Indonesian Smelters May Take Five Years to Build

The West Australian reported that at a WA Mining Club lunch yesterday, David Moore, founder of Mincor Resources NL (ASX:MCR), said it could take up to five years for nickel smelters to be built in Indonesia.

As quoted in the market news:

‘Firstly, it can only start happening once people are convinced the ban will stay in place – you don’t want to be half way through a billion-dollar construction to find you’ve lost your market.

‘Very little has actually started and the numbers I’m hearing is three years and $2.5 billion to build a 100,000tpa smelter.

‘But they don’t even know really what the costs are going to be. It’s quite difficult and it’s hard to see the smelter capacity currently in China replicated in Indonesia in three years – maybe it’ll take five years.’

Click here to read the full report from The West Australian.

Get the Latest Nickel Investing Stock Information

Get the latest information about companies associated with Nickel Investing delivered directly to your inbox.


By selecting company or companies above, you are giving consent to receive email from those companies. And remember you can unsubscribe at any time.

Equitas Resources (TSXV:EQT; FSE:T6UN) is one of the first junior resource companies in the last 20 years to hold such a large, consolidated land package in the Voisey’s Bay district. With a first-class, experienced team of professionals skilled in raising capital and managing successful exploration projects Equitas Resources has a tight share structure on early stage of nickel focused exploration. Learn more about this world class deposit.

Leave a Reply