South Star Battery Metals Announces Approval of the Environmental Permits for the Santa Cruz Graphite Mine Phases 2 & 3 in Bahia, Brazil

South Star Battery Metals Announces Approval of the Environmental Permits for the Santa Cruz Graphite Mine Phases 2 & 3 in Bahia, Brazil

THIS NEWS RELEASE IS NOT FOR DISTRIBUTION TO U.S. NEWSWIRE SERVICES FOR DISSEMINATION IN THE UNITED STATES

South Star Battery Metals Corp. ("South Star" or the "Company") (TSXV:STS)(OTCQB:STSBF), is pleased to announce that the environmental permits for Santa Cruz Graphite Mine Phases 2 and 3 have been approved for up to 50,000 tonne per annum ("tpa") of concentrate for eight mining claims. Following approval of the environmental permits, five of the principal claims were approved by the regional office of the National Mining Agency ("ANM") and forwarded to the Ministry of Mines and Energy ("MME") in Brasilia for final review of the life-of-mine permit applications. The Phases 2 and 3 environmental permits were approved with conditions generally in line with the Phase 1 permit and are consistent with the current environmental and community engagement programs already underway

South Star President, Richard Pearce, commented, "This important approval is another big achievement for Santa Cruz and is a key step forward in derisking our future operations and scaling our production at a critical time for battery metals. Once the full mining concessions incorporating Phases 2 and 3 are approved by the MME, we will be able to increase our Phase 1 production to name plate capacity of 13,000 tpa from 5,000 tpa and deliver more high-quality Brazilian flake graphite to our clients. Our goal is to have all permits/licenses in hand shortly for 50,000 tpa of production and advancing the Santa Cruz feasibility study so we are ready to make an investment decision shortly after delivery of the report in December 2024. Up to US$18M is available through our agreement with Sprott Streaming for Phase 2 production expansion upon delivery of the FS. I would like to sincerely thank our team, the Municipality of Itabela and all stakeholders for their continuing support of Santa Cruz as we responsibly scale our operations in one of the most proven graphite districts in the world. Santa Cruz will be the first new graphite production in the Americas since 1996, and we look forward to scaling operations soon as our clients request additional production from us."

Upcoming catalysts in 2024 include advancing the Santa Cruz NI 43-101 Feasibility Study ("FS"), which will build on the Prefeasibility Study previously released in 2021. The FS will advance Santa Cruz operations with a phased, modular design plant facility and will include the following milestones:

  • Approximately 4,000m of diamond and reverse circulation drilling
  • Updated Resource/Reserve estimate
  • Updated mine plans
  • Flow sheet optimizations
  • Natural flake graphite concentrate production expansion
    • Phase 1: 5,000 scaling to 13,000 tpa
    • Phase 2: +25,000 tpa module
    • Phase 3: +25,000 tpa module
  • Infrastructure and access
  • Project CAPEX/OPEX
  • Project Economics

About South Star Battery Metals Corp
South Star Battery Metals Corp. is a Canadian battery metals project developer focused on the selective acquisition and development of near-term production projects in the Americas. South Star's Santa Cruz Graphite Project, located in Southern Bahia, Brazil is the first of a series of industrial and battery metals projects that will be put into production. Brazil is the second-largest graphite-producing region in the world with more than 80 years of continuous mining. Santa Cruz has at-surface mineralization in friable materials, and successful large-scale pilot-plant testing (> 30t) has been completed. The results of the testing show that approximately 65% of Cg concentrate is +80 mesh with good recoveries and 95%-99% Cg. With excellent infrastructure and logistics, South Star is fully funded for Phase 1, and the construction and commissioning are underway. Santa Cruz will be the first new graphite production in the Americas since 1996 with Phase 1 commercial production projected in Q1 2024. Phase 2 production (25,000 tpa) is partially funded and planned for 2026, while Phase 3 (50,000 tpa) is scheduled for 2028.

