- AustraliaNorth AmericaWorld
Investing News NetworkYour trusted source for investing success
- Lithium Outlook
- Oil and Gas Outlook
- Gold Outlook Report
- Uranium Outlook
- Rare Earths Outlook
- All Outlook Reports
- Top Generative AI Stocks
- Top EV Stocks
- Biggest AI Companies
- Biggest Blockchain Stocks
- Biggest Cryptocurrency-mining Stocks
- Biggest Cybersecurity Companies
- Biggest Robotics Companies
- Biggest Social Media Companies
- Biggest Technology ETFs
- Artificial Intellgience ETFs
- Robotics ETFs
- Canadian Cryptocurrency ETFs
- Artificial Intelligence Outlook
- EV Outlook
- Cleantech Outlook
- Crypto Outlook
- Tech Outlook
- All Market Outlook Reports
- Cannabis Weekly Round-Up
- Top Alzheimer's Treatment Stocks
- Top Biotech Stocks
- Top Plant-based Food Stocks
- Biggest Cannabis Stocks
- Biggest Pharma Stocks
- Longevity Stocks to Watch
- Psychedelics Stocks to Watch
- Top Cobalt Stocks
- Small Biotech ETFs to Watch
- Top Life Science ETFs
- Biggest Pharmaceutical ETFs
- Life Science Outlook
- Biotech Outlook
- Cannabis Outlook
- Pharma Outlook
- Psychedelics Outlook
- All Market Outlook Reports
Abra Construction At 97% Complete – First Ore Stockpiled For January Processing
GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 97% complete as of 30 November 2022. Processing plant commissioning is progressing quickly with practical completion now expected in December 2022. Ore currently being mined from underground is being stockpiled in readiness for processing to begin in January 2023. Concentrate production will commence January 2023.
Managing Director, Tony James commented, “Record underground development in November with delivery of the first 9,000t of ore to the ROM pad along with successful plant commissioning to date puts Abra on the verge of a quick transition into production. Recruitment and other operational readiness activities are well advanced in preparation for January production”.
Figure 1 – First material being tipped into the crusher during commissioning (Photo 26 November).
Figure 2 – Crushing and screening plant commissioning (Photo 26 November).
The following link will show a short video of the Abra crusher commissioning. https://youtube.com/shorts/iSG58MiW_3o
Update on Abra Project progress
Overall progress continues as planned, with first concentrate production expected in Q1 CY2023, following ore commissioning in January 2023. Practical completion of the processing plant is now expected ahead of schedule in December 2022. The processing plant engineering, procurement and construction has reached 99% complete. Piping and electrical works have made significant progress and at the end of November were 96% and 92% complete, respectively. Mechanical items installation is almost complete at 99%.
In November, the first material was crushed and screened as part of the staged commissioning process. The crushing plant ran at design capacity and all commissioning milestones were successfully achieved. Dry commissioning also progressed in most areas of the plant including water and air services, tailings and concentrate thickening, grinding and reagents. Dry commissioning of the remaining areas will be completed in December. Water commissioning commenced in the tailings and concentrate thickening areas of the plant and the remaining areas are expected to be wet commissioned by the end of December. The remaining commissioning schedule is unchanged from the last update and is shown below in Table 1.
Click here for the full ASX Release
This article includes content from Galena Mining, licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.
Galena Mining Investor Kit
- Corporate info
- Insights
- Growth strategies
- Upcoming projects
GET YOUR FREE INVESTOR KIT
Galena Mining
Overview
Galena Mining Limited (ASX:G1A, Galena) owns 60 percent of the Abra base metals mine located in the Gascoyne region of Western Australia - home to one of the largest lead and silver deposits in the world, set to produce the highest-grade, cleanest lead concentrate available globally. The company is capitalizing on its Tier 1 asset in a Tier 1 jurisdiction, strengthened by and leveraging partnerships with Japan's largest zinc and lead smelter, as well as with one of the top base metals trading firms in the world.
The company also owns 100 percent of the Jillawarra Project, which covers 76 kilometers of strike extension directly to the west of Abra. The Jillawarra Project contains several large-scale analogous exploration targets including the Woodlands Complex, Quartzite Well and Copper Chert areas.
Galena's major partnerships include Toho Zinc (TSE:5707), Japan's largest zinc and lead smelter, and IXM SA, one of the world's top three base metals trading firms. Toho provided AU$90 million project equity and has a long-term offtake agreement to purchase 40 percent of Abra's production; while IXM has entered into a 10-year take-or-pay offtake contract to purchase the remaining 60 percent.
The company's management team brings decades of experience in the mining and base metals industry and has a proven track record of success throughout all stages of exploration, from development to production.
