positively to the mining industry and the communities in which it operates. In addition, Endeavour has a portfolio of exploration projects in Mexico, Chile and the United States to facilitate its goal to become a premier senior silver producer.

Contact Information
Allison Pettit, Director Investor Relations
Tel: (877) 685 - 9775
Email: apettit@edrsilver.com
Website: www.edrsilver.com

Follow Endeavour Silver on Facebook , X , Instagram and LinkedIn

Cautionary Note Regarding Forward-Looking Statements

This news release contains "forward-looking statements" within the meaning of the United States private securities litigation reform act of 1995 and "forward-looking information" within the meaning of applicable Canadian securities legislation. Such forward-looking statements and information herein include but are not limited to statements regarding the suspension of processing at Guanacevi, timing for completion of repairs at the Guanacevi mill, the availability and assessment of alternative processing methods, the impact on Q3 production and annual production and cost guidance, and Endeavour's anticipated performance in 2024 including changes in mining operations and forecasts of production levels, anticipated production costs and all-in sustaining costs. The Company does not intend to and does not assume any obligation to update such forward-looking statements or information, other than as required by applicable law.

Forward-looking statements or information involve known and unknown risks, uncertainties and other factors that may cause the actual results, level of activity, production levels, performance or achievements of Endeavour and its operations to be materially different from those expressed or implied by such statements. Such factors include but are not limited to the ability to complete repairs at the Guanacevi mill in a timely manner, the availability of alternative processing methods, changes in production and costs guidance; and satisfaction of conditions precedent to drawdown under the Debt Facility; as well as those factors described in the section "risk factors" contained in the Company's most recent form 40F/Annual Information Form filed with the S.E.C. and Canadian securities regulatory authorities.

Forward-looking statements are based on assumptions management believes to be reasonable, including but not limited to: the ability to complete repairs at the Guanacevi mill in a timely manner, the availability of alternative processing methods, the continued operation of the Company's mining operations, no material adverse change in the market price of commodities, forecasted mine economics as of 2024, mining operations will operate and the mining products will be completed in accordance with management's expectations and achieve their stated production outcomes, and such other assumptions and factors as set out herein. Although the Company has attempted to identify important factors that could cause actual results to differ materially from those contained in forward-looking statements or information, there may be other factors that cause results to be materially different from those anticipated, described, estimated, assessed or intended. There can be no assurance that any forward-looking statements or information will prove to be accurate as actual results and future events could differ materially from those anticipated in such statements or information. Accordingly, readers should not place undue reliance on forward-looking statements or information.


Primary Logo

News Provided by GlobeNewswire via QuoteMedia

EDR:CA,EXK
The Conversation (0)
Endeavour Silver Announces 2024 Annual General Meeting Voting Results

Endeavour Silver Announces 2024 Annual General Meeting Voting Results

Endeavour Silver Corp. ("Endeavour" or the "Company") (NYSE: EXK; TSX: EDR) is pleased to announce that shareholders voted in favour of all items of business at the Company's 2024 Annual General Meeting ("AGM") held on May 28, 2024 in Vancouver. A total of 104,090,503 votes were cast or represented by proxy at the AGM, representing 43.31% of the outstanding common shares as of the record date. The following is a tabulation of the votes submitted by proxy:

DIRECTORS

NUMBER   OF   SHARES PERCENTAGE   OF   VOTES   CAST
FOR WITHHELD/
ABSTAIN
FOR WITHHELD
Rex J. McLennan 50,212,585 11,699,944 81.10% 18.90%
Margaret M. Beck 61,370,134 542,396 99.12% 0.88%
Ricardo M. Campoy 61,455,874 456,656 99.26% 0.74%
Daniel Dickson 61,461,186 451,345 99.27% 0.73%
Amy Jacobsen 61,364,651 547,879 99.12% 0.88%
Kenneth Pickering 53,516,716 8,395,815 86.44% 13.56%
Mario D. Szotlender 61,428,282 484,248 99.22% 0.78%
Angela Johnson 61,333,538 578,992 99.06% 0.94%

All director nominees were re-elected, including the addition of Angela Johnson to the Board of Directors (see news release dated April 18, 2024 ) to fill vacancy left by the retirement of Christine West.