South Star's second project in the development pipeline is strategically located in Alabama in the center of a developing electric vehicle, aerospace, and defense hub in the southeastern United States. The BamaStar Project is a historic mine active during World Wars I & II. A NI43-101 technical report with the maiden resource estimate has been filed on SEDAR. Trenching, phase 1 drilling, sampling, analysis, and preliminary metallurgical testing have been completed. The testing indicates a traditional crush/grind/flotation concentration circuit that achieved grades of approximately 94-97% Cg with approximately 86% recoveries. South Star is executing on its plan to create a multi-asset, diversified battery metals company with near-term operations in strategic jurisdictions. South Star trades on the TSX Venture Exchange under the symbol STS, and on the OTCQB under the symbol STSBF.

South Star is committed to a corporate culture, project execution plan and safe operations that embrace the highest standards of ESG principles based on transparency, stakeholder engagement, ongoing education, and stewardship. To learn more, please visit the Company website at http://www.southstarbatterymetals.com.

This news release has been reviewed and approved by Richard Pearce, P.E., a "Qualified Person" under National Instrument 43-101 and President and CEO of South Star Battery Metals Corp.

On behalf of the Board,

MR. RICHARD PEARCE
Chief Executive Officer

For additional information, please contact:
South Star Investor Relations
Email: invest@southstarbatterymetals.com
+1 (604) 706-0212

Twitter: https://twitter.com/southstarbm

Facebook: https://www.facebook.com/southstarbatterymetals

LinkedIn: https://www.linkedin.com/company/southstarbatterymetals/

YouTube: South Star Battery Metals - YouTube

CAUTIONARY STATEMENT
Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this press release.

Forward-Looking Information
This press release contains "forward-looking statements" within the meaning of applicable securities legislation. Forward-looking statements relate to information that is based on assumptions of management, forecasts of future results, and estimates of amounts not yet determinable. Any statements that express predictions, expectations, beliefs, plans, projections, objectives, assumptions or future events or performance are not statements of historical fact and may be "forward-looking statements". Forward-looking statements in this press release include, but are not limited to, statements relating to the successful closing of the Private Placement and anticipated timing thereof and the intended use of proceeds and statements regarding moving Santa Cruz into production and scaling operations as well as advancing the Alabama project; and the Company's plans and expectations.

Forward-looking statements are subject to a variety of risks and uncertainties which could cause actual events or results to differ from those reflected in the forward-looking statements, including, without limitation: risks related to failure to obtain adequate financing on a timely basis and on acceptable terms; risks related to the outcome of legal proceedings; political and regulatory risks associated with mining and exploration; risks related to the maintenance of stock exchange listings; risks related to environmental regulation and liability; the potential for delays in exploration or development activities or the completion of feasibility studies; the uncertainty of profitability; risks and uncertainties relating to the interpretation of drill results, the geology, grade and continuity of mineral deposits; risks related to the inherent uncertainty of production and cost estimates and the potential for unexpected costs and expenses; results of prefeasibility and feasibility studies, and the possibility that future exploration, development or mining results will not be consistent with the Company's expectations; risks related to commodity price fluctuations; and other risks and uncertainties related to the Company's prospects, properties and business detailed elsewhere in the Company's disclosure record. Should one or more of these risks and uncertainties materialize, or should underlying assumptions prove incorrect, actual results may vary materially from those described in forward-looking statements. Investors are cautioned against attributing undue certainty to forward-looking statements. These forward-looking statements are made as of the date hereof and the Company does not assume any obligation to update or revise them to reflect new events or circumstances. Actual events or results could differ materially from the Company's expectations or projections.

This news release does not constitute an offer to sell or a solicitation of an offer to buy any of the securities in the United States. The securities have not been and will not be registered under the United States Securities Act of 1933, as amended (the "U.S. Securities Act") or any state securities laws and may not be offered or sold within the United States or to U.S. Persons unless registered under the U.S. Securities Act and applicable state securities laws or an exemption from such registration is available.

SOURCE: South Star Battery Metals Corp.



