Global Atomic Continues to Advance the Dasa Project, Including Progressing Financing Options and Positive Engagement with Niger's Mines Minister

 Global Atomic Corporation ("Global Atomic" or the "Company"), (TSX: GLO) (OTCQX: GLATF) (FRANKFURT: G12) today provided an update on its financing and development of the Dasa Uranium Project in the Republic of Niger including:

  • Updates on the approaches made to the Company to finance the development of the Dasa Project and timeline for the approval of the proposed US$295 million debt financing facility led by a US development bank
  • Updates on the recent trip to Niger by President & CEO, Stephen G. Roman , CFO, Rein Lehari, and Chief Technology Officer, Dr. Santiago Faucher

Dasa Uranium Project – Financing Options

To complete the project financing for the development of the Dasa Project, the Company has received several approaches, including:

  • The proposed US$295 million debt financing, led by a U.S. development bank which is advancing to the approval stage;
  • Approaches from a variety of sources for pre-payments on uranium delivery contracts;
  • Approaches for a strategic equity investment into the Company from a number of financial institutions and private equity firms;
  • Approaches for a minority Joint Venture investment at the project level; and
  • Approaches from investment banks for an equity financing.

The Company is actively considering the host of funding options available and intends to advance several of the options in parallel in order to determine the preferred funding structure.

Dasa Uranium Project – Debt Financing

  • The U.S. development bank that will provide the proposed US$295 million debt financing facility for the development of the Dasa Project, has continued to actively make progress and is completing the final documentation to submit to its Credit Committee for approval, which has now been scheduled to take place in mid-July 2024 .
  • With approval at the Committee level, the Company expects final review by the bank's Board of Directors in September.

Global Atomic President and CEO, Stephen G. Roman commented : "We are excited with the prospect of partnering with the U.S development bank. We believe that the advancement of the Dasa Project aligns with the strategic priorities of the United States Government and its efforts to secure uranium supply and reduce dependence on Russia . We believe the U.S. Government recognizes the significance of the Dasa Project and its meaningful contribution to global uranium supply diversification."

Dasa Uranium Project – Recent Site Visit

During the recent visit to Niger , Company executives:

  • Met with several government officials, including the Mines Minister, Commissaire Colonel Ousmane Abarchi , who confirmed his support for Dasa and offered his office's assistance to streamline administrative bottlenecks and offer assistance to facilitate the timely importation of supplies and equipment.
  • Visited the Dasa site to review the progress of the underground development as well as the earthworks being undertaken to prepare for the installation of the processing plant and the associated camp for the construction crew.
  • Witnessed the exemplary safety measures and practices of the SOMIDA team, which has now achieved 675 days without a Lost Time Injury ("LTI").
  • Attended a meeting of the SOMIDA Board of Directors, where our new Board chairman Mr. Abdourazakou Abdou Moumouni, who represents the office of the President of Niger , was appointed. The new Chairman is an experienced mining engineer having worked previously at Orano Mining's Cominak and Somair mines.

Global Atomic President and CEO, Stephen G. Roman commented, "During my most recent trip to Niger , I had the privilege of meeting Niger's Mines Minister. The Government of Niger continues to provide strong support for Dasa, and praised SOMIDA's progress to date, which he witnessed during his site visit in early May."

"At our Dasa Project, I was pleased with the morale, work ethic and progress being made by the mining and site development teams.  From mining to camp construction to site preparation for the plant to equipment maintenance to health and safety to community engagement, the whole team is working well together and making excellent progress."

"The implementation of innovative solutions, such as controlled blasting of large surface rocks to assist the work of the rock-breaking equipment, are accelerating our pace to complete the project on time and on budget. I commend the Dasa team for keeping the project on schedule and for implementing best-practice operating policies to keep the team productive and safe."