In November 2020, Galena put in place US$110 million in finalized debt facilities arranged by Taurus Funds Management. The facilities include a US$100-million project finance facility plus a US$10-million cost overrun facility.
The project finance facility consists of a 69-month term loan primarily to fund capital expenditures for the development of Abra. Key terms include:
- Fixed interest of 8 percent per annum on drawn amounts, payable quarterly in arrears.
- 1.125 percent net smelter return royalty.
- No mandatory hedging.
- Early repayment allowed without penalty.
- 15 quarterly repayments commencing on 31 December 2023.
The cost overrun facility is a loan to finance identified cost overruns on the project in capital expenditure and working capital. Fixed interest of 10 percent per annum applies to amounts drawn under the cost overrun facility.
The Taurus debt facilities have been fully drawn and are secured against Abra Project assets and over the shares that each of Galena and Toho own in Abra.
Company Highlights
- Positioned to realize value for shareholders:
- Abra mine construction completed in December 2022, on time and on budget.
- First in-specification concentrate shipment achieved in March 2023.
- Abra is one of the largest and cleanest lead-silver deposits in the world (high-grade, high-value concentrate 1/10th typical deleterious elements).
- Exciting exploration ground and known copper-gold mineralisation below the Abra lead-silver deposit.
- JV between Galena (60 percent) and Japan's largest zinc and lead smelter Toho Zinc (40 percent) underpins long mine life (10+ years) in an exciting new mineral province in Western Australia.
- Galena has a 10-year offtake agreement with IXM, one of the world’s largest base metals traders.
- Annual steady-state guidance:
- Mill throughput of more than 1.3 million tonnes per annum (Mtpa), producing +90,000 tonnes per annum lead and +550,000 ounces per annum silver.
- Annual average lead C1 direct cash cost of US$0.55 to US$0.65/lb.
- Annual average EBITDA (earnings before interest, taxes, depreciation, and amortization) of AU$90 million to $100 million.
- The Abra mine is located in the Gascoyne Region of Western Australia, home to one of the largest undeveloped lead deposits in the world and the highest-grade lead concentrate available, globally.
- The Abra mine carries a JORC mineral resource estimate (July 2023) of 16.2 million tons (Mt) at 7.3 percent lead and 19 grams per ton (g/t) silver in the indicated category, and 16.9 Mt at 6.9 percent lead and 15 g/t silver in the inferred category.
- Abra has been named the world's lowest-cost primary lead mine by Wood Mackenzie, a leading mining research and consultancy group.
- US$110 million of project financing debt facilities from leading mining-specialist lending fund Taurus Funds Management.
- Galena's management team brings decades of experience in the mining and base metals industry and has a proven track record of success throughout all stages of exploration, from development to production.
Key Projects
Abra Mine
The Abra Mine is a 60:40 joint venture between Galena and Japanese lead producer Toho Zinc. It is a globally significant lead-silver project located in the Gascoyne region of Western Australia, between the towns of Newman and Meekatharra approximately 110 kilometers from the DeGrussa copper mine owned by Sandfire Resources (ASX:SFR).
Abra Mine Site Location
The Abra mine carries a total JORC mineral resource estimate published in July 2023 of 33.4 Mt at 7.1 percent lead and 17 g/t silver (5 percent Pb cut-off grade), which includes 0.3 Mt at 7.3 percent lead and 32 g/t silver in the measured category; 16.2 Mt at 7.3 percent lead and 19 g/t silver in the indicated category; and 16.9 Mt at 6.9 percent lead and 15 g/t silver in the inferred category.
All permits for the Abra project have been obtained from the appropriate Western Australian regulatory bodies. The project is also subject to an existing land use and heritage agreement with the Jidi Jidi Aboriginal Corporation. The Abra property is well-serviced by public roads and highways, and all the necessary infrastructure has been developed to transport lead-sulphide concentrates to the Port of Geraldton, Abra's primary export port.
Abra Processing Plant
A final investment decision to complete the Abra Project was made in June 2021 and construction was completed in December 2022, on time and on budget. Several important milestones were achieved in the March 2023 quarter, including the commissioning of the processing plant, first ore fed into the plant and first concentrate produced in January 2023.
The processing plant achieved in-specification concentrate production from the commencement of concentrate production and during the 2023 calendar year, 967,622 tons of ore was processed and 61,800 tons of lead concentrate was produced.
The company is currently undertaking detailed technical work to develop an updated production plan for 2024 production targets and guidance.
Jillawarra Project
Exploration and growth associated with the 100 percent Galena-owned Jillawarra Project covers a highly prospective elongated tenement package covering approximately 76 kilometers of continuous strike length and 508 square kilometers directly to the west of Abra.