View the original press release on accesswire.com

News Provided by ACCESSWIRE via QuoteMedia

STS:CA
The Conversation (0)
South Star Announces Additional Sales of Natural Flake Graphite Concentrate to U.S. Customer

South Star Announces Additional Sales of Natural Flake Graphite Concentrate to U.S. Customer

Advancing the First New Natural-Flake Graphite Mine in the Americas this Century

 

South Star Battery Metals CORP. ("South Star" or the "Company") (TSXV:STS)(OTCQB:STSBF) is pleased to announce that, further to the Company's May 6, 2024 announcement ("South Star Battery Metals Announces the First Sale of Natural Flake Graphite Concentrate from its Santa Cruz Graphite Mine in Brazil") and its August 1, 2024 announcement ("South Star Announces Successful Product Qualification and 100-Tonne Sale of Natural Flake Graphite Concentrate to U.S. Customer"), South Star has executed another binding commercial sales agreement (the "Agreement") for an initial 40 tonnes (more than 88,000 pounds) of natural-flake graphite concentrate from the Company's flagship Santa Cruz Graphite Mine("Santa Cruz"), located in northeastern Brazil's Bahia state. This most recent sales Agreement was formally executed with a prominent American industrial graphite customer (the "U.S. Client

News Provided by ACCESSWIRE via QuoteMedia

Keep reading...Show less
South Star Announces Successful Product Qualification and 100-Tonne Sale of Natural Flake Graphite Concentrate to U.S. Customer

South Star Announces Successful Product Qualification and 100-Tonne Sale of Natural Flake Graphite Concentrate to U.S. Customer

South Star advancing the first new natural-flake graphite mine in the Americas this century.

 

South Star Battery Metals CORP. ("South Star" or the "Company") (TSXV:STS)(OTCQB:STSBF) is pleased to announce that further to the Company's May 6, 2024 announcement ("South Star Battery Metals Announces the First Sale of Natural Flake Graphite Concentrate from its Santa Cruz Graphite Mine in Brazil"), South Star has executed another binding commercial sales agreement (the "Agreement") for the initial purchase of 100 tonnes (more than 220,000 pounds) of graphite concentrate from the Company's flagship Santa Cruz Graphite Mine ("Santa Cruz"), located in northeastern Brazil's Bahia state

News Provided by ACCESSWIRE via QuoteMedia

Keep reading...Show less
South Star Announces Substantial Completion and Commissioning of the Santa Cruz Phase 1 Graphite Mine in Brazil

South Star Announces Substantial Completion and Commissioning of the Santa Cruz Phase 1 Graphite Mine in Brazil

Highlights

  • Mine prestrip, preliminary dump foundations and ramps are complete, and approximately 50,000 tonnes of ore is being placed on the ore pad by end of August for commissioning and initial operations.

News Provided by ACCESSWIRE via QuoteMedia

Keep reading...Show less
South Star Battery Metals Announces Successful Metallurgical Results for its BamaStar Graphite Project in Alabama, USA

South Star Battery Metals Announces Successful Metallurgical Results for its BamaStar Graphite Project in Alabama, USA

Highlights:

  • Metallurgical work completed on representative oxide, transition and fresh rock composite samples ranging in grade from 2.36% Cg for fresh rock to 3.04% Cg for oxide samples.
  • Bond abrasion and work index testing show low to medium abrasion and low energy requirements.
  • Open circuit flotation tests resulted in excellent concentrates grade ranging from 94.4% Cg for fresh rock materials to 99.5% Cg for oxide samples with a simple flowsheet that maximizes graphite recovery and minimizes flake degradation.
  • The open circuit graphite recoveries were high, ranging between 87.5% and 91.5%.
  • Given the superior response of the oxide and transitional material, the next phase of work will investigate mining pit design to maximize processing of oxide and transitional material early in the project life and postpone mining of the fresh ore in order to decrease initial CAPEX, lower OPEX and target improved project economics.
  • The NI43-101 Preliminary Economic Assessment results for BamaStar are scheduled for release in August 2024.