"The key area of focus at Dasa is logistics. Hundreds of trucks bearing plant equipment and mining supplies will be arriving at site between now and the end of construction in Q4 2025. The continued closure of the Benin border prevents access to the port of Cotonou, the closest and historically most used ocean port for Niger . While we are having success using other ports, delays can occur from time to time at various points along these extended routes. The government assistance offered to us by the Mines Minister to help expedite our inbound shipments is very much appreciated as the timely importation of materials is critical for Dasa and the realization of the tremendous benefits that Dasa can deliver to our shareholders, the Niger government, its people and further reduce dependance on fossil fuels and electrify the world economy through clean and reliable nuclear energy."

"We look forward to the final approval of our debt facility by the US development bank in Q3 to finance the Dasa processing plant. The debt financing facility will provide 60% of the project funding and 50% of cost overruns, if any. The Company has already invested approximately US$90 million of the required equity portion of the Dasa financing and is well advanced with project development."

Below are photos of Management's recent site visit which are available on the Company's website www.globalatomiccorp.com .

Global Atomic - Management visits Niger's Mines Minister, Colonel Ousmane Abarchi (CNW Group/Global Atomic Corporation)

Global Atomic - Operating Team inspecting the ore face (CNW Group/Global Atomic Corporation)

Global Atomic - Department Heads morning meeting (CNW Group/Global Atomic Corporation)

About Global Atomic

Global Atomic Corporation ( www.globalatomiccorp.com ) is a publicly listed company that provides a unique combination of high-grade uranium mine development and cash-flowing zinc concentrate production.

The Company's Uranium Division is currently developing the fully permitted, large, high grade Dasa Deposit, discovered in 2010 by Global Atomic geologists through grassroots field exploration. The "First Blast Ceremony" occurred on November 5, 2022 , and commissioning of the processing plant is scheduled for Q1, 2026. Global Atomic has also identified 3 additional uranium deposits in Niger that will be advanced with further assessment work.

Global Atomic's Base Metals Division holds a 49% interest in the Befesa Silvermet Turkey, S.L. (BST) Joint Venture, which operates a modern zinc recycling plant, located in Iskenderun, Türkiye. The plant recovers zinc from Electric Arc Furnace Dust (EAFD) to produce a high-grade zinc oxide concentrate which is sold to zinc smelters around the world. The Company's joint venture partner, Befesa Zinc S.A.U. (Befesa) holds a 51% interest in and is the operator of the BST Joint Venture. Befesa is a market leader in EAFD recycling, with approximately 50% of the European EAFD market and facilities located throughout Europe , Asia and the United States of America .

Global Atomic - TSX30 - OTC (CNW Group/Global Atomic Corporation)

The information in this release may contain forward-looking information under applicable securities laws.  Forward-looking information includes, but is not limited to, statements with respect to completion of any financings; Global Atomics' development potential and timetable of its operations, development and exploration assets; Global Atomics' ability to raise additional funds necessary; the future price of uranium; the estimation of mineral reserves and resources; conclusions of economic evaluation; the realization of mineral reserve estimates; the timing and amount of estimated future production, development and exploration; cost of future activities; capital and operating expenditures; success of exploration activities; mining or processing issues; currency exchange rates; government regulation of mining operations; and environmental and permitting risks.   Generally, forward-looking statements can be identified by the use of forward-looking terminology such as "plans", "is expected", "estimates", variations of such words and  phrases or statements that certain actions, events or results "could", "would", "might", "will be taken", "will begin", "will include", "are expected", "occur" or "be achieved".  All information contained in this news release, other than statements of current or historical fact, is forward-looking information.   Statements of forward-looking information are subject to known and unknown risks, uncertainties and other factors that may cause the actual results, level of activity, performance or achievements of Global Atomic to be materially different from those expressed or implied by such forward-looking statements, including but not limited to those risks described in the annual information form of Global Atomic and in its public documents filed on SEDAR from time to time.