The Jillawarra Project hosts many base metals prospects which have had limited shallow exploration work completed since the 1970s by various companies. The bulk of the exploration work was completed by Amoco, Geopeko, Apex Minerals and Abra Mining Limited. The work completed to date has identified several base metals, manganese and gold prospects, of which the Woodlands Complex, Quartzite Well, Manganese Range, Copper Chert, TP and 46-40 were subject to early-stage exploration. Most of the drilling completed within the Jillawarra Project investigated the first 100 to 200-meter depth which, based on recent knowledge of Abra, may not have reached the depths required.
The main prospective corridor within the Jillawarra Project lies within the margins of the Quartzite Well – Lyons River Fault zones which extend east-west along the entire tenement package. Also, the contact between the dolomitic sediments of Irregully Formation and the lower sedimentary unit, polymictic conglomerate, of the Kiangi Creek Formation represents an important marker for the occurrence of base metal mineralisation as seen at Abra.
The Woodlands Complex is an Australian scaled geophysical anomaly which represents a significant target area with the anomaly being 12 kilometers long and 10 kilometers wide. Limited work and technical evaluation have occurred at Woodlands which presents a great opportunity for Galena in the years to come. Ongoing geophysical and exploration drilling will occur concurrently with the development of Abra. The knowledge and understanding of Abra due to its development will provide a significant exploration advantage at Jillawarra.
Management Team
Tony James – Managing Director and CEO
Tony James is a mining engineer with over 30 years’ mine operating and project development experience predominantly in Western Australia. He also has previous experience at managing director level of three ASX-listed companies with two of those companies successfully guided through a merger and takeover process benefiting the shareholders. He has a strong mine operating background (examples being the Kanowna Belle gold mine and the Black Swan nickel mine) and a strong feasibility study / mine development background (examples being the Pillara zinc/lead mine and the Trident/Higginsville gold mine).
Adrian Byass – Non-executive Chairman
Adrian Byass has more than 25 years of experience in the mining industry both in listed and unlisted entities globally. He has served as non-executive and executive director of various listed and unlisted mining entities, which have successfully transitioned to production in bulk, precious and specialty metals around the world. He currently serves on the boards of ASX gold, base metals and lithium companies.
Neville Gardiner – Non-executive Director
Neville Gardiner has over 30 years of experience advising boards on mergers and acquisitions,
equity and debt capital markets, transaction structuring, capital allocation and complex
commercial arrangements. His career achievements include senior executive leadership
roles in Deloitte, Torridon Partners, and at Bank of America Merrill Lynch, where he spent five years as the head of its Australian Natural Resources Team. He also spent nine years with Macquarie Bank, where he had responsibility for its Western Australian Corporate Finance business and its Australian Oil and Gas Advisory business. He has a very strong experience and knowledge base associated with the resources sector in Australia.
Stewart Howe – Non-executive Director
Stewart Howe has more than 40 years of experience in the global resource industry including 18 years in mining. He was chief development officer at Zinifex, one of the world’s largest miners and smelters of lead and zinc. He led the spin-off of Zinifex’s smelters to create Nyrstar NV, and restarted the development of the Dugald River mine.
Craig Barnes – Chief Financial Officer
Craig Barnes has over 25 years of experience in senior finance and financial management within the mining industry and previously the financial services industry. He has considerable experience in project financing, mergers and acquisitions, joint ventures, treasury and implementation of accounting controls and systems.
Before joining Galena, he held the position of CFO of Paladin Energy for more than five years and was part of the team that successfully completed the company's capital restructuring in 2018. Prior to that, he was the chief financial officer of DRDGOLD (NYSE and JSE:DRD) and its affiliated subsidiaries for more than seven years.
Aida Tabakovic – Company Secretary
Aida Tabakovic has over 11 years of experience in the accounting profession, which includes financial accounting reporting, company secretarial services, ASX and ASIC compliance requirements. She has been involved in listing several junior exploration companies on the ASX and is currently company secretary for numerous ASX-listed companies
Abra Construction At 92% Complete – Reaches First Ore Underground
Managing Director, Tony James commented, “Reaching first ore underground is extremely rewarding for everyone involved in the project. To see for the first time what we have predicted and interpreted as the Abra orebody delivers a significant step forward for the project. Record development metres in October has taken the mine to the ore and we continue to establish key underground infrastructure with the completion of the 6m diameter surface rise that will be the primary return airway.”
Update on Abra Project progress
Overall progress continues to remain in line for Project completion, with first commercial production expected in Q1 CY2023. The processing plant engineering, procurement and construction has reached 97% complete. Structural steel has been completed in October and mechanical installations are at 96% complete. Piping at 80% and electrical at 71% complete continue to progress quickly.
