Auric Mining

First Cash Expected in Week Commencing 23 October 2023. Jeffreys Find Stage One Production Passes 7,700 Ounces.

Auric Mining Limited (ASX: AWJ) (Auric or the Company) is pleased to update the ASX on Stage One mining from the Jeffreys Find Gold Mine near Norseman. As at Sunday 15 October 2023, more than 7,700 ounces of gold have been produced. As at Tuesday 17 October 2023, 5,667 ounces have been sold generating gross revenue of $16,612,642.


Highlights

  • Stage One gold production surpasses 7,700 ounces at 15 October 2023 as toll milling continues.
  • Total of 166,000 tonnes of gold ore now delivered to the Greenfields Mill at Coolgardie for processing.
  • On target to process 180,000 tonnes for Stage One.
  • Expected to produce more than 9,500 ounces.
  • First cash to Auric expected in week commencing 23 October 2023.
Auric’s partner, BML Ventures Pty Ltd of Kalgoorlie, (BML) has confirmed it expects all ore to be transported from Jeffreys Find to the Greenfields Mill by the 23 October 2023.

“It looks as though the First Stage mining of Jeffreys Find will produce more than 9,500 ounces. At this point of the campaign it’s running through the mill at almost 1.97g/t but we have 15,000 tonnes of lower grade ore at the end which will pull the average grade down slightly,” said Managing Director Mark English.

“Overall,it’satremendousresultforAuric.Idon’tknowofanyotherjuniorminersin the last couple of years that have gone from tenement acquisition to mining and free cash in the timeframe we have.

To date the Stage One pit has delivered everything we predicted for the joint parties. Gross revenue from mining Jeffreys Find should exceed $28 million when it’s completed and produce more than $8 million in surplus cash.

We expect first cash proceeds to Auric next week,” said Mr English.

Status of Jeffreys Find Production as at Sunday, 15 October 2023

*Unreconciled mill calculation

Status of Jeffreys Find Gold Sales as at Tuesday, 17 October 2023

*As at 17 October 2023, there is gold in an account at Perth Mint, gold in production, in transit and in circuit at Greenfields Mill.

BML are incurring and paying all mining costs and expenses. After completing the first stage of mining the partners will subtract all costs, including a cash retention for the second stage pit, before splitting the surplus cash proceeds on a 50:50 basis. This will provide Auric with a substantial cash boost, throughout October and November 2023.

A Second Stage mining of Jeffreys Find will commence early in 2024.

The entire project life is short and final mining is expected to be completed late 2024/early 2025. The project budgeted for a gold price of AUD$2,600/ounce. A substantially higher price has subsequently placed the joint venture in a more favourable position. Cash generated for Auric will be used principally to progress the development of the Munda Gold Deposit at Widgiemooltha.

Auric will continue to update the ASX market on production, yield, gross revenue and cash distributions from Jeffreys Find as information comes to hand.


Click here for the full ASX Release

This article includes content from Auric Mining, licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.

AWJ:AU
Auric Mining

Auric Mining Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

The Conversation (0)
Auric Mining (ASX:AWJ)

Auric Mining


Keep reading...Show less
EMU NL

Quarterly Activity Report 31 March 2024

EMU NL (ASX: EMU) (“EMU” or “the Company”) is pleased to report on its activities for the quarter ending 31 March 2024.

Keep reading...Show less
Redstone Resources

Quarterly Report for the Period Ending 31 March 2024

Redstone Resources Limited (ASX: RDS) (Redstone or the Company) is pleased to provide its quarterly report for the period ending 31 March 2024 (the Quarter).

Keep reading...Show less
Metals Australia

Metals Australia Quarterly Activities Report - to 31 March 2024

Metals Australia Limited (ASX: MLS) (“Metals Australia”, the “Company” or “MLS”) is pleased to report its activities for the quarter ended 31 March 2024 (“Quarter”):

Keep reading...Show less
Basin Energy Logo

Basin Energy Mining Exploration Entity or Oil and Gas Exploration Entity Quarterly Cash Flow Report

Basin Energy (ASX:BSN) is pleased to announced its mining exploration entity or oil and gas exploration entity quarterly cash flow report.

Keep reading...Show less
Basin Energy Logo

Basin Energy Quarterly Activities Report for the Period Ending 31 March 2024

Basin Energy Ltd (ASX: BSN) (‘Basin’, or the ‘Company’) is pleased to provide an overview of activities for the period ending 31 March 2024 (‘Quarter’, ‘Reporting Period’) and an accompanying Appendix 5B.

Keep reading...Show less
Auric Mining (ASX:AWJ)

Auric Mining Quarterly Activities Report

31 March 2024

Auric Mining Limited (ASX: AWJ) (Auricor the Company) is pleased to report on its activities during the 31 March 2024 Quarter and up to the date of this announcement.

Keep reading...Show less
Auric Mining

Auric Mining Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

Latest Press Releases

Related News

×