Forward-looking statements are based on the opinions and estimates of management at the date such statements are made.  Although management of Global Atomic has attempted to identify important factors that could cause actual results to be materially different from those forward-looking statements, there may be other factors that cause results not to be as anticipated, estimated or intended.  There can be no assurance that such statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements.  Accordingly, readers should not place undue reliance upon forward-looking statements.  Global Atomic does not undertake to update any forward-looking statements, except in accordance with applicable securities law.  Readers should also review the risks and uncertainties sections of Global Atomics' annual and interim MD&As.

The Toronto Stock Exchange has not reviewed and does not accept responsibility for the adequacy and accuracy of this news release.

Global Atomic Corporation (CNW Group/Global Atomic Corporation)

SOURCE Global Atomic Corporation

Cision View original content to download multimedia: http://www.newswire.ca/en/releases/archive/June2024/17/c4615.html

News Provided by Canada Newswire via QuoteMedia

GLO:CA,GLATF
The Conversation (0)
GLOBAL ATOMIC PROVIDES DASA PROJECT UPDATE

GLOBAL ATOMIC PROVIDES DASA PROJECT UPDATE

Global Atomic Corporation ("Global Atomic" or the "Company"), (TSX: GLO) (FRANKFURT: G12) (OTCQX: GLATF) is pleased to report on the continuing development of its Dasa Uranium Project in the Republic of Niger .

Stephen G. Roman , President & CEO, stated, " The primary question investors ask is regarding the timing of a term sheet for our banking syndicate's Dasa Project loan facility. While this has been a much longer process than expected, the financing terms are in the final stage of completion, which, upon agreement, will then go to the banks' Boards for approval prior to announcement to our shareholders."

News Provided by Canada Newswire via QuoteMedia

Keep reading...Show less
Global Atomic Announces Q1 2023 Results

Global Atomic Announces Q1 2023 Results

Dasa Uranium Project On Schedule to Produce Yellowcake in Q1 2025

Global Atomic Corporation ("Global Atomic" or the "Company"), (TSX: GLO) (OTCQX: GLATF) (FRANKFURT: G12) announced today its operating and financial results for the quarter ended March 31, 2023 .

News Provided by Canada Newswire via QuoteMedia

Keep reading...Show less
Global Atomic Completes a Second Definitive Agreement to Supply Uranium to a Major North American Utility

Global Atomic Completes a Second Definitive Agreement to Supply Uranium to a Major North American Utility

Global Atomic Corporation ("Global Atomic" or the "Company"), (TSX: GLO) (OTCQX: GLATF) (FRANKFURT: G12) announced today that the Company has formalized its June 2022 Letter of Intent by signing a Definitive Agreement with a major North American utility for their procurement of uranium from the Dasa Project. The agreement represents the supply of up to 2.1 million pounds U 3 O 8 within a multi-year delivery window beginning in 2025, representing about 7% of Dasa's annual production over the period with a revenue potential valued in excess of US$110 million in real terms.

In January 2023 , the Company formalized a similar agreement with another major North American utility for the procurement of Dasa's uranium, representing the supply of 2.4 million pounds U 3 O 8 over a six-year period commencing in 2025, representing a revenue potential of US$140 million in real terms.  In total these two agreements represent revenue potential of over US$250 million .

News Provided by Canada Newswire via QuoteMedia

Keep reading...Show less
Global Atomic Announces 2022 Results

Global Atomic Announces 2022 Results

Dasa Uranium Project On Schedule to Produce Yellowcake in Q1 2025

Global Atomic Corporation ("Global Atomic" or the "Company"), (TSX: GLO) (OTCQX: GLATF) (FRANKFURT: G12) announced today its operating and financial results for the year ended December 31, 2022 .

News Provided by Canada Newswire via QuoteMedia

Keep reading...Show less
Global Atomic Update and Outlook for 2023

Global Atomic Update and Outlook for 2023

Global Atomic Corporation ("Global Atomic" or the "Company"), (TSX: GLO) (OTC-QX: GLATF) (Frankfurt: G12) is pleased to report on operations at its Turkish zinc recycling joint venture and its Dasa Uranium Project in the Republic of Niger .