Pacific Energy’s Hybrid 10MW LNG/solar power station completed full integration with the solar power supply, dry commissioning of the crushing and screening areas was completed in early November and first rock crushing is scheduled for late November. Grinding section dry and wet commissioning will commence in the second half of November and is planned for completion by mid-December. The remaining commissioning schedule is unchanged from the last update and is shown below in Table 1.
Mine decline development continued during October. A total of 311m was developed with the decline reaching 1,284mRL. October represents the highest individual development month since the first cut was fired in the portal in October 2021. The decline location is 266m vertically below the surface and is 29m vertically below the original top of the orebody (1313mRL). Underground drilling has now identified mineralisation as high as 1330mRL which is currently being reviewed for potential extraction. The 1300mRL ore access drive reached first ore in early November (See ASX announcement 14 November 2022).
The 1290mRL horizon is a significant work area for development as underground infrastructure for pumping, ventilation, second means of egress and power are all distributed from this level outwards into the development network. All this infrastructure is currently being established and will result in an increased focus on lateral development and lower decline development in the short term.
Click here for the full ASX Release
This article includes content from Galena Mining, licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.
Abra Mine Reaches Ore
Managing Director, Tony James commented, “Reaching first ore underground delivers another significant step in bringing the Abra project on-line. The first cut in the portal was taken in October 2021, and now 2,949m later and 250m below surface we have reached the orebody. Special acknowledgement needs to be given to Byrnecut and the Abra mining team for achieving this milestone, and everyone involved should be very proud of what they have achieved. It’s also important to acknowledge Pacific Energy and the Abra project team for the faultless commissioning of the power station and completing the full integration of the solar system”.
First ore heading underground has been reached on the 1300mRL access drive. Project to date (PTD) underground development to this point in time was 2,949m and first ore is 250m below the surface. Figure 2 below shows the mine development completed to the end of October 2022. The second underground development Jumbo has commenced at Abra in line with multiple headings being established and underground development is expected to increase accordingly. Underground grade control drilling continues and the 6m diameter return airway shaft drilling has been completed in November through to the surface.
On 20 October, the site changed over to mains power station with the commissioning of the Pacific Energy hybrid 10MW gas/solar/BESS power station. On the 10 November the system was fully integrated with the successful integration of the 6MW solar panels. The mine and general site infrastructure is running on mains power and plant commissioning to date includes the energisation of the crushing/screening sections.
Click here for the full ASX Release
This article includes content from Galena Mining, licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.
Galena Mining Activities Report For Quarter Ended 30 September 2022
GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) reports on its activities for the quarter ended 30 September 2022 (the “Quarter”), primarily focused on construction of its 60%- owned Abra Base Metals Mine (“Abra” or the “Project”) located in the Gascoyne region of Western Australia.
Highlights
- Abra Project 87% complete at end of the Quarter (14% of construction works completed during the Quarter). Project focus remains on underground access to the orebody and completion of the processing plant and remaining surface infrastructure.
- Underground development achieved 771m advance during the Quarter remaining on schedule with the decline reaching 1,300mRL. The decline is 13m below the top of the orebody and 250m below the surface.
- Overall processing plant construction has reached 93% complete. Plant engineering and drafting work is 100% complete and site construction work is 90% complete.
- All key overseas supplied equipment has arrived on site.
- Completed oversubscribed placement to raise A$17.2M.
- US$25M final debt drawdown was completed under the Taurus Debt Facilities.
- Cash balance at Quarter-end A$60.5M.
ABRA BASE METALS MINE (60%-OWNED)
Abra comprises a granted Mining Lease, M52/0776 and surrounding Exploration Licence E52/1455, together with several co-located General Purpose and Miscellaneous Leases. The Project is 100% owned by Abra Mining Pty Limited (“AMPL” the Abra Project joint-venture entity), which in turn is 60% owned by Galena, with the remainder owned by Toho Zinc Co., Ltd. (“Toho”) of Japan.
Abra is fully permitted and under construction. First production of its high-value, high-grade lead- silver concentrate is currently scheduled for the first quarter of 2023 calendar-year.
Click here for the full ASX Release
This article includes content from Galena Mining, licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.
Exploration Update - Visible Gold Intersected at Salanie
Apollo Minerals Limited (ASX: AON) (‘Apollo Minerals’ or ‘the Company’) provides an update on its exploration activities at the Salanie Gold Project (“Salanie”) in Gabon and the Belgrade Copper Project in Serbia. The first round of drilling has now been completed at both projects. Visible gold has been intersected at the A1 Prospect at Salanie, an area that has not seen exploration or modern drilling in 70 years.
