Galena Mining

Abra Construction At 97% Complete – First Ore Stockpiled For January Processing

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 97% complete as of 30 November 2022. Processing plant commissioning is progressing quickly with practical completion now expected in December 2022. Ore currently being mined from underground is being stockpiled in readiness for processing to begin in January 2023. Concentrate production will commence January 2023.


Managing Director, Tony James commented, “Record underground development in November with delivery of the first 9,000t of ore to the ROM pad along with successful plant commissioning to date puts Abra on the verge of a quick transition into production. Recruitment and other operational readiness activities are well advanced in preparation for January production”.

Figure 1 – First material being tipped into the crusher during commissioning (Photo 26 November).

Figure 2 – Crushing and screening plant commissioning (Photo 26 November).

The following link will show a short video of the Abra crusher commissioning. https://youtube.com/shorts/iSG58MiW_3o

Update on Abra Project progress

Overall progress continues as planned, with first concentrate production expected in Q1 CY2023, following ore commissioning in January 2023. Practical completion of the processing plant is now expected ahead of schedule in December 2022. The processing plant engineering, procurement and construction has reached 99% complete. Piping and electrical works have made significant progress and at the end of November were 96% and 92% complete, respectively. Mechanical items installation is almost complete at 99%.

In November, the first material was crushed and screened as part of the staged commissioning process. The crushing plant ran at design capacity and all commissioning milestones were successfully achieved. Dry commissioning also progressed in most areas of the plant including water and air services, tailings and concentrate thickening, grinding and reagents. Dry commissioning of the remaining areas will be completed in December. Water commissioning commenced in the tailings and concentrate thickening areas of the plant and the remaining areas are expected to be wet commissioned by the end of December. The remaining commissioning schedule is unchanged from the last update and is shown below in Table 1.


Click here for the full ASX Release

This article includes content from Galena Mining, licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.

G1A:AU
Galena Mining

Galena Mining Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

The Conversation (0)
Galena Mining (ASX:G1A)

Galena Mining


Keep reading...Show less
Galena Mining

Abra Construction At 92% Complete – Reaches First Ore Underground

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 92% complete as of 31 October 2022. Underground mine has reached the first ore (see ASX announcement 14 November 2022) and plant commissioning continues in several key areas with the project focussed on achieving first concentrate production in Q1 2023.
Keep reading...Show less
Galena Mining

Abra Mine Reaches Ore

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the underground development at its Abra Base Metals Mine (“Abra” or the “Project”) has reached the Abra orebody. Commissioning has commenced in several key areas of the processing facility and the Power Station (Pacific Energy) completed full integration of the hybrid gas/solar/battery energy storage system (BESS) power station on 10 November. The project remains on track for first concentrate production in Q1 2023.
Keep reading...Show less
Galena Mining

Galena Mining Activities Report For Quarter Ended 30 September 2022

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) reports on its activities for the quarter ended 30 September 2022 (the “Quarter”), primarily focused on construction of its 60%- owned Abra Base Metals Mine (“Abra” or the “Project”) located in the Gascoyne region of Western Australia.

Keep reading...Show less
Augustus Minerals

Airborne EM over Multiple Targets on Ti-Tree Project

Augustus Minerals (ASX: AUG; “Augustus” or the “Company”) is pleased to announce that an airborne Versatile Time Domain Electromagnetic (VTEM) Max survey will be undertaken at three areas within the 3,600km2 Ti-Tree Project in the Gascoyne Region. The survey is scheduled for August.

Keep reading...Show less
Mount Burgess Mining NL

Kihabe-Nxuu Polymetallic Project Silver/Gallium Potential

In response to recent enquiries, Mount Burgess Mining Ltd (MTB:ASX, the “Company”) is pleased to update the silver potential of the Kihabe-Nxuu Project (“Project”) in Botswana. With the recent increase in silver prices and multiple forecasts predicting a structural deficit over the coming years, the importance of the silver content of the Project has increased substantially.

Keep reading...Show less
IMARC

Registration Opens for the Inaugural Mining, Metals and the Circular Economy Conference

Early bird delegate passes are now on sale for the inaugural Mining, Metals and the Circular Economy conference, scheduled to take place at the ICC Sydney on 29 & 30 October 2024.

The launch of this event is timely, as circularity in the mining and metals industry is important for reaching net-zero goals and global decarbonisation, while also addressing the rising demand for minerals required for future technologies and other vital materials.

Organised by Beacon Events, the Mining, Metals and the Circular Economy conference will be co-located with the International Mining and Resources Conference (IMARC), providing attendees with unprecedented access to industry experts and thought leaders in the mining sector, fostering a dynamic exchange of innovative ideas and best practices. What sets this conference apart is that it is the world’s first and only event to explore the global context of process and product circularity throughout the mining industry’s value chain.

Keep reading...Show less
Aldoro Resources

Latest Kameelburg Assays Up To 10.38% Nb2o5 and 9.89% TREO

Aldoro Resources Ltd (“Aldoro”, “The Company”) (ASX: ARN) is pleased to provide an update on the large-scale geological mapping campaign at the Kameelburg Carbonatite Project, targeting priority areas across the southern and eastern margins of the large carbonatite plug.

Keep reading...Show less
Firetail Resources

Firetail Resources

Keep reading...Show less
Aura Energy

Aura Increases Tiris’ Mineral Resources by 55% to 91.3 Mlbs U3O8

Resource growth adds confidence in future expansion and scale opportunities

Aura Energy Limited (ASX: AEE, AIM: AURA) (“Aura” or “the Company”) is pleased to provide an update on the Mineral Resource Estimate (“MRE”) for the Tiris Uranium Project (“Tiris” or the “Project”) in Mauritania.

Keep reading...Show less
Galena Mining

Galena Mining Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

Latest Press Releases

Related News

×