Turkish Zinc Recycling Joint Venture

News Provided by Canada Newswire via QuoteMedia

Keep reading...Show less
  Boss Energy

Strong Intercepts Confirm Significant Production Potential at Gould’s Dam

Latest results support Boss’ strategy to significantly increase Honeymoon’s annual production capacity and mine life

Boss Energy Limited (ASX: BOE; OTCQX: BQSSF) is pleased to announce high-grade drill results on theGould’s Dam satellite deposit.

Keep reading...Show less
Nuclear Fuels

Nuclear Fuels


Keep reading...Show less
Four nuclear reactors in a field.

ASX Uranium Stocks: 5 Biggest Companies in 2024

Uranium has thrived in recent years, gaining traction in 2020 and 2021 while most of the world was at a standstill due to COVID-19. Prices for the energy fuel have continued to climb since then, sparking optimism for the future.

In 2022, the uranium price began spiking early in the year, reaching US$64.50 per pound in mid-April. This positive trend continued through 2023, when prices rose 87 percent to reach US$90.27 by the end of the year.

Uranium reached its highest level in nearly two decades when values surpassed the US$100 level in February. Since then, prices have contracted, but remain historically high. As of mid-June, values were holding in the US$85.50 range.

Keep reading...Show less
Blocks spelling "M&A" with stock charts in background.

Paladin Energy to Acquire Fission Uranium in C$1.14 Billion Deal

Australia's Paladin Energy (ASX:PDN,OTCQX:PALAF) has announced plans to acquire Saskatchewan-focused Fission Uranium (TSX:FCU,OTCQX:FCUUF) in a transaction valued at C$1.14 billion.

“The acquisition of Fission, along with the successful restart of our Langer Heinrich Mine, is another step in our strategy to diversify and grow into a global uranium leader across the top uranium mining jurisdictions of Canada, Namibia and Australia,” said Paladin CEO Ian Purdy in a press release on Monday (June 24).

Under the terms of the agreement, Paladin will acquire 100 percent of the issued and outstanding shares of Fission, while Fission shareholders will receive 0.1076 fully paid shares of Paladin for each Fission share that they hold.

Keep reading...Show less

NexGen Advances Through Completeness Check for the Final Federal Environmental Assessment Process

NexGen Energy Ltd. ("NexGen" or the "Company") (TSX: NXE) (NYSE: NXE) (ASX: NXG) is pleased to announce that on June 21, 2024 the Canadian Nuclear Safety Commission (" CNSC ") concluded their 30-day completeness check of NexGen's May 21, 2024 submission of responses to the remaining 49 technical review comments and revised Federal Environmental Impact Statement (" EIS ") for NexGen's 100% owned Rook I Project (" Rook I " or the " Project ").

NexGen Energy Ltd. Logo (CNW Group/NexGen Energy Ltd.)

The technical review by the CNSC has now commenced through the Federal-Indigenous Review Team, and upon confirmation that all technical review comments have been resolved after its prescribed 60-day review, the CNSC will then be able to deem the EIS final. When the EIS is deemed final, the CNSC will establish the Federal Commission Hearing date.

Leigh Curyer, NexGen's Chief Executive Officer, commented: "The Company continues to successfully advance through the Federal EA process which formally initiated in April 2019 . We look forward to the conclusion of the technical review process, for the Federal EIS to be deemed final, and the establishment of a Federal Commission Hearing date for the Rook I Project in order to deliver the significant generational benefits to the local Indigenous Nations, communities, the Province and Canada .

