Elixir Energy

Daydream-2 Update

Elixir Energy Limited (“Elixir” or the “Company”) is pleased to provide an update on the preparations for the Daydream-2 appraisal well located in its 100% owned Grandis Gas Project in Queensland’s Taroom Trough.


HIGHLIGHTS

  • Well site and access road civils work completed
  • Water well production casing in place
  • Surface conductor installed prior to rig arrival
  • Well due to spud in first few weeks of November
Construction of the well pad and upgrade of pre-existing access roads for Daydream-2 has now been completed.

The drilling of an on-site water well has been successful, with the target formation encountered at 1,006 metres. This formation initially free flowed, which is a positive sign for water productivity. Production casing has now been cemented in place.

The drilling of the water well provided useful offset geological information, allowing Daydream-2’s surface conductor to be installed in the concrete cellar at the well pad prior to the arrival of the rig. This is an upfront saving of 2-3 days of rig time and associated spread rate costs.

The high pressure rated blow-out preventer (BOP) that Elixir requested the drilling contractor to procure for the well has arrived in Australia and has now been successfully pressure tested.

The latest advice from Elixir’s drilling contractor SLB (previously known as Schlumberger) is that the contracted rig SLR 185 will be released by its current operator in the first week of November and will be mobilized to the Daydream-2 site immediately thereafter. It will then spud within a week after that.

Conductor set for Daydream-2

Elixir’s Managing Director, Mr Neil Young, said: “The spud of the Daydream-2 well now only a few weeks away, with strong progress being made on all the required fronts to deliver what will be the highest impact well in Elixir’s history. We look forward to providing the market with regular updates on our progress in the weeks and months to come.”


Click here for the full ASX Release

This article includes content from Elixir Energy, licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.

EXR:AU
Elixir Energy

Elixir Energy Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

The Conversation (0)
Elixir Energy

Elixir Energy


Keep reading...Show less
Apollo Minerals Limited

Exploration Update - Visible Gold Intersected at Salanie

Apollo Minerals Limited (ASX: AON) (‘Apollo Minerals’ or ‘the Company’) provides an update on its exploration activities at the Salanie Gold Project (“Salanie”) in Gabon and the Belgrade Copper Project in Serbia. The first round of drilling has now been completed at both projects. Visible gold has been intersected at the A1 Prospect at Salanie, an area that has not seen exploration or modern drilling in 70 years.

Keep reading...Show less
Metal Bank Limited

Wadi Al Junah VMS-Style Copper-Zinc-Gold-Silver Project in Saudi Arabia

Metal Bank Limited (ASX: MBK) (‘Metal Bank’, ‘MBK’ or the ‘Company’) is pleased to announce further details regarding the Wadi al Junah Copper-Zinc-Gold-Silver Project (‘Wadi al Junah’ or ‘the Project’), which has been awarded to Consolidated Mining Company (CMC) following a highly competitive Saudi government exploration licensing Round 6.

Keep reading...Show less
Octava Minerals Limited

Octava to Commence Drilling at Yallalong High-Grade Antimony Project

Octava Minerals Limited (ASX:OCT) (“Octava” or the “Company”), a Western Australia focused explorer of the new energy metals antimony, REE’s, Lithium and gold, is pleased to report that the drill rig is relocating to site at the Yallalong antimony project and will commence drilling this weekend. Drilling will focus on two antimony targets, Discovery and Central, with No.4 and North targets to be drilled in the new year.

Keep reading...Show less
Warriedar Resources

Targeted Exploration Focus Delivers an Additional 471koz or 99% Increase in Ounces, and a Higher Grade for Ricciardo

Warriedar Resources Limited (ASX: WA8) (Warriedar or the Company) is pleased to report on an updated MRE for its flagship Ricciardo Gold Deposit, part of the broader Golden Range Project located in the Murchison region of Western Australia.

Keep reading...Show less
Octava Minerals Limited

Octava Selects Drilling Contractor for its Yallalong Antimony Project in Western Australia

Australian mineral exploration company Octava Minerals (ASX:OCT) has selected the drilling contractor for the exploration work commencing at its 100-percent-owned Yallalong antimony project, according to an article by Business News - Australia. The deal will kick off the company’s 3,000-metre program focused on the Discovery target.

Keep reading...Show less
Australian flag with "economy" and "growth" blocks.

Western Australia Allocates AU$14 Million to Improving Environmental Approval Process

Western Australia's governmentsaid on Monday (November 11) that it is allotting AU$14 million to support the employment of additional staff at the Environmental Protection Authority (EPA) and the Office of the Appeals.

The boost comes in response to the Vogel-McFerran Review commissioned by the government in 2023. It recommended various steps to speed up the state's environmental approval system and secure major projects.

According to the government, employing additional staff will help address existing backlogs and provide faster decisions “without impacting the high standard for protecting WA's unique environment.”

Keep reading...Show less
Elixir Energy

Elixir Energy Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

Latest Press Releases

Related News

×