Galena Mining

Abra Production and Operations Update

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that production numbers achieved in October (subject to final reconciliation) show continual improvement and ramp-up progress at its Abra Base Metals Mine (“Abra”). In October, Abra achieved new record highs for overall mining and processing rates, and successful despatch of the mine’s seventh high-grade lead-silver concentrate shipment.


HIGHLIGHTS

  • October concentrate shipment was largest high-grade lead-silver concentrate shipment to date of ~10kt generating ~A$19.0 million revenue (loaded and despatched 5-7 November).
  • The following has been achieved in October (subject to final reconciliation):
    • New monthly record total ore milled of over 117kt (i.e., >1.4Mtpa implied annualised production rate compared to previous steady-state guidance of 1.3Mtpa).
    • New monthly record total material movement with ore and waste mined of over 150kt (high grade ore 105kt including 71kt from stope production).
    • During October the mine set multiple daily production records, including 4,593t of ore processed (~1.7Mtpa rate compared to previous steady-state guidance of 1.3Mtpa), 383t of concentrate produced (~140ktpa rate), 36m of development (~1,080m per month rate), 3,844t stoping production (~115kt per month rate) and 4,650t of total ore mined (~1.7Mtpa rate compared to previous steady-state guidance of 1.3Mtpa).
    • Underground development of ~750m (compared to September 2023 quarter monthly average of 713m) showing continued progress to our near-term 800-850m per month target.
  • December quarter mining and processing plans reaffirmed following October’s mining and production performance:
    • Processing over 320,000t of ore.
    • Lead concentrate shipments of approximately 25-30kt.
    • Mining over 2,400m of development and over 260,000t of stope ore.
    • Forecast group cash balance as at 31 December 2023 of A$15-25 million (after first Taurus debt repayment of ~A$7.0 million in December and finance costs), i.e., forecast positive all- in cash flow of A$8-18 million before taking into account the ~A$7.0 million debt repayment.
  • Detailed technical work is currently underway to look at 2024 production targets, with strong confidence based on ongoing ramp-up that Abra can comfortably exceed the previous mature steady-state target of 1.3Mtpa without material incremental capital expenditure. Planning underway to continue ramp-up towards 1.5Mtpa steady-state level.
Managing Director, Tony James commented, “Abra continues to set new monthly production records as ramp-up continues. Following October’s mining and processing performance we are well on track to meet our guidance for the December quarter. This will allow us to achieve our 31 December 2023 forecast group cash balance of A$15-25 million after accounting for the first Taurus debt repayment.

More importantly, we continue to see scope for continued ramp-up beyond the original 1.3Mtpa target without material capital expenditure and planning is underway to continue ramping-up towards a production running rate in the order of 1.5Mtpa, which we expect to be achieved during 2024.

Figure 1 – Vessel “CORETALENT OL” containing Abra’s seventh lead-silver concentrate shipment at Geraldton Port bound for Qinzhou, China

Figure 2 – Qube Logistics Services transferring the RotaboxTM containers to the ship for unloading. Once inside the ship’s hold, the lifting mechanism rotates the container to place the concentrate in the hold(photo 7 November 2023).


Click here for the full ASX Release

This article includes content from Galena Mining, licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.


G1A:AU
Galena Mining

Galena Mining Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

The Conversation (0)
Galena Mining (ASX:G1A)

Galena Mining


Keep reading...Show less
Galena Mining

Abra Construction At 97% Complete – First Ore Stockpiled For January Processing

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 97% complete as of 30 November 2022. Processing plant commissioning is progressing quickly with practical completion now expected in December 2022. Ore currently being mined from underground is being stockpiled in readiness for processing to begin in January 2023. Concentrate production will commence January 2023.

Keep reading...Show less
Galena Mining

Abra Construction At 92% Complete – Reaches First Ore Underground

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 92% complete as of 31 October 2022. Underground mine has reached the first ore (see ASX announcement 14 November 2022) and plant commissioning continues in several key areas with the project focussed on achieving first concentrate production in Q1 2023.
Keep reading...Show less
Galena Mining

Abra Mine Reaches Ore

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the underground development at its Abra Base Metals Mine (“Abra” or the “Project”) has reached the Abra orebody. Commissioning has commenced in several key areas of the processing facility and the Power Station (Pacific Energy) completed full integration of the hybrid gas/solar/battery energy storage system (BESS) power station on 10 November. The project remains on track for first concentrate production in Q1 2023.
Keep reading...Show less
Galena Mining

Galena Mining Activities Report For Quarter Ended 30 September 2022

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) reports on its activities for the quarter ended 30 September 2022 (the “Quarter”), primarily focused on construction of its 60%- owned Abra Base Metals Mine (“Abra” or the “Project”) located in the Gascoyne region of Western Australia.

Keep reading...Show less
EMU NL

Investor Presentation Fiery Creek Georgetown

EMU NL (ASX: EMU) (“EMU” or “the Company”) is pleased to present its investor presentation.
Keep reading...Show less
Augustus Minerals

EIS Grant for Minnie Springs Copper Porphyry Drilling

Augustus Minerals (ASX: AUG; “Augustus” or the “Company”) is pleased to advise the grant of a co-funded EIS drilling grant of up to $110,000 for the Minnie Springs Cu-Mo project in the Gascoyne Region. Augustus thanks the State Government and DEMIRS for supporting exploration in Western Australia with these grants.

Keep reading...Show less
EMU NL

Quarterly Activity Report 31 March 2024

EMU NL (ASX: EMU) (“EMU” or “the Company”) is pleased to report on its activities for the quarter ending 31 March 2024.

Keep reading...Show less
Redstone Resources

Quarterly Report for the Period Ending 31 March 2024

Redstone Resources Limited (ASX: RDS) (Redstone or the Company) is pleased to provide its quarterly report for the period ending 31 March 2024 (the Quarter).

Keep reading...Show less
Metals Australia

Metals Australia Quarterly Activities Report - to 31 March 2024

Metals Australia Limited (ASX: MLS) (“Metals Australia”, the “Company” or “MLS”) is pleased to report its activities for the quarter ended 31 March 2024 (“Quarter”):

Keep reading...Show less
Basin Energy Logo

Basin Energy Mining Exploration Entity or Oil and Gas Exploration Entity Quarterly Cash Flow Report

Basin Energy (ASX:BSN) is pleased to announced its mining exploration entity or oil and gas exploration entity quarterly cash flow report.

Keep reading...Show less
Galena Mining

Galena Mining Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

Latest Press Releases

Related News

×