HIGHLIGHTS:
- Visible gold identified in drilling at the A1 prospect at 19m depth (Figure 1), associated within a broader 13m zone of quartz veining and shearing from 9.6m downhole:
- Interpreted as extension to system in trench SATR001 (10.3m @ 3.4g/t Au and 1.4m @ 15.7 g/t Au) (Figure 5);
- Assays for this hole are pending.
- At P6, a significant quartz veining/shear system over 20m with associated sulphides has been identified along the trend of historical high-grade underground workings that produced at an average of 16g/t Au.
- The underground workings at P6 represent a priority target that will be further targeted in the 2025 drill season:
- System displays as quartz veining and associated visual estimates of sulphides (trace to 25% pyrite+/-chalcopyrite) intersected in three principal positions in drillhole SLDD002 (61- 65m; 71-75m and 84-87m).
- Drilling completed for the current field season, with discussions advanced with a highly reputable new drilling contractor for drilling in 2025.
- At Salanie, five holes for 328m (two at the P6 prospect and three at the A1 prospect) were completed (two of these did not reach target depth due to drilling performance), with assay results received for 3 holes.
- In the northern areas around the Mikouma and Binda prospects, infill soil sampling has strengthened existing gold targets in these regions with anomalies up to 200ppb Au. Follow up ground reconnaissance will assist in delineating further the drill targets.
- Company to undertake a one (1) for three (3) non-renounceable entitlements offer to raise approximately $3.25 million (before costs).
Figure 1: Examples of visible gold identified in SLDD004 – at 19.04m (associated with chalcopyrite (Cpy) and galena (Gn)).
The Company cautions that visual estimates of sulphides or mineral abundance should never be considered a proxy or substitute for laboratory analysis. Laboratory analysis would be required to determine the widths and grades of sulphides, visible gold, or suspected mineralised intervals reported herein. Visual information also potentially provides no information regarding impurities or deleterious physical properties relevant to valuations. Assays are expected within 3-5 weeks.
Apollo Minerals’ Managing Director, Mr Neil Inwood, commented:
“The first pass drilling is highly encouraging having identified visible gold associated with quartz veining at A1 and a significant shear/quartz vein system at P6. Assays are pending from the key holes at A1. The Salanie system is interpreted to be in the same regional trend of Archean greenstones as Managem’s 1m oz Eteke deposit; highlighting the potential in the broader system.”
“Unfortunately, a combination of late arrival and poor performance from the drilling contractor and the end of the field season has meant that less than a quarter of the planned holes for 2024 were completed and the P6 target was only partially tested by one drill hole. We are in advanced discussions with another drilling company to commence drilling in the new year. Such a partner will enable a significant increase in drilling rate and quality and enable us to further unlock the untested potential at the Salanie Gold Project.”
Click here for the full ASX Release
This article includes content from Apollo Minerals Limited, licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.
Wadi Al Junah VMS-Style Copper-Zinc-Gold-Silver Project in Saudi Arabia
Metal Bank Limited (ASX: MBK) (‘Metal Bank’, ‘MBK’ or the ‘Company’) is pleased to announce further details regarding the Wadi al Junah Copper-Zinc-Gold-Silver Project (‘Wadi al Junah’ or ‘the Project’), which has been awarded to Consolidated Mining Company (CMC) following a highly competitive Saudi government exploration licensing Round 6.
Highlights
- As announced on 6 November, MBK’s Saudi Arabian JV company, has been awarded the Wadi Al Junah Project as part of the Saudi Government’s Exploration Licensing Round 6
- Wadi Al Junah is prospective for volcanogenic massive sulphide (VMS) copper-zinc- gold-silver mineralisation and for shear zone gold-silver, with several untested priority targets
- The Project is 35km east of the Al Hajar Au-Ag-(Cu-Zn) deposit previously mined by Ma’aden and is proximal to the regional centre of Bisha, and close to major access routes, local towns and workforce
- Saudi exploration strategy is supported by a well capitalised in-country JV Company in CMC and significant Saudi government incentives to de-risk and fast-track exploration
- Metal Bank continues to assess new potential project areas in Saudi Arabia prospective for copper, gold and other critical minerals – several tenement applications in progress
CMC is a Saudi Arabian limited liability company owned by MBK (60%) and Central Mining Holding Company (‘CMH’, 40%). CMH is a member of the Al Qahtani Holdings group, and was the JV partner of Citadel Resources which, under the leadership of Inés Scotland as Managing Director, was responsible for the exploration and development of the Jabal Sayid copper project in Saudi Arabia (prior to its acquisition by Equinox). CMC will be responsible for managing and implementing the work program for the Wadi Al Junah project utilising the technical expertise of MBK, as the exploration JV partner, in combination with the KSA expertise of the Al Qahtani Group. CMC has a current capitalisation of SAR5m (~AUD2.1m).
