Mines Management Inc. (TSX:MGT,NYSE:MGN) released its financial and operating results for the third quarter, which ended on September 30th, 2013. The Final Environmental Impact Statement is advancing, and the 404 Permit to be issued by the U.S. Army Corps of Engineers advanced with a detailed mitigation plan sent to the U.S. Environmental Protection Agency (EPA), USFS, and Montana Dept. of Environmental Quality for review. The Biological Consultation between the U.S. Fish and Wildlife Service and the U.S. Forest Service also continued during the third quarter, which resulted in the completion of an internal working draft of the Biological Opinion for aquatics and terrestrial species.

 Mines Management Inc. (TSX:MGT,NYSE:MGN) released its financial and operating results for the third quarter, which ended on September 30th, 2013. The Final Environmental Impact Statement is advancing, and the 404 Permit to be issued by the U.S. Army Corps of Engineers advanced with a detailed mitigation plan sent to the U.S. Environmental Protection Agency “EPA”, USFS, and Montana Dept. of Environmental Quality for review. The Biological Consultation between the U.S. Fish and Wildlife Service and the U.S. Forest Service also continued during the third quarter, which resulted in the completion of an internal working draft of the Biological Opinion for aquatics and terrestrial species.

As quoted in the press release:

Overview Third Quarter 2013

  • The Biological Consultation between the U.S. Fish and Wildlife Service (“USFWS”) and the U.S. Forest Service (“USFS”) continued during the third quarter and resulted in the completion of an internal working draft of the Biological Opinion (“BO”) for aquatics and terrestrial species.
  • The 404 Permit to be issued by the U.S. Army Corps of Engineers (“USACE”) advanced with a detailed mitigation plan sent to the U.S. Environmental Protection Agency “EPA”, USFS, and Montana Dept. of Environmental Quality (“MDEQ”) for review. Comments on the mitigation plan were received during the third quarter and supplemental information and design details are being prepared to address the comments.
  • The Final Environmental Impact Statement (“EIS”) is advancing with numerous sections already complete in draft form. The agency contractor responsible for writing the Final EIS, has provided the agencies with a draft and comments are being incorporated into the final version.