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
Endeavour Silver Highlights Progress on its Three-Year Sustainability Strategy in 2023 Sustainability Report

Endeavour Silver Highlights Progress on its Three-Year Sustainability Strategy in 2023 Sustainability Report

Endeavour Silver Corp. ("Endeavour" or the "Company") (TSX: EDR, NYSE: EXK) made further progress executing its 2022-2024 Sustainability Strategy as outlined in the Company's 2023 Sustainability Report released today.

Entitled "Transformation in Motion", the report provides insights into Endeavour's sustainability performance and approach over 2023, including second-year progress highlights against the strategy.

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
Boab Metals Limited

Corporate Presentation December 2024

Boab Metals Limited (ASX: BML) (“Boab” or “Company”) is pleased to present its investor presentation.


Keep reading...Show less
Alex Wallis, vice president of exploration at Silver47 Exploration.

Silver47 Beefs Up Drilling Plans to Expand Resource at Red Mountain Polymetallic Project

Following release of the final results from Silver47 Exploration's (TSXV:AGA) 2024 exploration program, the company is beefing up plans for a more expansive and targeted drill campaign in the new year at its flagship Red Mountain project in Alaska. Alex Wallis, vice president of exploration, said the aim is to “increase both the grade and the tonnage."

“With the modern drilling and the recoveries we saw this year, we have a really good chance to increase just from infilling the historic zones to really bulk that resource out as well,” he said.

Approximately 20 percent of future drilling efforts will focus on fresh exploration targets like Galleon and Horseshoe, according to Wallis. The company is eyeing more than 15 exploration targets at Red Mountain that have never been drill tested with geochemical and geophysical targeting.

Keep reading...Show less
  Unico Silver Limited

Cerro Leon drill results

Further high-grade mineralisation identified at the Karina prospect

Unico Silver Limited (“USL” or the “Company”) is pleased to announce first assay results from ongoing drilling at the Cerro Leon project, located in the Santa Cruz province of Argentina.

Keep reading...Show less

First Majestic Announces Mailing of Materials for Special Meeting

First Majestic Silver Corp. (NYSE: AG) (TSX: AG) (FSE: FMV) (the "Company" or "First Majestic") is pleased to announce that it has commenced mailing of its meeting materials for the special meeting of the Company's shareholders (the "Special Meeting") that will be held on Tuesday, January 14, 2025 at 11:00 a.m. (Pacific Time) at the offices of Bennett Jones LLP, located at Suite 2500 - 666 Burrard Street, Vancouver, British Columbia V6C 2X8.

At the Special Meeting, pursuant to the requirements of the rules of the Toronto Stock Exchange and the New York Stock Exchange, First Majestic shareholders will be asked to approve an ordinary resolution (the "Share Issuance Resolution") approving the issuance of up to 190,000,000 common shares of First Majestic ("First Majestic Shares") to stockholders of Gatos Silver, Inc. ("Gatos") in connection with the previously announced acquisition by First Majestic of all of the shares of common stock of Gatos (the "Transaction"). First Majestic's Board of Directors unanimously recommends that the Company's shareholders vote FOR the Share Issuance Resolution.

News Provided by Newsfile via QuoteMedia

Keep reading...Show less

Pan American Silver Provides Annual Exploration Update

Pan American Silver Corp. (NYSE: PAAS) (TSX: PAAS) ("Pan American" or the "Company") provides an annual exploration update and releases new exploration drill results for its Jacobina, El Peñon, La Colorada, Huaron, Minera Florida and Timmins mines, as well as its La Colorada Skarn project.

"The success of our exploration program highlights the potential for long-term organic growth at many of our assets," said Christopher Emerson, Vice President of Exploration and Geology at Pan American. "Based on the results we were achieving in exploration this year, we increased our drill budget to over 450,000 metres for 2024. This exploration update highlights these results, and showcases the ongoing discovery of new mineralized structures in and around our existing mining operations."

News Provided by Business Wire via QuoteMedia

Keep reading...Show less
Boab Metals

Boab Metals Limited (ASX: BML) – Trading Halt

Boab Metals Limited (ASX:BML) (the “Company”) hereby requests a trading halt of its securities be granted by the ASX effective immediately, pending a release of an announcement regarding an Offtake and Project Finance Agreement. The trading halt will last until the earlier of commencement of trading on Wednesday, 11 December 2024 or the release to the market of an announcement as specified above. The Company is not aware of any reason why the trading halt should not be granted or of any other information necessary to inform the market about the trading halt. This request was authorised for release by the Board of the Company.

Keep reading...Show less

Latest Press Releases

Related News

×