South Star Battery Metals Corp. ("South Star" or the "Company") (TSXV:STS)(OTCQB:STSBF) is pleased to announce successful results from the ongoing metallurgical process development program for the Bama Star graphite project in Alabama, USA

News Provided by ACCESSWIRE via QuoteMedia

Keep reading...Show less
South Star Battery Metals Announces Land Purchase, Construction Update, and the Approval of the Definitive Mining Licenses For Phases 1, 2 & 3 for its Santa Cruz Graphite Mine in Brazil

South Star Battery Metals Announces Land Purchase, Construction Update, and the Approval of the Definitive Mining Licenses For Phases 1, 2 & 3 for its Santa Cruz Graphite Mine in Brazil

Santa Cruz Graphite Mine Highlights:

  • Final payment of land purchase for Phase 1 Plant and Operations.
  • Approval of the Definitive Mining Licenses For Phases 1, 2 & 3. All mining and environmental licenses/permits are approved and in-hand for the future phased, modular expansion of Santa Cruz graphite production up to 50,000 tonnes/year.
  • Phase 1 construction is on schedule for substantial completion by the end of June 2024 followed by a 6-week plant commissioning and ramp-up period. Commercial sales are planned to start in September 2024. Name plate production capacity is expected to be reached in Q4 2024.

South Star Battery Metals Corp. ("South Star" or the "Company") (TSXV:STS)(OTCQB:STSBF) is pleased to announce the final payment of the previously announced (Aug. 02, 2022) land purchase required for construction of the Phase 1 mine and plant facilities. The farm totals approximately 325 hectares and is where all the plant facilities, mine and infrastructure installations are required for the first three years of operations at its Santa Cruz Graphite Project in Bahia, Brazil

News Provided by ACCESSWIRE via QuoteMedia

Keep reading...Show less
Altech Batteries Ltd  Cerenergy Battery Project Funding Progressing Well

Altech Batteries Ltd Cerenergy Battery Project Funding Progressing Well

Perth, Australia (ABN Newswire) - Altech Batteries Limited (ASX:ATC,OTC:ALTHF) (FRA:A3Y) (OTCMKTS:ALTHF) is pleased to announce an update on funding of the CERENERGY(R) sodium-chloride solid-state battery project in Saxony, Germany.

DEBT PROCESS

As previously mentioned, Altech has engaged ten commercial banks and two venture debt funds in the first round of financing discussions, receiving largely positive initial feedback. Based on this feedback, the Company has selected a preferred financial institution- a European bank with a proven track record in providing debt funding for technology-driven projects, particularly those within the innovation sector.

Although the mandate has not yet been formally executed, Altech intends to make an official announcement once this step is complete.

Meanwhile, the bank's commercial and technical teams have been diligently conducting a comprehensive review of the Cerenergy projects and its technology. The technical due diligence process is critical for ensuring that the project meets the bank's financing and risk criteria. As part of this process the onsite Altech experts are in detailed discussions with the bank's representative. The banks have visited Dresden and the Fraunhofer testing facilities and visit Hermsdorf, Germany where the prototype production is located in the coming weeks, which will be a key step in concluding the technical evaluation.

In parallel with these efforts, Altech is progressing discussions for securing a federal government guarantee, which would further strengthen its ability to secure the necessary debt funding for the project. Officials from the Ministry of Finance have already been briefed on the initiative, and the due diligence process for the application is actively underway. This federal guarantee will serve as an underwriter and therewith derisk any debt funding for the project substantially.

EQUITY FUNDING

In parallel with ongoing debt financing efforts, the Group has engaged several equity advisers to assist in securing the equity component of the project's funding package. As part of this strategy, Altech plans to divest a minority interest in the project to one or two strategic investors. This partial divestment is intended to attract investors who can contribute not only capital, but also strategic value, aligning with the CERENERGY(R) project's long-term goals of growth and sustainability.