Wadi al Junah with an area of 427km2 was the largest of the projects offered in Round 6 and is proximal to the major regional centre and airport of Bisha, with major access routes passing through the license area and local towns and workforce close by. The Project is located in the prospective Wadi Shwas Gold Belt, a region under-explored for shear zone gold, VMS copper-zinc-gold-silver and intrusion-related gold and base metal deposits. It is supported by several mineral occurrences with encouraging geological observations, and gold, silver and copper grades in historic regional- scale reconnaissance mapping, which have not been followed up by modern work.
MBK’s technical team has prepared a comprehensive two-year work program, with an initial focus on following up the previous limited and surface based exploration for mineral occurrences of copper, gold and silver. MBK is aiming to be drill-ready within the next six months.
Commenting on this acquisition, Metal Bank’s Chair, Inés Scotland said:
“The successful tender for the Wadi al Junah project in Saudi Arabia by our JV company CMC via a tightly contested and highly competitive exploration round speaks to our commitment, capability and technical expertise in achieving our strategy of acquiring prospective tenure within Saudi Arabia, which we believe remains underexplored and highly prospective.
Wadi al Junah represents our first project back in Saudi Arabia, a region in which MBK’s management team has extensive experience and a proven track record of success, having previously developed the Jabal Sayid project. We are well-supported by both our JV partner and the significant government incentives provided by the Kingdom of Saudi Arabia in search for the next Jabal Sayid. The Arabian Shield has so much underexplored potential, and we are ready to get our initial phase of exploration underway as quickly as possible.”
Wadi al Junah Copper-Zinc-Gold-Silver Summary
The Wadi al Junah project area covers an area of 427sq km within the Asir province of the Arabian Shield, southwest Saudi Arabia (Figures 1 and 2). It is approximately 375km south-east of Jeddah, 150km east-northeast of the port of Al Quinfidhad and around 35km east of the Al Hajar Au-Ag-(Cu- Zn) deposit previously mined by Ma’aden. It is proximal to the major regional centre and airport of Bisha, with major access routes passing through the license area and local towns and workforce close by. The majority of the project area is accessed by local tracks and wadi valleys in moderate topography.
Figure 1: MBK MENA projects showing Wadi al Junah (Saudi Arabia) and Malaqa, Area 47 and Area 65 (Jordan).
Figure 2: Wadi al Junah location map within the Arabian Shield showing major geological provinces and major Au and Cu mines (modified from KSA Ministry of Industry and Minerals publication after Nehlig et al, 2002)
Geology
Wadi al Junah is situated within the central Asir terrane of the Archaean Arabian Shield (Figure 2) within the ~80km long north-trending Wadi Shwas Gold Belt. The Shwas VMS belt on the western margin of the Wadi Shwas Gold Belt is host to the Al Hajar Au-Ag-Cu-Zn deposit, and numerous other VMS base metal and Au mineral occurrences of Proterozoic age are present in the region (Figure 3).
Three known mineral occurrences occur in the tenement area – Haniyat (Ag-Cu-+/-Au+/-Zn), Wadi al Maytha (Ag-Cu) and Wadi Umm Rahka (Ag-Cu). Very limited rock chip sampling as part of regional scale mapping work in the 1960’s and 1970’s includes results up to 1.53% Cu, 0.44g/t Au and 160g/t Ag from these prospects, which were never followed up1.
Click here for the full ASX Release
This article includes content from Metal Bank Limited, licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.
Octava to Commence Drilling at Yallalong High-Grade Antimony Project
Octava Minerals Limited (ASX:OCT) (“Octava” or the “Company”), a Western Australia focused explorer of the new energy metals antimony, REE’s, Lithium and gold, is pleased to report that the drill rig is relocating to site at the Yallalong antimony project and will commence drilling this weekend. Drilling will focus on two antimony targets, Discovery and Central, with No.4 and North targets to be drilled in the new year.
Highlights
- Drill rig relocating to site with drilling to commence this weekend.
- The 3000m reverse circulation (RC) drill program is targeting further high-grade antimony at the Discovery prospect.
- Historic drilling at Discovery recorded high-grade antimony intercepts over a strike length of ~300m and remains open. Results include:
- YRC16: 7m @ 3.27% Sb from 12m including 1m @ 11.5% from 18m
- YRC06: 3m @ 6.83% Sb from 21m including 1m @ 13.6% Sb from 22m
- After drilling at Discovery, the drill rig will relocate to the Central antimony target, 2km north along strike. There has been no previous drilling at Central.