With the acceptance of the Federal licence application and receipt of Provincial EA approval in September and November 2023 , respectively – and broad-based support and advocacy from our valued stakeholders and local Indigenous Nation partners and communities – the team is ready to immediately commence major construction of this generational project upon receipt of remaining approvals. The detailed engineering and procurement activities continue along the critical path as do the significant local training programs underway for the future staffing requirements. Rook I represents a crucial clean fuel source that is fully in line with Government of Canada's critical minerals strategy and desire to be a leader in the provision of clean energy solutions including nuclear power and NexGen will be instrumental in global efforts to bring diversified, reliable, carbon-free energy to the world."

About NexGen

NexGen Energy is a Canadian company focused on delivering clean energy fuel for the future. The Company's flagship Rook I Project is being optimally developed into the largest low cost producing uranium mine globally, incorporating the most elite standards in environmental and social governance. The Rook I Project is supported by a NI 43-101 compliant Feasibility Study which outlines the elite environmental performance and industry leading economics. NexGen is led by a team of experienced uranium and mining industry professionals with expertise across the entire mining life cycle, including exploration, financing, project engineering and construction, operations and closure. NexGen is leveraging its proven experience to deliver a Project that leads the entire mining industry socially, technically and environmentally. The Project and prospective portfolio in northern Saskatchewan will provide generational long-term economic, environmental, and social benefits for Saskatchewan, Canada , and the world.

NexGen is listed on the Toronto Stock Exchange, the New York Stock Exchange under the ticker symbol "NXE" and on the Australian Securities Exchange under the ticker symbol "NXG" providing access to global investors to participate in NexGen's mission of solving three major global challenges in decarbonization, energy security and access to power. The Company is headquartered in Vancouver, British Columbia , with its primary operations office in Saskatoon, Saskatchewan .

Cautionary Note to U.S. Investors

This news release includes Mineral Reserves and Mineral Resources classification terms that comply with reporting standards in Canada and the Mineral Reserves and the Mineral Resources estimates are made in accordance with NI 43-101. NI 43-101 is a rule developed by the Canadian Securities Administrators that establishes standards for all public disclosure an issuer makes of scientific and technical information concerning mineral projects. These standards differ from the requirements of the Securities and Exchange Commission (" SEC ") set by the SEC's rules that are applicable to domestic United States reporting companies. Consequently, Mineral Reserves and Mineral Resources information included in this news release is not comparable to similar information that would generally be disclosed by domestic U.S. reporting companies subject to the reporting and disclosure requirements of the SEC Accordingly, information concerning mineral deposits set forth herein may not be comparable with information made public by companies that report in accordance with U.S. standards.

Forward-Looking Information

The information contained herein contains "forward-looking statements" within the meaning of applicable United States securities laws and regulations and "forward-looking information" within the meaning of applicable Canadian securities legislation. "Forward-looking information" includes, but is not limited to, statements with respect to mineral reserve and mineral resource estimates, the 2021 Arrow Deposit, Rook I Project and estimates of uranium production, grade and long-term average uranium prices, anticipated effects of completed drill results on the Rook I Project, planned work programs, completion of further site investigations and engineering work to support basic engineering of the project and expected outcomes. Generally, but not always, forward-looking information and statements can be identified by the use of words such as "plans", "expects", "is expected", "budget", "scheduled", "estimates", "forecasts", "intends", "anticipates", or "believes" or the negative connotation thereof or variations of such words and phrases or state that certain actions, events or results "may", "could", "would", "might" or "will be taken", "occur" or "be achieved" or the negative connotation thereof. Statements relating to "mineral resources" are deemed to be forward-looking information, as they involve the implied assessment that, based on certain estimates and assumptions, the mineral resources described can be profitably produced in the future.