The Group on one hand is specifically targeting large utility companies, data centre operators, investment funds, and corporations that are deeply committed to the green energy transition and on the other hand industrial partners with access and know-how and resources relevant to Cerenergy battery production, implementation or market access. These potential partners are seen as ideal due to their strong alignment with the project's sustainable energy focus and their ability to provide significant financial support. Progress in equity discussions has been promising, with several Non-Disclosure Agreements (NDAs) signed, enabling deeper engagement with prospective investors. Additionally, draft term sheets have been circulated to interested parties, outlining the key terms and conditions for investment. These documents provide a foundation for negotiations and facilitate more detailed discussions around the equity stake and partnership structure.

The decision to divest part of the project is strategically aimed at easing the Company's financial burden while bringing in experienced partners who can contribute to the project's success. By securing both equity and debt financing, Altech aims to finalize the full funding package, ensuring the timely construction and commissioning of the CERENERGY(R) battery plant. Moving forward, the focus will be on advancing these discussions and converting interest into formal commitments, which are critical for the project's progression.

GRANT APPLICATIONS

Altech has been actively applying for various grants offered by the State of Saxony, Federal Government of Germany, and the European Union. The State of Saxony and Brandenburg, along with the European Union, offer substantial support for renewable energy projects, including grants aimed at converting lignite coal to renewable energy sources. These grants are part of broader efforts to transition regions dependent on fossil fuels toward sustainable energy solutions. Altech's site, located in these areas, stands to benefit from various funding programs designed to support clean energy projects, including EU grants for energy transformation and innovation. Altech has applied for several of these grants to advance its CERENERGY(R) project, securing essential financial backing for technology development, high-tech industries, expert employment and infrastructure upgrades.

OFFTAKE ARRANGEMENTS

Altech has secured three key Offtake Letters of Intent (LOIs) for 100% of its CERENERGY(R) production.

1. Zweckverband Industriepark Schwarze Pumpe (ZISP): An agreement was signed on 13 September 2024 for ZISP to purchase 30 MWh of energy storage capacity annually, consisting of 1MWh GridPacks, for the first five years of production. The purchase is contingent on performance tests and battery specifications meeting customer requirements.

2. Referenzkraftwerk Lausitz GmbH (RefLau): A second LOI was executed with RefLau, a joint venture between Enertrag SE and Energiequelle GmbH. RefLau will buy 30 MWh of CERENERGY(R) storage n the first year, increasing to 32 MWh annually for the next four years. Additionally, Altech will purchase green electricity for its planned production plant.

3. Axsol GmbH: A third LOI was signed with Axsol, a leading renewable energy solutions provider. Axsol will exclusively distribute CERENERGY(R) batteries to the Western defense industry, facilitating early market entry and sales. These agreements are crucial for financing and advancing the CERENERGY(R) project.

 

About Altech Batteries Ltd:  

Altech Batteries Limited (ASX:ATC,OTC:ALTHF) (FRA:A3Y) is a specialty battery technology company that has a joint venture agreement with world leading German battery institute Fraunhofer IKTS ("Fraunhofer") to commercialise the revolutionary CERENERGY(R) Sodium Alumina Solid State (SAS) Battery. CERENERGY(R) batteries are the game-changing alternative to lithium-ion batteries. CERENERGY(R) batteries are fire and explosion-proof; have a life span of more than 15 years and operate in extreme cold and desert climates. The battery technology uses table salt and is lithium-free; cobalt-free; graphite-free; and copper-free, eliminating exposure to critical metal price rises and supply chain concerns.

The joint venture is commercialising its CERENERGY(R) battery, with plans to construct a 100MWh production facility on Altech's land in Saxony, Germany. The facility intends to produce CERENERGY(R) battery modules to provide grid storage solutions to the market.