- A detailed geophysical survey over the antimony corridor at Yallalong is now complete, with the data being processed. This is expected to generate further targets within the antimony corridor.
Octava’s Managing Director Bevan Wakelam stated, "It’s great to have the rig heading to site and earlier than we had planned. The drilling will start on Discovery, then move to the Central target and should take about 2 weeks to complete. High-grade antimony has already been intersected at Discovery over a significant strike length and this drilling will further test the size. We will also twin some of the previously drilled holes."
Figure 1. Planned drill hole locations at the Discovery antimony target - Yallalong Antimony Project.
The antimony (Sb) mineralisation identified at Yallalong appears within a 10km north-south striking mineralised corridor that is interpreted to be related to a structural belt between the regional scale Darling and Woodrarung faults. Previous exploration identified four principal antimony targets where antimony mineralisation was exposed at surface. Only the Discovery Prospect has any drilling and remains open. Antimony ingot prices at that time were ~$8000/tonne compared to over $30,000/tonne now1.
Figure 2. Antimony targets at Yallalong antimony project with underlying geology.
Drilling at Discovery target recorded some of the highest-grade antimony drill intersections in Australia, at shallow depth, over a strike of ~300m including:
- YRC16: 7m @ 3.27% Sb from 12m including 1m @ 11.5% from 18m
- YRC06: 3m @ 6.83% Sb from 21m including 1m @ 13.6% Sb from 22m
- YRC27: 6m @ 1.35% Sb from 13m
After drilling at the Discovery target is complete, the rig will then move to the Central target, which is located 2 kilometres north along strike. There has been no previous drilling at the Central target.
Click here for the full ASX Release
This article includes content from Octava Minerals Limited, licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.
Targeted Exploration Focus Delivers an Additional 471koz or 99% Increase in Ounces, and a Higher Grade for Ricciardo
Warriedar Resources Limited (ASX: WA8) (Warriedar or the Company) is pleased to report on an updated MRE for its flagship Ricciardo Gold Deposit, part of the broader Golden Range Project located in the Murchison region of Western Australia.
HIGHLIGHTS:
- Updated Mineral Resource Estimate (MRE) for the Ricciardo Deposit (part of the broader Golden Range Project) of 16.44 Mt @ 1.8 g/t Au for 947.5 koz gold.
- Represents a 99% increase in Ricciardo MRE contained gold ounces.
- Proven high-returning exploration with the increased Ricciardo MRE ounces delivered at an attractive all-in discovery cost of only approx. A$16/oz.
- High-quality resource additions given drilling focus on high-grade growth ounces with strong commercial potential.
- The updated Ricciardo MRE comprises:
- 467.5 koz @ 1.6 g/t Au open-pit gold Resource (75% M&I) (optimised pit shell constrained at A$3,300/oz)
- 480.0 koz @ 2.0 g/t Au underground gold Resource
- Critically, the Ricciardo system remains wide open at depth and along strike.
- Total Golden Range Project Mineral Resources now stand at over 1.28 Moz gold, a 58% increase from the previous level.
- This initial outcome validates the excellent potential for further growth within the broader 25km ‘Golden Corridor’ via the ongoing, simple strategy of targeting fresh rock extensions under shallow existing pits.
- RC drilling at the southern end of the ‘Golden Corridor’ targeting high-grade Resource growth is progressing well; 9 holes completed for 1,472 metres to date, assays pending.
Warriedar Managing Director and CEO, Amanda Buckingham, commented:
“This is the result we have been working towards all year. With less than 15,000m of targeted, efficient drilling we have added over 470 koz to the Ricciardo deposit, doubling the Resource.
We are excited by both the outcome itself, and the outlook that it delivers us for the wider corridor of gold deposits. The simple strategy of drilling below shallow open pits to find mineable ounces worked exceptionally well for our producing neighbours. The validity of this strategy is now beyond doubt, for us.
Not only is the Ricciardo system still wide open down-plunge, but the entire 25km long ‘Golden Corridor’ offers similar potential upside from such a relatively simple drilling focus.
In the middle of the infrastructure-rich southern Murchison, and located on existing Mining Leases, the opportunity in front of us is utterly irresistible.”
The Ricciardo Deposit
The Ricciardo Gold Deposit is located on existing mining leases 100% owned by WA8, in the Murchison Region, approximately 300 km east of Geraldton, and 420 km by road north-northeast of Perth. Sitting approximately 8km South of the Golden Range Mill on M59/421, and M59/458, within the Golden Range group of historic open pit mines and deposits.