Forward-looking information and statements are based on the then current expectations, beliefs, assumptions, estimates and forecasts about NexGen's business and the industry and markets in which it operates. Forward-looking information and statements are made based upon numerous assumptions, including among others, that the mineral reserve and resources estimates and the key assumptions and parameters on which such estimates are based are as set out in this news release and the technical report for the property , the results of planned exploration activities are as anticipated, the price and market supply of uranium, the cost of planned exploration activities, that financing will be available if and when needed and on reasonable terms, that third party contractors, equipment, supplies and governmental and other approvals required to conduct NexGen's planned exploration activities will be available on reasonable terms and in a timely manner and that general business and economic conditions will not change in a material adverse manner. Although the assumptions made by the Company in providing forward looking information or making forward looking statements are considered reasonable by management at the time, there can be no assurance that such assumptions will prove to be accurate in the future.

Forward-looking information and statements also involve known and unknown risks and uncertainties and other factors, which may cause actual results, performances and achievements of NexGen to differ materially from any projections of results, performances and achievements of NexGen expressed or implied by such forward-looking information or statements, including, among others, the existence of negative operating cash flow and dependence on third party financing, uncertainty of the availability of additional financing, the risk that pending assay results will not confirm previously announced preliminary results, conclusions of economic valuations, the risk that actual results of exploration activities will be different than anticipated, the cost of labour, equipment or materials will increase more than expected, that the future price of uranium will decline or otherwise not rise to an economic level, the appeal of alternate sources of energy to uranium-produced energy, that the Canadian dollar will strengthen against the U.S. dollar, that mineral resources and reserves are not as estimated, that actual costs or actual results of reclamation activities are greater than expected, that changes in project parameters and plans continue to be refined and may result in increased costs, of unexpected variations in mineral resources and reserves, grade or recovery rates or other risks generally associated with mining, unanticipated delays in obtaining governmental, regulatory or First Nations approvals, risks related to First Nations title and consultation, reliance upon key management and other personnel, deficiencies in the Company's title to its properties, uninsurable risks, failure to manage conflicts of interest, failure to obtain or maintain required permits and licences, risks related to changes in laws, regulations, policy and public perception, as well as those factors or other risks as more fully described in NexGen's Annual Information Form dated March 6, 2024 filed with the securities commissions of all of the provinces of Canada except Quebec and in NexGen's 40-F filed with the United States Securities and Exchange Commission, which are available on SEDAR+ at www.sedarplus.com and Edgar at www.sec.gov .

Although the Company has attempted to identify important factors that could cause actual results to differ materially from those contained in the forward-looking information or statements or implied by forward-looking information or statements, there may be other factors that cause results not to be as anticipated, estimated or intended. Readers are cautioned not to place undue reliance on forward-looking information or statements due to the inherent uncertainty thereof.

There can be no assurance that forward-looking information and statements will prove to be accurate, as actual results and future events could differ materially from those anticipated, estimated or intended. Accordingly, readers should not place undue reliance on forward-looking statements or information. The Company undertakes no obligation to update or reissue forward-looking information as a result of new information or events except as required by applicable securities laws .

Cision View original content to download multimedia: https://www.prnewswire.com/news-releases/nexgen-advances-through-completeness-check-for-the-final-federal-environmental-assessment-process-302179503.html

SOURCE NexGen Energy Ltd.

Cision View original content to download multimedia: http://www.newswire.ca/en/releases/archive/June2024/24/c7705.html

News Provided by Canada Newswire via QuoteMedia

Keep reading...Show less
Gladiator Resources Limited

Drilling Update for Mkuju Project

Gladiator Resources Ltd (ASX: GLA) (Gladiator or the Company) is pleased to announce that drilling at the Mkuju Project is progressing well. Highly mineralized intervals are observed in the core close to surface in 2 holes of the 4 completed. After the 5th hole the rig will commence drilling at the nearby Mtonya area to follow-up on the excellent historical intersections along the northwest side of the deposit which appears to be ‘open’. At the Likuyu North deposit, a 370 line-km ground magnetic survey is nearing completion – the data will guide the drill targeting aimed at identifying potential extensions or new zones.

Keep reading...Show less

Latest Press Releases

Related News

×