 

News Provided by ABN Newswire via QuoteMedia

Keep reading...Show less
Lithium Universe Ltd  Completes PV Solar Cell Recycling Acquisition

Lithium Universe Ltd Completes PV Solar Cell Recycling Acquisition

Melbourne, Australia (ABN Newswire) - Lithium Universe Limited (ASX:LU7,OTC:LUVSF) (FRA:KU00) (OTCMKTS:LUVSF) is pleased to announce that further to its announcements dated 18 June 2025 and 2 July 2025, it has successfully completed the acquisition of 100% of the issued capital New Age Minerals Pty Ltd (NAM) which is party to an exclusive licensing agreement with Macquarie University in respect to patented photovoltaic (PV) solar panel recycling technology known as Microwave Joule Heating Technology (the Acquisition).

Highlights

- Completion of the acquisition of 100% of the issued capital of New Age Minerals Pty Ltd

- Acquisition gives Lithium Universe exclusive rights to patented photovoltaic (PV) solar panel recycling technology known as Microwave Joule Heating Technology

Further details regarding the Microwave Joule Heating Technology are set out in the Company's announcement dated 18 June 2025.

Commenting on the Acquisition, Lithium Universe's Executive Chairman, Iggy Tan said:

"We are pleased to have completed this important milestone, which now allows us to begin working more closely with the Macquarie University team. This next phase will focus on developing a robust research program to enhance the Microwave Joule Heating Technology and unlock its full commercial potential. We believe this collaboration will play a pivotal role in advancing sustainable recycling solutions and position Lithium Universe as a leader in critical metal recovery from end-of-life solar panels."

 

About Lithium Universe Ltd:  

Lithium Universe Ltd (ASX:LU7,OTC:LUVSF) (FRA:KU00) (OTCMKTS:LUVSF) is a forward-thinking company on a mission to close the "Lithium Conversion Gap" in North America and revolutionize the photovoltaic (PV) solar panel recycling sector. The company is dedicated to securing the future of green energy by addressing two major strategic initiatives: the development of a green, battery-grade lithium carbonate refinery in Quebec, Canada, and pioneering the recycling of valuable metals, including silver, from discarded solar panels.

 

 

Source:
Lithium Universe Ltd

News Provided by ABN Newswire via QuoteMedia

Keep reading...Show less
VIDEO: Lithium Universe Ltd  Interview with Executive Chairman Iggy Tan

VIDEO: Lithium Universe Ltd Interview with Executive Chairman Iggy Tan

Melbourne, Australia (ABN Newswire) - In an interview with ABN Newswire, Lithium Universe Ltd (ASX:LU7,OTC:LUVSF) (OTCMKTS:LUVSF) Executive Chairman Iggy Tan outlines the current activities of the company including the vision of closing the "Lithium Conversion Gap".

Additionally, the company has recently licensed to acquire technology from Macquarie University for the extraction of silver from solar cells. The technique involves a specialised process to delaminate the components in the PV cell and avoid the crushing of the cell for recycling.

This method provides a cleaner disaggregation of the materials in the cell and enables the liberation of critical materials and a significant amount of silver. Silver is a component in the manufacture of PV cells, and with an estimated amount of 80 million tonnes of solar cell waste globally, typically dumped, the process facilitates easy recovery of these valuable materials.

To Watch the Interview with Mr. Iggy Tan, please visit:
https://www.abnnewswire.net/lnk/2HQJB3QO

 

About Lithium Universe Ltd:  

Lithium Universe Ltd (ASX:LU7,OTC:LUVSF) (FRA:KU00) (OTCMKTS:LUVSF) is a forward-thinking company on a mission to close the "Lithium Conversion Gap" in North America and revolutionize the photovoltaic (PV) solar panel recycling sector. The company is dedicated to securing the future of green energy by addressing two major strategic initiatives: the development of a green, battery-grade lithium carbonate refinery in Quebec, Canada, and pioneering the recycling of valuable metals, including silver, from discarded solar panels.

 

 

Source:
Lithium Universe Ltd

News Provided by ABN Newswire via QuoteMedia

Keep reading...Show less

Latest Press Releases

Related News

×