Discovered in the 1990’s, open pit mining of the oxide resources commenced in 2001, and the plant entered Care & Maintenance twice (between July 2004 and 2009, and May 2010 to mid- 2013). Production was over 300 Koz before finally going into ongoing Care and Maintenance in August 2019.
The Ricciardo deposit is located 90km north of Capricorn Metals’ Mt Gibson Gold Project, 8kms south of the Company’s plant, 26km from the neighbouring Golden Grove processing facility and 40 km northeast of Vault Minerals’ high grade Rothsay gold mine (Figure 1).
Figure 1: The location of the Ricciardo gold deposit within the Golden Range Project; within the broader Southern Murchison region.
The Ricciardo gold system spans a strike length of approximately 2.3km, with very limited drilling having been undertaken below 100m depth prior to Warriedar drilling. Historical mining operations at Ricciardo were primarily focused on oxide material, with the transition and primary sulphides mineralisation not systematically explored.
Warriedar’s drilling of Ricciardo during CY2024 achieved excellent results, demonstrating high- grade extensions to the resource. The results demonstrated that the previously quantified resource is part of a much larger system.
Warriedar engaged independent mining consultants, Measured Group to update the Ricciardo MRE, previously reported 476Koz gold.1
The Ricciardo Gold Deposit consists of six semi-continuous historical open pit mines along the 2.3 km arcuate stretch of the Mougooderra Shear Zone, running north to south. These mines are named (from north to south) Silverstone North, Ardmore, Copse, Silverstone, Silverstone South, and Eastern Creek (Figure 2).
Figure 2: Drilling carried out by the Company during 2023 & 2024, which was used to update the MRE.
Click here for the full ASX Release
This article includes content from Warriedar Resources Limited, licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.
Octava Selects Drilling Contractor for its Yallalong Antimony Project in Western Australia
Australian mineral exploration company Octava Minerals (ASX:OCT) has selected the drilling contractor for the exploration work commencing at its 100-percent-owned Yallalong antimony project, according to an article by Business News - Australia. The deal will kick off the company’s 3,000-metre program focused on the Discovery target.
“Antimony is on an absolute price tear, up almost 300 percent in the past four years and more recently exacerbated by a Chinese export ban. Given its prospects, Octava would seem to be perfectly positioned to take advantage,” the article said.
The exploration campaign will target the Discovery and Central zones and will begin in the next two weeks. The Central prospect has been drilled before with rock chips reported to contain up to 60 percent antinomy.
Western Australia Allocates AU$14 Million to Improving Environmental Approval Process
Western Australia's governmentsaid on Monday (November 11) that it is allotting AU$14 million to support the employment of additional staff at the Environmental Protection Authority (EPA) and the Office of the Appeals.
The boost comes in response to the Vogel-McFerran Review commissioned by the government in 2023. It recommended various steps to speed up the state's environmental approval system and secure major projects.
According to the government, employing additional staff will help address existing backlogs and provide faster decisions “without impacting the high standard for protecting WA's unique environment.”
"We've overhauled WA's environmental approvals system to fast-track approvals while maintaining the highest environmental standards in the world,” said Premier Roger Cook. "This resourcing boost will help our approvals agencies to clear the backlog of approvals and deliver faster outcomes for project proponents across the state."
The investment also follows recently legislated amendments to the Environmental Protection Act, including the allowance of government regulators to process and issue parallel approvals while EPA assessments are underway.
Aside from that, it grants Western Australia's environment minister the power to supply the EPA with a statement of expectation, and allows an overall membership expansion of the EPA’s board.
The government said the investment means investors will receive greater certainty and quicker decisions.
As part of its commitment to improving the resource industry, 22 out of 34 of the Vogel-McFerran Review’s recommendations have recently been fully or partly actioned by the Western Australian government.
Recently, 50 companies received grants worth AU$7.28 million under Round 30 of Western Australia's Exploration Initiative Scheme. The funds are for the drilling of projects between December 2024 and November 2025.
“We're delivering on our clean energy plan, securing major, job-creating projects to position WA as a global renewable energy powerhouse," Cook added in this week's press release.
Don’t forget to follow us @INN_Australia for real-time news updates!
Securities Disclosure: I, Gabrielle de la Cruz, hold no direct investment interest in any company mentioned in this article.
Latest News
Galena Mining Investor Kit
- Corporate info
- Insights
- Growth strategies
- Upcoming projects
GET YOUR FREE INVESTOR KIT
Latest Press Releases
Related News
TOP STOCKS
Investing News Network websites or approved third-party tools use cookies. Please refer to the cookie policy for collected data, privacy and GDPR compliance. By continuing to browse the site, you agree to our use of cookies.